Happenings


Weekly Road Construction Report

Thursday, September 09, 2004

I-75 widening project (mm 6 to mm 9) Motorists should be alert to changing conditions. Two lanes in each direction will be maintained throughout construction, with the exception of periodic nighttime or weekend lane closures. Congestion will be evident for several more weeks from the Lee Highway and Bonny Oaks Drive intersection to Jenkins Road to allow grading and installation of the drainage system.

The contractor has tentatively scheduled to shift traffic to the new concrete roadway on I-75 North from Bonny Oaks Drive to the north end of the project on Tuesday night, Sept. 14. To do this, the contractor will close one lane of I-75 North from mile marker 7 to mile marker 9 beginning at 8 p.m. on Tuesday, Sept. 14, and ending at 6 a.m. on Wednesday, Sept. 15. One lane of traffic will be maintained through the work zone.

Motorists may wish to seek an alternate route and, as always, watch for workers in the roadway performing the shift.

This shift will allow the contractor to begin the next phase of the project, consisting of completing the interstate grading and placing final concrete. Several more traffic shifts will be made as the final phases of work progress. Public notifications will be issued as future shifts are planned.

Motorists traveling from Summit to I-75 North must detour to the temporary loop ramp. Signs, as well as a message board, indicating directions to I-75 North have been installed until traffic becomes familiar with the temporary route.

I-75 Enterprise South Interchange (mm 9 to mm 11) The construction of the interchange to Enterprise South has begun. Two lanes in each direction will be maintained throughout construction with the exception of periodic nighttime or weekend lane closures. Motorists should use caution and be alert to changing traffic conditions throughout the work zone.

Currently the contractor is clearing the site and excavation has started. Estimated completion date is December of 2006.

U.S. 127 (SR-8, Market St.) resurfacing project from Martin Luther King Boulevard to 20th Street This project is now complete except for work proposed between 1st Street and 4th Street. Currently, sewer work by the city of Chattanooga is delaying the completion of this final work.

Immediately after the city has completed their work the contractor will schedule to complete this remaining paving work. Estimated completion date is June 2005.

Resurfacing of Broad Street (U.S. 11/41/64/72, S.R. 2) from the Overhead Railroad Bridge to 13th Street and U.S. 11 from the Georgia State Line to Cummings Highway (U.S. 41) The resurfacing project is tentatively scheduled to begin on the evening of Monday, Sept. 13, and work will be performed each night beginning at 7 p.m. and ending at 6 a.m. the following morning.

Currently the contractor is scheduled to maintain a seven-night per week work schedule on this project until it is completed. The estimated completion date is Nov. 30.

Resurfacing of Ringgold Road (U.S. 41/76, S.R. 8) from north of the Georgia State Line to west of Tombras Avenue Preliminary work (lowering of manholes, milling of intersections, installation of traffic detection loops) is tentatively scheduled to begin on this project on the evening of Monday, Sept. 13. All work on this project will be performed each night beginning at 7 p.m. and ending at 6 a.m. the following morning.

Currently the contractor is scheduled to maintain a Monday through Saturday schedule on this project until it is completed, with no work occurring on Sunday evenings. The estimated completion date is Nov. 15.

Highway 153 from I-75 to North of Amnicola Highway. This project is complete pending the contractor addressing the final punchlist items.

SR-319 (Hixson Pike) from Hideaway Lane to Dallas Hollow Road This project is complete pending final inspection and punchlist work.

US-127 (SR-8, Signal Mountain Blvd.) from US-27 (SR-29) to SR-27 (Suck Creek Road) The contractor continues work on this project.

Motorists should be aware of the following potential delays and seek an alternate route.

Mountain Creek Road will be closed to traffic at the intersection of Signal Mountain Road beginning at 7 p.m. on Friday, Sept. 10, and ending at 6 a.m. on Sunday Sept. 12.

Motorists should detour to Runyon Drive, Cross Street or Glendale Drive to bypass the work zone. The road closure is necessary to install storm sewer.

Westbound traffic will be reduced to one lane between Runyon Drive and Mundy Street during non-peak periods each day this week. The temporary lane closure is necessary to install storm sewers.

Russell Avenue will remain closed all week between Signal Mountain Road and Grandview Avenue. The closure is necessary to install curb and gutter. Through traffic should detour around via Glendale Drive, Cross Street or Mountain Creek Road.

Eastbound traffic between Pineville Road and U.S.-27/SR-29 will be reduced from three lanes to two lanes as soon as weather permits. This traffic change is necessary to safely construct proposed changes to facilitate the widening of Signal Mountian Blvd.

Motorists should use caution within the work zone, and be alert for changing traffic conditions.


Weekly Road Construction Report

I-24 resurfacing beginning west of Chattanooga Creek (LM 6.18 / MM 177) to near Crest Rd. (LM 11.35 / MM 183), including bridge deck repair:  The contractor has completed all contract items. The contractor may need either one lane or two lanes closed (only 10 p.m.-5 a.m.) to address punchlist items.  At least one lane of traffic will be maintained at all times.  THP ... (click for more)

Doonby Opening Feb. 24 At Wynnsong 10

The independent film "Doonby" is set to open on Feb. 24 at the Wynnsong 10. The story surrounds a mysterious drifter who arrives in a small Texas town.  Featuring an all-star cast including John Schneider, who made Bo Duke a TV heartthrob during the early 1980s, will play a modern George Bailey; Ernie Hudson (Ghostbusters, Law and Order) Joe Estevez (Soultaker), Robert ... (click for more)

Signs Vandalized At Cummings Cove As Battle With OHV Owners Continues

Two large advertising signs at the Cummings Cove development in Lookout Valley were vandalized Friday. One sign was spray painted with an expletive and another had the word "Aetna" in large letters.  There has been a long-running dispute between owners of Cummings Cove and those who enjoy going up the old Aetna Mountain Road to ride off-highway vehicles. Cummings ... (click for more)

Grohn, Floyd, Marceaux Pick Up For House Contests

Larry Grohn, Richard Floyd and Basil Marceaux are the latest to pick up for state House races. Mr. Grohn picked up papers for House District 30, a seat now held by Vince Dean of East Ridge. Rep. Dean is considering a race for the state Senate. Rep. Floyd picked up for House District 27, which he has long represented. Mr. Marceaux, who has run for a number of offices, ... (click for more)

We Are Blessed To Have Ron Littlefield As Our Mayor

Chattanooga is blessed beyond measure to have Ron Littlefield as our mayor.  It is a total travesty our city has had to endure the long frivolous battle with absolutely  no foundation other than disagreement with policy issues.  It has always been a vendetta directed personally at Mayor Littlefield which, if the "interveners" decide to appeal, will be a proven fact.   ... (click for more)

Roy Exum: The Sadness Of The Recall

Judge Jeff Hollingsworth, his eagle eyes zeroed on the U.S. Constitution and the laws that have been put into place since it was adopted in 1787, ended the recall of Chattanooga Mayor Ron Littlefield Friday afternoon, but the pall of sadness that the effort cast over the city will last for a lot longer. If “time is money,” the whole deal cost us millions of dollars and even more ... (click for more)