Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  




New Hamilton County Marriage Licenses

Here are the new marriage licenses from the County Clerk's office: WILLIAM CLAYTON BATEY                             AMBER JILL WHITE 5000 ST ELMO AVENUE                               8621 HORSESHOE BEND LANE CHATTANOOGA, TN 37409 ... (click for more)

Tennessee National Guard Prepared If Need Arises During Eclipse

From Clarksville to Athens, Tennessee is at the epicenter of next week’s eclipse. With the eclipse comes thousands of visitors, and the Tennessee National Guard is well prepared. Guard Soldiers and Airmen will work with the Tennessee Emergency Management Agency to support local and state authorities as needed.  "This is part of the Guard’s dual mission, we not only fight ... (click for more)

Coolidge Park Crowd Gets Twilight, Cricket Chirping As Solar Eclipse Arrives

A crowd at Coolidge Park and the nearby Walnut Street Bridge got twilight and cricket chirping as the heralded solar eclipse finally arrived at mid-afternoon Monday. As the moon moved across the sun around 2:30 p.m., birds quit chirping and began to roost. Crickets started going full force. Lights on the Market Street Bridge began to flicker on. The event, sponsored by Comcast, ... (click for more)

Chattanooga Airport President Gets New Contract Amid Double-Digit Growth, Improvements

Chattanooga Airport President Terry Hart has been given a six-year extension on his contract amid double-digit passenger increases and a host of airport improvements. There is no increase in his $158,377 pay, but the board plans to put in annual performance reviews with some built-in bonuses. Jim Hall, vice chairman of the Airport Board, said it is also important that the ... (click for more)

Tom Decosimo: My Great-Great-Grandparents Are Buried At The Confederate Cemetery - And Response

To Mayor Berke, I cannot add any more to the very fine comments made in opposition to your empty jester to remove the city as a trustee of the Confederate Cemetery. I can, however, add some personal perspective as my great-great-grandparents are buried there. Penelope McDermott Cooke was a Daughter of the Confederacy and was concerned the remains of the Confederates who ... (click for more)

Roy Exum: The New Mean

Until last Monday I believed nobody could ever hurt my feelings again. In the half-century I have been a writer I’ve had hundreds of people take swipes at me, been called more names, and received more hate mail than you can imagine. I also know the only way anyone can hurt you is for you to allow it and, brother, it is nigh impossible to get inside me. My defense mechanism is because ... (click for more)