Weekly Road Construction Report

Thursday, October 17, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Vehicle Donated To Bradley County Sheriff's Office

Sheriff Eric Watson and Chief Deputy Brian Smith accepted the gift of a free automobile from a Cleveland dealer.  Andy Kiswani, of David Auto Sales on South Lee Highway at Phillips Street, made the donation of a vehicle to the sheriff and chief. Mr. Kiswani said he greatly appreciates the effort made by the Bradley County Sheriff’s Office to keep the community safe, and ... (click for more)

Election Officials In Crockett, Dickson, Hamilton and Rutherford Counties Recognized For Passing Certification Exam

Secretary of State Tre Hargett would like to congratulate four administrators of elections who passed the certification exam on Friday: Lori Lott, Crockett County administrator of elections; Roxanna Hagewood, Dickson County administrator of elections; Kerry Steelman, Hamilton County administrator of elections; and Alan Farley, Rutherford County administrator of elections. ... (click for more)

Chattanooga Police Detective Karl Fields Terminated On Code Of Conduct Charges

Karl Fields, former Chattanooga Police detective, was terminated on Wednesday on code of conduct charges. The Chattanooga Police Department said it received a correspondence from the Hamilton County District Attorney’s Office o n Sept. 4, 2014,  informing it of allegations of inappropriate behavior committed by a CPD investigator during the course of a rape investigation. ... (click for more)

Autopsy Says 5-Year-Old Whitwell Boy Died Of Blunt Force Trauma

An autopsy on five-year-old Lucas Dillon of Whitwell says he died of blunt force trauma. The TBI is investigating the death, which is being treated as a homicide. The child, who lived on Jewell Lane Road, was injured on Saturday and died in a hospital on Monday. Lucas was a student at Whitwell Head Start. (click for more)

Physicians Thank Their Patients On Doctor’s Day

March 30 has been set aside as National Doctors’ Day since 1933 as a time to recognize the contributions made by our physicians. While the recognition is appreciated, our greatest satisfaction comes from caring for our patients.  For 132 years, the Chattanooga-Hamilton County Medical Society has been the physicians’ voice as we worked together to improve health of our community. ... (click for more)

Roy Exum: A Tragedy And A Triumph

Two summers ago there was a 15-year-old boy at Atlanta’s Egleston children’s hospital with two big problems. Doctors had discovered the child had dilated cardiomyopathy and the left ventricle in his heart was failing to pump enough blood. Doctors predicted that without a heart transplant he would only live six to nine more months. His other problem was a court-ordered monitoring ... (click for more)