Weekly Road Construction Report

Thursday, October 17, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



New Hamilton County Marriage Licenses

Here are the new marriage licenses from the County Clerk's office: EDWARD EDMUND GUTKNECHT, II                       JEANNE MARIE GASTRIGHT 258 BEARTOOTH PKWY                                258 BEARTOOTH PARKWAY, SUITE 100 DAWSONVILLE, GA ... (click for more)

Marion County Democratic Party To Hold Yard Sale To Raise Funds For Candidates

The Marion County Democratic Party will be assisting its candidates for local elections this fall by raising funds for their campaigns.   There will be a yard sale in The First Volunteer Bank parking lot in downtown Jasper on Saturday, from  9 a.m.-3 p.m.   In addition to the sale, candidates will be on hand for meet and greets from  ... (click for more)

Stone Domestic Assault Case Postponed Until Aug. 9

The case in which Bobby Stone is charged with domestic assault against his wife, advisor to Mayor Andy Berke Lacie Stone, has been postponed until Aug. 9. Officials said there will be no further action until the TBI completes its investigation.  The case had been set Tuesday morning before general sessions court Lila Statom. The TBI is believed to be looking into ... (click for more)

Chattanooga Honors Military Veterans

A Memorial Day service was held at the National Cemetery on Monday. (click for more)

Calling Out Bad Behavior In St. Elmo

I have lived in the St. Elmo community of Chattanooga for practicially all 52 years of my life. My grandmother moved to St. Elmo in 1919. My Dad was literally born in a home in St. Elmo and lived his entire 72 years in this community and my Mom has lived here 60 years of her life. I am very disappointed in what my neighborhood has become. I like people. ... (click for more)

Don't Squander The 2016 Election Opportunity

This is what I don't understand. Christians refusing to vote for anyone who is not squeaky clean and who doesn't live up to our standards. I'm not bashing Christians. I proudly proclaim Jesus as Lord and Savior.  But If we made our voice known more we could have a lot greater influence than we have. And I don't mean just boycotting. I specifically mean the last two ... (click for more)