Weekly Road Construction Report

Thursday, October 24, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday, the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Also on Wednesday and Thursday, Oct.31, the contractor will close Manning Street under U.S. 27 from 7 a.m.-7 p.m. for bridge demolition.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  




Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County: I-24 East bridge repair over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange and safety improvements on the bridges over the CSX Railroad and over U.S. 27:  Work on this project continues.  This project will repair the bridge on I 24 East over Chestnut Street at mile marker 178.6 near ... (click for more)

12th Annual Boyd-Buchanan Physics Trebuchet And Catapult Competition

Signal Mountain Committee Says Pulling Away From County Schools Is "Feasible"

After eight months of investigating the viability of Signal Mountain establishing a separate school district, a committee of six has determined that it is feasible and would meet the goal of improving the education provided to students. The committee was also tasked with identifying obstacles and if possible to find ways to overcome them.  Results of the report were presented ... (click for more)

Alexander, Corker Are Among Sponsors Of Bill To Stabilize Premiums And Access To Insurance

A group of 24 senators - 12 Republicans and 12 Democrats led by Senate health committee Chairman Lamar Alexander (R-Tenn.) and Ranking Member Patty Murray (D-Wash.) - on Thursday released short-term bipartisan legislation to stabilize premiums and access to insurance in individual health insurance markets. Senators Alexander and Murray said: “We have reached an agreement ... (click for more)

The Deer Decline At Enterprise South Nature Park

There are now 11 fewer deer to see at Enterprise Nature Park. The hunters snuck another one in secretly so as not to cause controversy.   I go to that park three or four times a week, and haven't seen any deer for months, and I used to see them all the time. They had to put out "salt licks" to attract deer from surrounding areas outside the park. Then they killed them ... (click for more)

Roy Exum: New Schools On Agenda

Hamilton County School Superintendent Bryan Johnson confirmed on Wednesday that a plan for several new public schools will be included on Thursday night’s School Board agenda. Hamilton County has fallen woefully behind other metro school districts in the state and, with an estimated $340 million in deferred repairs, upgrading facilities - that now average over 40 years old - was ... (click for more)