Weekly Road Construction Report

Thursday, October 24, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday, the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Also on Wednesday and Thursday, Oct.31, the contractor will close Manning Street under U.S. 27 from 7 a.m.-7 p.m. for bridge demolition.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Chattanooga Police Department Increases DUI Enforcement On Memorial Day Weekend

The Chattanooga Police Department will be partnering with the Tennessee Highway Patrol and other local agencies within Hamilton County to step up DUI enforcement this Memorial Day holiday.  “This is about preventing irresponsible and reckless driving,” said Lieutenant Adrian Gibb of the Chattanooga Police Department's Traffic Division. “We strongly believe highly visible, ... (click for more)

Public Meeting Set June 13 About Whitfield County Hazard Mitigation Plan

Whitfield County will hold a public meeting on June 13 at 9 a.m. at the Whitfield County Emergency Management Office located at 804 Professional Blvd. in Dalton to review and discuss a draft of an update to the Whitfield County Hazard Mitigation Plan. A draft copy of the plan can be found at www.whitfieldcountyga.com for review prior to the meeting. This Plan is required by ... (click for more)

Large Hole Develops In Lane Of I-24 Eastbound Over Chestnut Street; Emergency Repair Undertaken

 A large hole developed in the I-24 eastbound bridge over Chestnut Street in Chattanooga on Sunday evening. Jennifer Flynn of TDOT said, "The hole is such that we are having to close a lane to protect traffic.  This will cause a significant backup in traffic, especially given the holiday.  "This is the same bridge, but different location that we recently did ... (click for more)

12 Lost Hikers Rescued At Rainbow Lake, Edwards Point

Eleven adults and a child were briefly lost at Rainbow Lake and Edwards Point trails on Signal Mountain on Sunday. A 911 call was made at 9:45 p.m. from one of the hikers reporting the group lost sunlight hiking out of the trails at Edwards Point. Th Signal Mountain Fire Department and the Walden's Ridge Emergency Services have responded to the scene to ... (click for more)

Parking Discrimination Downtown

Many taxpayers who reside in Chattanooga (but outside Chattanooga's core) feel left behind when it comes to neighborhood paving, sidewalks, policing, streetscaping, street sweeping, public transportation, and other services. Some think most tax dollars are spent on downtown and not in their neighborhoods. It's not as if they can't vicariously experience the largesse of downtown. ... (click for more)

Roy Exum: One Nameless Ghost

One hundred years ago the United States was at war. The most intense fighting during World War I was on what was called The Western Front. The Germans wanted to invade France from the north and in order to do it, they had to push through Flanders province in Belgium. It has been described as a hell unequalled in raw hand-to-hand combat, In just four months on Flanders fields, ... (click for more)