Weekly Road Construction Report

Thursday, October 24, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday, the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Also on Wednesday and Thursday, Oct.31, the contractor will close Manning Street under U.S. 27 from 7 a.m.-7 p.m. for bridge demolition.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Shirley Keyes Named 2014 Signal Mountain Woman Of The Year

Mrs. Shirley Keyes of Signal Mountain was named at the 2014 Signal Mountain Woman of the Year Wednesday at the annual Signal Mountain Community Guild Dogwood Luncheon.  "This year's recipient was selected because she is an example of volunteerism," said Lara Buchheit, chairman of the Woman of the Year selection committee, as she made the announcement, which is the highlight ... (click for more)

Jenkins Road And Center Street Closed Wednesday And Thursday

The 1400 block of Jenkins Road will be narrowed to one lane for a sewer rehabilitation project.  Flagmen will be onsite to control traffic flow.   Hours of operation are 8:30 a.m. until  4 p.m. on both Wednesday and Thursday.  Flagmen will be onsite to control traffic flow.      The 2300 block of Center Street will ... (click for more)

Catoosa Man Convicted Of Sexual Abuse Of 5 Young Girls Gets Life Plus 250 Years

A Catoosa County man convicted of the sexual abuse of five young girls and possession of child pornography has been sentenced to life plus 250 years. James Martin Ferris, 34, was found guilty after a recent trial. The day after his conviction, Judge Ralph Van Pelt set the sentence. Ferris on June 5, 2013, was indicted by the Catoosa County Grand Jury on 46 counts.   ... (click for more)

Jury Finds Glover Not Guilty Of Attempted Aggravated Robbery

A Criminal Court jury on Tuesday night found 22-year-old Imari Glover not guilty of the charge of attempted aggravated robbery. The trial only lasted several hours, and the panel deliberated about two hours. According to police, Glover and two friends made plans to rob the Moe's Southwest Grill on Gunbarrel Road on Nov. 17, 2010. However, they were stopped by police ... (click for more)

Use The Current Rail System Already In Place - And Response

Why spend $20 million or more on an unproven system to run from the Southside of Chattanooga when we already have the beginnings of a system?  The question apparently has surfaced of why the Choo Choo City doesn't have a rail line. We do have a rail line with the Tennessee Valley RR Museum and their hardware. And they already make runs from the Southside to close to Enterprise ... (click for more)

Roy Exum: Clemson Prayer And Much More

Clemson’s football program, which has won 11 games in each of the past two years and was ranked 8 th in the nation after whipping Ohio State in this year’s Orange Bowl, has just been “blind-sided.” The Freedom from Religion Foundation claims Coach Dabo Sweeney and his staff are doing far too much “to promote Christianity to their student athletes.” Clemson promptly roared back ... (click for more)