Weekly Road Construction Report

  • Thursday, October 24, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is October.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday, the contractor will implement a closure of Signal Mountain Road under the bridge between the ramps to clean bridge beams for the U.S. 27 North exit ramp bridge over Signal Mountain Road from 7 p.m.-6 a.m.  Also on Wednesday and Thursday, Oct.31, the contractor will close Manning Street under U.S. 27 from 7 a.m.-7 p.m. for bridge demolition.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project has begun.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  


Happenings
Mason Keith Earns Eagle Scout Rank
Mason Keith Earns Eagle Scout Rank
  • 4/23/2024

Mason Keith, age 15, has earned the rank of Eagle Scout, the highest rank within the Boy Scouts of America program. He is a member of Troop 224, chartered to Elizabeth Lee Methodist Church in ... more

Children’s Nutrition Program Of Haiti Hosts Walk-A-Thon Mother’s Day Weekend
  • 4/23/2024

For more than 25 years, the Children’s Nutrition Program of Haiti – headquartered in Chattanooga – has been working in Haiti to raise a healthy generation of Haitian children, who can, in turn, ... more

Gallery At Blackwell Announces Summer Show And Opening Reception May 10
  • 4/23/2024

The Photographic Society of Chattanooga will hold a reception at the Gallery at Blackwell on Friday, May 10 from 6-8 p.m. to present the summer show. Refreshments will be provided and the public ... more