Watts Bar Unit 2 Progress Stays On Track

Tuesday, October 29, 2013

Progress on Watts Bar Nuclear Plant’s Unit 2 reactor remains on schedule and on budget more than a year after completion estimates were revised for the critical project, the Tennessee Valley Authority said Tuesday.

TVA released a fifth quarterly update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the 1,100-megawatt unit in April 2012.

The new estimate to complete, or ETC, included additional funding of $1.5 billion to $2 billion, bringing the total cost to complete the unit to the range of $4 billion to $4.5 billion. Estimated completion of Watts Bar 2 was projected between September 2015 and June 2016. The project currently is tracking a most likely completion date of December 2015.

“Performance during the quarter continued to be consistent with the revised ETC and targets for safety, quality, cost and schedule are being met,” said Mike Skaggs, TVA senior vice president for Watts Bar Operations and Construction.

“The work in progress on Unit 2 is being completed according to a detailed plan, and bulk construction is in the final phase,” Mr. Skaggs said. “The plant is approximately 80 percent complete, and we are focusing on completing and readying plant systems for pre-operational testing.”

About 3,300 workers are engaged in the Watts Bar 2 completion project, which will be TVA’s seventh nuclear unit and have the capability to provide enough energy for approximately 650,000 Tennessee Valley homes.

Highlights of the fifth quarter, which covered May-July 2013, include:

  • Safety performance remained strong, with workers achieving more than 21.3 million work-hours without a lost-time accident, dating back to March 2010.
  • The Quality Control Acceptance Rate remained high, with 96 percent of work presented for inspection meeting quality control requirements.
  • Cost and schedule expectations were met.
  • No new risks were identified that might compromise project completion.

Significantly, three operating systems that are required for open vessel testing – the first of five functional tests designed to demonstrate Watts Bar 2 is being built to high standards of quality – were released ahead of schedule from the construction organization for pre-operational engineering tests.

The open vessel testing, which is scheduled for early 2014, involves pumping water through several systems that are used when shutting down the reactor, as well as support for other nuclear operations.

Challenges to completing Watts Bar 2 include completing complex work and required documentation; performing tests on shared Watts Bar Unit 1 and Unit 2 systems without impacting the safe and reliable operations of Unit 1; addressing regulatory and licensing issues, and successfully transitioning the site into dual-unit operation.

“TVA has invested in nuclear power as a key component in generating safe, reliable, carbon-free, low-cost energy,” Mr. Skaggs said. “Completing the Watts Bar 2 project in a safe manner, on time and within budget will validate this investment and the value of using a diverse mix of energy sources to meet the Valley’s electricity needs.”

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


New Hamilton County Businesses

Here are the new business licenses from the County Clerk's office: AAG & ASSOCIATES ANDREA   THOMAS RESIDENTIAL REMODELING SUHRIE RD OOLTEWAH TN 37363 BIG POPPA QUICK MART JAYDEEP  P GANDHI GROCERY STORE 4109 DODDS AVE CHATTANOOGA TN 37407 BLISS OUT HAIR SALON MADELEINE  TOUTOUTE HAIR BRADING AND STYLING 3715 CLEIO AVE ... (click for more)

State Representative Kevin Brooks Encourages Residents To Utilize Annual Sales Tax Holiday

With the beginning of a new school year right around the corner, State Representative Kevin Brooks is encouraging the families who live in House District 24 to utilize the state’s annual sales tax holiday to save on items such as clothing, school and art supplies, as well as computer purchases.   The state’s annual Tax Free Weekend is set for July 28-30. It begins at 12:01 ... (click for more)

3 Hikers Missing In Big Soddy Creek Gulf Area Are Found Safe

Three hikers missing since Sunday afternoon at Big Soddy Creek Gulf have been found safe. They left around noon, and were supposed to return around 6 p.m. The hikers are a married couple and their friend. They are avid hikers. Crews with the Soddy Daisy Police and Fire Departments began searching at daybreak on Monday. (click for more)

Pair Arrested In Connection With Lookout Mountain Vehicle Thefts, Break-Ins

Police on Lookout Mountain said two arrests have been made tied to the theft of  two vehicles stolen from a home in Lookout Mountain, Ga., last week.   In connection to the vehicle thefts, seven other vehicles were entered and several items were stolen. Lookout Mountain, Ga., Chief Todd Gann said, "Early  Wednesday  morning, a Georgia resident noticed ... (click for more)

Do Something To Protect Our Children

It is unconscionable in this day and age that these children had to exist in such deplorable conditions and that an innocent baby suffered and died alone in a locked car.  Yes, there is blame and accountability considering this family had child neglect charges filed a few years ago (that were apparently dropped and expunged) and a large part of the responsibility should ... (click for more)

Roy Exum: Not Many Know This

The best story of the summer – by far – came out of Panama City over the Fourth of July weekend when over 80 total strangers on a Panama City beach responded to screams. Two boys, ages 14 and 11, were caught in a rip tide and all of these “angels” quickly formed a human chain -- over 80 people with their arms locked -- to stretch out in the water, reach those kids and tug them out ... (click for more)