Watts Bar Unit 2 Progress Stays On Track

Tuesday, October 29, 2013

Progress on Watts Bar Nuclear Plant’s Unit 2 reactor remains on schedule and on budget more than a year after completion estimates were revised for the critical project, the Tennessee Valley Authority said Tuesday.

TVA released a fifth quarterly update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the 1,100-megawatt unit in April 2012.

The new estimate to complete, or ETC, included additional funding of $1.5 billion to $2 billion, bringing the total cost to complete the unit to the range of $4 billion to $4.5 billion. Estimated completion of Watts Bar 2 was projected between September 2015 and June 2016. The project currently is tracking a most likely completion date of December 2015.

“Performance during the quarter continued to be consistent with the revised ETC and targets for safety, quality, cost and schedule are being met,” said Mike Skaggs, TVA senior vice president for Watts Bar Operations and Construction.

“The work in progress on Unit 2 is being completed according to a detailed plan, and bulk construction is in the final phase,” Mr. Skaggs said. “The plant is approximately 80 percent complete, and we are focusing on completing and readying plant systems for pre-operational testing.”

About 3,300 workers are engaged in the Watts Bar 2 completion project, which will be TVA’s seventh nuclear unit and have the capability to provide enough energy for approximately 650,000 Tennessee Valley homes.

Highlights of the fifth quarter, which covered May-July 2013, include:

  • Safety performance remained strong, with workers achieving more than 21.3 million work-hours without a lost-time accident, dating back to March 2010.
  • The Quality Control Acceptance Rate remained high, with 96 percent of work presented for inspection meeting quality control requirements.
  • Cost and schedule expectations were met.
  • No new risks were identified that might compromise project completion.

Significantly, three operating systems that are required for open vessel testing – the first of five functional tests designed to demonstrate Watts Bar 2 is being built to high standards of quality – were released ahead of schedule from the construction organization for pre-operational engineering tests.

The open vessel testing, which is scheduled for early 2014, involves pumping water through several systems that are used when shutting down the reactor, as well as support for other nuclear operations.

Challenges to completing Watts Bar 2 include completing complex work and required documentation; performing tests on shared Watts Bar Unit 1 and Unit 2 systems without impacting the safe and reliable operations of Unit 1; addressing regulatory and licensing issues, and successfully transitioning the site into dual-unit operation.

“TVA has invested in nuclear power as a key component in generating safe, reliable, carbon-free, low-cost energy,” Mr. Skaggs said. “Completing the Watts Bar 2 project in a safe manner, on time and within budget will validate this investment and the value of using a diverse mix of energy sources to meet the Valley’s electricity needs.”

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Develop CENTS Hosts Ribbon-Cutting Ceremony

IT startup Develop CENTS will celebrate the opening of their 6110 Shallowford Road location with a ribbon-cutting ceremony on Thursday, Aug. 4 from 10-11 a.m. Founded in 2013, the company specializes in providing IT support and web hosting to nonprofits and small businesses. Officials said their expansion, including a new office space and an addition to the staff, will allow ... (click for more)

HHM Certified Public Accountants Promotes 22

HHM CPAs, the largest locally owned accounting firm, promoted 22 professionals within the firm.  Senior manager promotions include Jon Paul Davis, Adam Osborne and Branden Wilson.  Manager promotions include: Blake Bennett, Will Clegg, Chad Goodman, Chelsea Tackett Garcia, Zach Hutcherson, Tammy Jacobs, Josh Jolley, Robert Malone and Sydney Zumbrun.  Supervisor ... (click for more)

$30 Million Development Planned At King And South Market; Will Include Hotel, Condos, Offices, Retail, Possible Restaurant

A new $30 million development is planned for the Southside at King Street and South Market. Nick Wilkinson, city deputy director for economic development, said it will include a hotel, condos, offices, retail and possibly a restaurant. It could also include some light industry. A storage building and a parking lot are now at the site. He said the developers plan to reuse ... (click for more)

DA's Office Defends Suspended Sentence In School Bus Driver Rape Case

The District Attorney's Office defended a controversial suspended sentence in a rape case involving a substitute county school bus driver. Prosecutor Jason Demastus said the victim, who was 15 years old at the time of the March 2015 incident, was in agreement on the plea and refused to testify against Alexander Rodriquez. Rodriguez, 34, last Thursday pleaded guilty to ... (click for more)

Make America Good Again - And Response

“No people can be great, who have ceased to be virtuous.”   Samuel Johnson (1709 – 1784) Last week I witnessed first hand the 2016 Republican National Convention in Cleveland, Ohio. As I observed the happenings within the Quicken Arena, the one theme that continued to pop up again and again, was  Make America Great Again .  Of course, that being ... (click for more)

Roy Exum: Keep Mike Carter’s Genius

Mike Carter, who has just been chosen as the “Best Overall” member of the Tennessee Legislature by a group known as the Tennessee Forum and “Legislator of the Year” by Citizens for Home Rule, is truly both. A lawyer and then a Sessions Court judge for 8 ½ years, he is overwhelmingly favored to win a third term during next Thursday’s election and rightly so. While it is laudable ... (click for more)