Watts Bar Unit 2 Progress Stays On Track

Tuesday, October 29, 2013

Progress on Watts Bar Nuclear Plant’s Unit 2 reactor remains on schedule and on budget more than a year after completion estimates were revised for the critical project, the Tennessee Valley Authority said Tuesday.

TVA released a fifth quarterly update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the 1,100-megawatt unit in April 2012.

The new estimate to complete, or ETC, included additional funding of $1.5 billion to $2 billion, bringing the total cost to complete the unit to the range of $4 billion to $4.5 billion. Estimated completion of Watts Bar 2 was projected between September 2015 and June 2016. The project currently is tracking a most likely completion date of December 2015.

“Performance during the quarter continued to be consistent with the revised ETC and targets for safety, quality, cost and schedule are being met,” said Mike Skaggs, TVA senior vice president for Watts Bar Operations and Construction.

“The work in progress on Unit 2 is being completed according to a detailed plan, and bulk construction is in the final phase,” Mr. Skaggs said. “The plant is approximately 80 percent complete, and we are focusing on completing and readying plant systems for pre-operational testing.”

About 3,300 workers are engaged in the Watts Bar 2 completion project, which will be TVA’s seventh nuclear unit and have the capability to provide enough energy for approximately 650,000 Tennessee Valley homes.

Highlights of the fifth quarter, which covered May-July 2013, include:

  • Safety performance remained strong, with workers achieving more than 21.3 million work-hours without a lost-time accident, dating back to March 2010.
  • The Quality Control Acceptance Rate remained high, with 96 percent of work presented for inspection meeting quality control requirements.
  • Cost and schedule expectations were met.
  • No new risks were identified that might compromise project completion.

Significantly, three operating systems that are required for open vessel testing – the first of five functional tests designed to demonstrate Watts Bar 2 is being built to high standards of quality – were released ahead of schedule from the construction organization for pre-operational engineering tests.

The open vessel testing, which is scheduled for early 2014, involves pumping water through several systems that are used when shutting down the reactor, as well as support for other nuclear operations.

Challenges to completing Watts Bar 2 include completing complex work and required documentation; performing tests on shared Watts Bar Unit 1 and Unit 2 systems without impacting the safe and reliable operations of Unit 1; addressing regulatory and licensing issues, and successfully transitioning the site into dual-unit operation.

“TVA has invested in nuclear power as a key component in generating safe, reliable, carbon-free, low-cost energy,” Mr. Skaggs said. “Completing the Watts Bar 2 project in a safe manner, on time and within budget will validate this investment and the value of using a diverse mix of energy sources to meet the Valley’s electricity needs.”

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Unum Appoints David Hill As New AVP Of Aviation

David Hill has joined Unum as assistant vice president of aviation, where he will oversee the company’s corporate aviation team of 13 that is based in Chattanooga. Mr. Hill joins Unum following an 18 year career with Duke Energy in Charlotte, N.C., where he led a fleet of 10 and a team of 42. A veteran, Mr. Hill dedicated 27 years to the U.S. National Guard, and 10 years ... (click for more)

Clint Powell: I Can Do That Myself!

Asking tough questions is sometimes…well…tough! That just makes sense right? However, knowing that tough questions are tough to ask…doesn’t mean they are still not…well...tough! Shoot…I did it again. Captain Obvious on the job. Well, what kind of tough questions are we talking about? There are quite a few I could spend time on. ‘How old are you?’ – ‘How much do you weigh?’ – ‘Is ... (click for more)

Harr Outlines $40 Million Plan For Chattanooga Light Rail System

Outgoing Chamber of Commerce President Ron Harr on Monday outlined a $40 million plan for a Chattanooga light rail system that would serve not only downtown, but also the Airport and the Enterprise South Industrial Park. In a speech to the Chattanooga Engineers Club, Mr. Harr said most cities looking at such an ambitious plan "would be facing costs of over a billion dollars." ... (click for more)

Chattanooga Choo Choo Adding Clubs, Restaurants In $8 Million Renovation

The historic Chattanooga Choo Choo is adding clubs and restaurants in a $7 million renovation, it was announced in front of the South Market Street landmark on Monday morning. The Comedy Catch will be moving from its longtime home in Brainerd and there will be a new 500-person music venue that will be in addition to Track 29. The new venue, managed by Track 29, will feature a ... (click for more)

Senator Bob Corker: An Open Letter To Tennesseans

We are incredibly fortunate to live in a state in which companies worldwide are clamoring to establish a presence. Many attribute it to our pro-business culture, well-prepared workforce, low tax environment, right-to-work policies, and engaged citizenry.  That is why the announcement by Volkswagen to build its midsize sports utility vehicle and establish the South’s ... (click for more)

Roy Exum: Wamp Refuses To Stoop

With less than two weeks before the Aug. 7 th election and the last week of early voting now underway in Hamilton County, Congressional challenger Weston Wamp sounded upbeat and relaxed early yesterday afternoon. “I’m pleased to say that I believe we are right where we need to be … maybe even more than we had hoped.” Wamp, who is challenging two-term incumbent Chuck Fleishmann ... (click for more)