Watts Bar Unit 2 Progress Stays On Track

Tuesday, October 29, 2013

Progress on Watts Bar Nuclear Plant’s Unit 2 reactor remains on schedule and on budget more than a year after completion estimates were revised for the critical project, the Tennessee Valley Authority said Tuesday.

TVA released a fifth quarterly update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the 1,100-megawatt unit in April 2012.

The new estimate to complete, or ETC, included additional funding of $1.5 billion to $2 billion, bringing the total cost to complete the unit to the range of $4 billion to $4.5 billion. Estimated completion of Watts Bar 2 was projected between September 2015 and June 2016. The project currently is tracking a most likely completion date of December 2015.

“Performance during the quarter continued to be consistent with the revised ETC and targets for safety, quality, cost and schedule are being met,” said Mike Skaggs, TVA senior vice president for Watts Bar Operations and Construction.

“The work in progress on Unit 2 is being completed according to a detailed plan, and bulk construction is in the final phase,” Mr. Skaggs said. “The plant is approximately 80 percent complete, and we are focusing on completing and readying plant systems for pre-operational testing.”

About 3,300 workers are engaged in the Watts Bar 2 completion project, which will be TVA’s seventh nuclear unit and have the capability to provide enough energy for approximately 650,000 Tennessee Valley homes.

Highlights of the fifth quarter, which covered May-July 2013, include:

  • Safety performance remained strong, with workers achieving more than 21.3 million work-hours without a lost-time accident, dating back to March 2010.
  • The Quality Control Acceptance Rate remained high, with 96 percent of work presented for inspection meeting quality control requirements.
  • Cost and schedule expectations were met.
  • No new risks were identified that might compromise project completion.

Significantly, three operating systems that are required for open vessel testing – the first of five functional tests designed to demonstrate Watts Bar 2 is being built to high standards of quality – were released ahead of schedule from the construction organization for pre-operational engineering tests.

The open vessel testing, which is scheduled for early 2014, involves pumping water through several systems that are used when shutting down the reactor, as well as support for other nuclear operations.

Challenges to completing Watts Bar 2 include completing complex work and required documentation; performing tests on shared Watts Bar Unit 1 and Unit 2 systems without impacting the safe and reliable operations of Unit 1; addressing regulatory and licensing issues, and successfully transitioning the site into dual-unit operation.

“TVA has invested in nuclear power as a key component in generating safe, reliable, carbon-free, low-cost energy,” Mr. Skaggs said. “Completing the Watts Bar 2 project in a safe manner, on time and within budget will validate this investment and the value of using a diverse mix of energy sources to meet the Valley’s electricity needs.”

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Local Vapor Store Expands; Creates Premium Chattanooga-Inspired EJuices

After opening on June 12, the locally-owned Chattanooga Vapor Company has continued to thrive at its North Shore locations off of Frazier Avenue and in Soddy Daisy, at the corner of Dayton and Thrasher Pike. No matter where one falls within the company’s three-step process, they ensure each individual’s needs are met. Its focus on helping people quit smoking and using tobaccos is ... (click for more)

HTI Employment Solutions Job Fair Draws Over 500 Applicants And Counting

HTI Employment Solutions is holding its first job fair in Chattanooga on Thursday, from 10 a.m.-7 p.m.   at Embassy Suites Hotel at 2321 Lifestyle Way near Hamilton Place Mall. The company was awarded the bid to staff 300 positions created by Tier 1 Automotive Supplier and will staff ... (click for more)

County Schools Have Plan To Put Security Cameras At Every School

The Hamilton County Schools have a plan to put security cameras in every school, Supt. Rick Smith told the County School Board Thursday night. He said the money would come from the $2,201,000 the schools received last year from the sale of the old Ooltewah Elementary School property. The proposal must get approval from the School Board at the December meeting, then from the ... (click for more)

Lookout Mountain, Ga., Raises Sewer Rates; Joins In Kudzu Fight

The Lookout Mountain, Ga., City Council on Thursday night approved an increase in sewer charges. The council approved ordinance 281 increasing sewer rates to $6 per 100 cubic feet of water from the previous rate of $4.77.  The new increase will be in effect in January 2015.    City Manager Brad Haven said the town will be replacing the flow meter for ... (click for more)

Don't Allow Us To Be Overrun By People Who Do Not Belong Here - And Response (5)

Thank you, Senator Corker, for your clear, concise evaluation of the president's attempt to bypass Congress and personally and independently establish national policy that violates our current immigration laws.   Our long-standing failure to enforce our laws to control illegal immigration across our southern border has made this country less safe and ... (click for more)

Roy Exum: ‘Pretty’ Seeking ‘Rich’

The story has been around for a while, long enough for the fact-checking Snopes.com to classify it as a “legend,” which means “great story but lacks validity,” so as we hope Tennessee’s football team can somehow beat 19 th -ranked Missouri in a rough-and-tumble game at Neyland Stadium tonight, allow me to share this because it is delightful just the same. The following is what ... (click for more)