Watts Bar Unit 2 Progress Stays On Track

Tuesday, October 29, 2013

Progress on Watts Bar Nuclear Plant’s Unit 2 reactor remains on schedule and on budget more than a year after completion estimates were revised for the critical project, the Tennessee Valley Authority said Tuesday.

TVA released a fifth quarterly update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the 1,100-megawatt unit in April 2012.

The new estimate to complete, or ETC, included additional funding of $1.5 billion to $2 billion, bringing the total cost to complete the unit to the range of $4 billion to $4.5 billion. Estimated completion of Watts Bar 2 was projected between September 2015 and June 2016. The project currently is tracking a most likely completion date of December 2015.

“Performance during the quarter continued to be consistent with the revised ETC and targets for safety, quality, cost and schedule are being met,” said Mike Skaggs, TVA senior vice president for Watts Bar Operations and Construction.

“The work in progress on Unit 2 is being completed according to a detailed plan, and bulk construction is in the final phase,” Mr. Skaggs said. “The plant is approximately 80 percent complete, and we are focusing on completing and readying plant systems for pre-operational testing.”

About 3,300 workers are engaged in the Watts Bar 2 completion project, which will be TVA’s seventh nuclear unit and have the capability to provide enough energy for approximately 650,000 Tennessee Valley homes.

Highlights of the fifth quarter, which covered May-July 2013, include:

  • Safety performance remained strong, with workers achieving more than 21.3 million work-hours without a lost-time accident, dating back to March 2010.
  • The Quality Control Acceptance Rate remained high, with 96 percent of work presented for inspection meeting quality control requirements.
  • Cost and schedule expectations were met.
  • No new risks were identified that might compromise project completion.

Significantly, three operating systems that are required for open vessel testing – the first of five functional tests designed to demonstrate Watts Bar 2 is being built to high standards of quality – were released ahead of schedule from the construction organization for pre-operational engineering tests.

The open vessel testing, which is scheduled for early 2014, involves pumping water through several systems that are used when shutting down the reactor, as well as support for other nuclear operations.

Challenges to completing Watts Bar 2 include completing complex work and required documentation; performing tests on shared Watts Bar Unit 1 and Unit 2 systems without impacting the safe and reliable operations of Unit 1; addressing regulatory and licensing issues, and successfully transitioning the site into dual-unit operation.

“TVA has invested in nuclear power as a key component in generating safe, reliable, carbon-free, low-cost energy,” Mr. Skaggs said. “Completing the Watts Bar 2 project in a safe manner, on time and within budget will validate this investment and the value of using a diverse mix of energy sources to meet the Valley’s electricity needs.”

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


New Hamilton County Businesses

Here are the new business licenses from the County Clerk's office: A SPINNING WHEEL 7640 GANN RD HIXSON, TN 37343 AMELIAS BOUTIQUE 133 FRAZIER AVE CHATTANOOGA, TN 37405 ANGEL HANDS CLEANING SERVICE 7902 HANDCOCK RD CHATTANOOGA, TN 37406 ANN CURREY FINE ARTS LLC 1401 WILLIAMS ST CHATTANOOGA, TN 37408 ANNS SOULFOOD KITCHEN AND MORE 3504 CLIO ... (click for more)

CBL & Associates Declares Common Stock Dividend And Preferred Stock Dividend

CBL & Associates Properties, Inc. on Friday announced that its Board of Directors has declared a quarterly cash dividend for the company’s Common Stock of $0.265 per share for the quarter ending March 31. The dividend is payable on April 17 to shareholders of record as of March 30.  The Board also declared a quarterly cash dividend of $0.4609375 per depositary share ... (click for more)

2 Homes Totally Destroyed By Fire On Sunday In Separate Blazes

Two homes were totally destroyed by fire in separate blazes on Sunday afternoon. At  5 p.m. , a neighbor called 911 reporting a house fire at 3910 Fairmont Pike on Signal Mountain. Walden's Ridge Emergency Services responded and arrived on the scene reporting a fully involved house fire. A mutual aid response was requested for additional manpower and apparatus ... (click for more)

Signal School Study Says Under Own School System Much More Could Go To The Classroom; Lennon Says Getting Land, Buildings A Major Issue

A panel studying a new school system operated by Signal Mountain concluded that much more money could go directly into the classroom, helping students further increase their potential.   However, County School Board member Kathy Lennon said how the town would be able to acquire the land and buildings is a major issue.   A group of Signal Mountain residents ... (click for more)

CVB Should Share Financials With The Home Folks

The recent debate over the Convention and Visitor's Bureau's funding and budget has gotten ugly. A Hamilton County commissioner has asked questions and made comments about the CVB. The director of the CVB has organized a campaign to dismiss the commissioner's questions and comments. The children on the playground are choosing sides and nothing useful seems to be happening. It's ... (click for more)

Roy Exum: The Eye Of The Storm

There is a very serious building in Norman, Okla., that houses the nation’s Storm Prediction Center for the National Oceanic and Atmospheric Administration and the National Weather Service. According to a Four-Day Forecast released on Sunday, north Alabama and the Chattanooga area are in the middle of the bulls eye for the United States. Yes, it was about 40 degrees and sunny ... (click for more)