Weekly Road Construction Report

Thursday, October 31, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is November.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November. 

U.S. 27 (Rossville Boulevard) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project continues.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November.   

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  




IRONKIDS Chattanooga Fun Run Is Saturday

UnitedHealthcare will sponsor the IRONKIDS Chattanooga Fun Run on Saturday at Ross’s Landing. The UnitedHealthcare IRONKIDS Chattanooga Fun Run gives children ages 3 to 13 the opportunity to run on the same course as Little Debbie IRONMAN Chattanooga presented by McKee A Family Bakery athletes.  The one-mile and half-mile runs are for “triathletes-to-be” and aim ... (click for more)

Vine Street To Be Closed Through End Of Year For Dormitory Construction

Vine Street will be closed between Houston Street and Douglas Street for dormitory construction. The closure will be in place until  Dec. 31 . (click for more)

Firefighters Battle 2-Alarm Apartment Building Fire

More than a dozen people were forced from their homes early Thursday morning when fire broke out in their apartment building.   The Chattanooga Fire Department received the alarm at  2:58 a.m.  and responded to Rainbow Creek Apartments at  7604 Standifer Gap Road  with six fire companies. Seeing a significant amount of fire upon arrival, a ... (click for more)

Lone Survivor Of Lookout Valley Massacre Says He Is 100% Sure Morse Was One Of Shooters; Detective Tells Of Retrieving Guns

The lone survivor of a massacre at a Lookout Valley trailer park on April 9, 2014, testified Wednesday that he is 100 percent sure that Derek Morse was one of the two shooters. Matthew Callam said he was thrown off initially by the fact that Morse had facial hair at the time, but he said when he was shown a recent photo of Morse soon after the incident "it was like I was looking ... (click for more)

Why The Ed Johnson Memorial Matters To Me, A Libertarian

I have seen a lot of responses to the question of whether or not our city and county should financially support the Ed Johnson Memorial at the Walnut Street bridge. Some fully support government pitching in and some say that private individuals and civic organizations should pitch in. Both are correct.  Our city has become a very sought after place to live. From our hometown ... (click for more)

Roy Exum: McQueen & Her TVAAS

If I am reading my Ouija Board right, I suspect the Hamilton County School Board will vote to allow a controversial “partnership” to be formed with the state Board of Education tonight at its monthly meeting. State Education Commissioner Candice McQueen has said she will demand the one-sided partnership to take over the operation of five at-risk schools in Hamilton County and, if ... (click for more)