Weekly Road Construction Report

Thursday, November 21, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Road) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is December.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert and to obey all traffic signs.  The contractor has been addressing a final water line issue on the south side that required the water company to relocate their line before the contractor could complete work in that area.  This has just been done, and after the newly relocated water line is successfully tested, the contractor will be able to continue work in that area.  Even though they could not work in this particular area during the time they were waiting for the water company, they have continued to work on the remainder of the project during this time.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project continues.  The contractor will be paving during this report period.  The contractor will be installing the final striping, raised pavement markings and performing general clean-up during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  


PHOTOS: 2017 National Cornbread Festival

Picnic In The Passageways Happening In Downtown Chattanooga Alleyways This May

Friday afternoons in May will look a little different in select Downtown Chattanooga alleyways this year. Held in two of the Passageways alleys on the 700 block of Cherry Street, Picnic in the Passageways will be every Friday in May from 11:30 a.m.-1:30 p.m. with food trucks, local music, and art projects. The schedule for each Friday is: ... (click for more)

Judge Walter Williams May Go Back On The Bench As Administrative Hearing Officer

One of the city's most colorful judges may go back on the bench. The City Council on Tuesday is set to vote on the nomination of former City Court Judge Walter Williams as administrative hearing officer - a new city position. The law license of the former judge was transferred to disability inactive status in August of 2015 after he suffered a stroke early in the year.  ... (click for more)

Body Believed To Be That Of McCallie Student Jackson Standefer Recovered In Colorado River

A body believed to be that of a McCallie School student who was swept away in a creek in the Grand Canyon was recovered on Friday. The Grand Canyon Regional Communications Center said it was notified by a commercial river trip that they located a body on the Colorado River at River Mile 152. Park rangers responded and recovered the body, which was transported to the rim ... (click for more)

White Coat Syndrome And The Medical System - And Response (2)

Today I wish to share what I am feeling as a patient in our medical system. I am too old to put on airs at this point, and this is too pervasive of a problem for me to contain.   As I enter my AARP years, I am faced with so many medical encounters that evoke all kinds of uncomfortable feelings. I dread physician’s appointments riddled with government regulatory hypocrisy, ... (click for more)

Roy Exum: The Readers Are Right

It is hardly a secret that since I have become intensely interested in public education in Chattanooga, I have tried to read, research and understand how our efforts have fallen horribly short in the last 15 years. We agree we have a crisis on many fronts and I hope it is equally obvious I am desperate for solutions. Much like school board member Karista Jones, I worry that we are ... (click for more)