Weekly Road Construction Report

Thursday, November 21, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Road) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is December.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert and to obey all traffic signs.  The contractor has been addressing a final water line issue on the south side that required the water company to relocate their line before the contractor could complete work in that area.  This has just been done, and after the newly relocated water line is successfully tested, the contractor will be able to continue work in that area.  Even though they could not work in this particular area during the time they were waiting for the water company, they have continued to work on the remainder of the project during this time.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project continues.  The contractor will be paving during this report period.  The contractor will be installing the final striping, raised pavement markings and performing general clean-up during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County: I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan ... (click for more)

NCBW Hosts 17th Annual Black Pioneer Women Of Excellence Awards

The National Coalition of 100 Black Women, Chattanooga Chapter, Inc. will honor three community leaders at its 17th Annual Black Pioneer Women of Excellence Awards Ceremony on Saturday, April 28, at 11:30 a.m. at Hawkinsville Missionary Baptist Church.  This year’s honorees are Dorothy Lee Grisham for achievements in Entrepreneurship; Mildred Moreland for achievements in ... (click for more)

Mayor Berke Plans Affordable Housing Fund, Expansion Of Innovation District; Creation Of Council Against Extremism

Mayor Andy Berke, in his annual State of the City Address on Thursday, said he plans to establishing the city’s first Affordable Housing Fund. He said the city plans to commit $1 million to the fund "that will be used exclusively to aid the creation of affordable and workforce housing throughout Chattanooga. These funds will be used to supplement federal funding, various ... (click for more)

Chattanooga Man Who Was Recently Charged With Murder Is Accused In Another Earlier Shooting

Chattanooga Police have charged Britian Crutcher with the September 2017 shooting of LaSandra Burdette. Ms. Burdette, 26, was shot just after 3 a.m. in the 2000 block of Ocoee Street in Avondale. Her vehicle was involved in a minor wreck just before the shooting. The shooter was in another vehicle. Police recently charged Crutcher in the homicide of 28-year-old ... (click for more)

A Tribute For My Brother – Sgt. Jonathan Gardner, U.S. Army

Seven years ago today, my family and I found out that my brother, Sgt. Jonathan D. Gardner, was seriously injured by a roadside bomb, (explosively formed penetrator - EFP), while on a mission in Kuwait. The EFP went through the bottom of his seat and put a softball size hole in his upper thigh. The doctors said that if the bomb had entered the Humvee an inch to the right, he ... (click for more)

Roy Exum: The Black Telephone

If you have never seen one in an antique store you wouldn’t know that the first telephones were contained in a not-so-small wooden box that had a snout-looking mouth piece and a separate speaker that you would hold on your ear while you talked. This was many years ago when phones were fun as compared to today’s tiny cell phones that rudely interrupt us from the task-at-hand both ... (click for more)