Weekly Road Construction Report

Thursday, November 7, 2013

Here is the weekly road construction report for Hamilton County: 

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is December.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project continues.  The contractor will have lane closures Thursday in both directions to perform striping operations from 7 p.m.-6 a.m.  From Sunday–Wednesday, the contractor will be working on project during daylight hours.  No lane closures will be in place but workers will slow traffic’s speed to stripe project.  THP and/or flaggers will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  Work on project continues.  The contractor will be paving during this report period.  There will be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is November.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Driver Services Division Offers Tennesseans Opportunity To Reissue Driver License

The Tennessee Department of Safety and Homeland Security Driver Services division is offering Tennesseans more ways to reinstate their driver license.  Citizens have the ability to reinstate online, in-person, or via mail.   Once fees have been paid, court clearance documents, and receipts have been received by the Department of Safety Financial Responsibility division ... (click for more)

40th Anniversary Of Cherokee Valley Region Event On Feb. 4

The public is invited to attend the 40th Anniversary of the Cherokee Valley Region of the Antique Automobile Club of America on Saturday, Feb. 4 at 6 p.m. in the Commons of First United Methodist Church, 3425 Ocoee Street North in Cleveland. This is the annual Beans and Cornbread Supper.  Attendees are asked to bring a dish, and their memories of the Cherokee Valley ... (click for more)

City Council Told Cost Has Soared For Moving Sewer Line Off Tubman Industrial Site

City Council members were told on Tuesday that the cost has soared for moving a sewer line completely off the Harriet Tubman industrial site. Bill Payne, city engineer, said it initially was around $1.5 million, but is now pegged at over $4 million. Councilman Chris Anderson, who heads the council's economic development committee, said the assertion brought "stunned looks" ... (click for more)

Report On Tragic School Bus Says Driver Apparently Had Deviated From Normal Route

A preliminary report from the National Transportation Safety Board on a wreck that killed six Woodmore Elementary School students said the bus apparently was off its normal route.   The brief report detailed how the tragic accident happened on curvy Talley Road in Brainerd on Nov. 21.   The report says:   On Monday, November 21, 2016, ... (click for more)

Beyond Freedom Of Speech - And Response

Yes, most people know about the First Amendment to our Constitution, "The right, guaranteed by the First Amendment to the U.S. Constitution, to express beliefs and ideas without unwarranted government restriction."  I being a "deplorable" draw the line when people block traffic, try to disrupt, and even stop an activity through malice and disregard for others. Case being ... (click for more)

Roy Exum: What Else $3 Can Mean

Orchard Knob Middle School, located on North Highland Park Avenue in Chattanooga, led every other secondary school in the state of Tennessee last year with 6.8 percent of its students expelled. So as people are working feverishly to keep the school from being taken over by the state’s Department of Education, allow me to pose a question. Last Friday during the last period of ... (click for more)