Weekly Road Construction Report

Thursday, December 12, 2013

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing paving operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is December.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  On Thursday, from 7p.m.-until midnight the contractor will close Signal Mountain Road between the U.S. 27 entrance and exit ramps to reset portable concrete barrier rail.  Detours will be posted.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is December. 

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

SR-58 resurfacing from north of Eller Road (LM 6.43) to Lakewood Acres Drive (LM 9.20):  The contractor will be working on punch list items during this report period.  There may be temporary lane closures as required on this project.  One lane in each direction will remain open at all times.  Flaggers will be in place to assist with traffic control.  Estimated completion time is December. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Free Meter Parking On Independence Day

The Chattanooga Parking Authority has announced downtown parking meters will not be enforced (and need not be paid) on Monday in honor of the Independence Day holiday. Parking in an unlawful area or manner (bus or loading zones, yellow curb, no parking, handicap space, Fort Wood Residential District, etc.) is enforceable 24 hours / seven days a week. Additionally Bus ... (click for more)

Erlanger Accepting Registrations For Chattanooga Heroes Run/Walk On July 16

The Chattanooga Heroes Run/Walk, presented by Erlanger’s Level One Trauma Center, will take place on Saturday, July 16 beginning at 8 a.m.  The event features a five mile run or walk that begins on Amnicola Highway at the Naval Operational Support Center and Marine Corps Reserve Center, follows part of the path that EMS took last July 16 down Amnicola Highway, connects to the ... (click for more)

County Commission Gives Up Fight On $900,000 In Discretionary Funds

County Commission members have given up the fight for the annual $900,000 in discretionary funds. Commission Chairman Chester Bankston said there was not enough money available after requests from a number of agencies and departments were cut to balance the budget without a tax increase. Commissioner Sabrena Smedley said the fact that commissioners can no longer allot the ... (click for more)

Bridge Repair Over 12th Street To Cause Temporary Lane Closure On US 27

While investigating a pothole in the bridge on U.S. 27 North over 12 th Street in the construction zone, crews discovered a potential weak spot in the bridge deck that could over time result in more damage to the bridge deck.  For the safety of the traveling public, the outside lane in this area will be closed until the contractor makes necessary repairs, TDOT officials ... (click for more)

A Disturbing Trend At Exit 11 - And Response (2)

So, am I the first to notice a trend?   How many wrecks does exit 11 need before anyone asks "whats up with that?"  I have lost count of the wrecks that continue to happen, even after last year's awful loss of life (which I believe 51 percent of the blame should fall on the THP officer on duty).  The problem with this section of interstate are sight lines ... (click for more)

Roy Exum: A Story You Won’t See

In a puzzling time when the big daily newspapers have veered strongly away from “all the news that is fit to print,” allow me to share a story that you very likely will not see on CNN, ABC News, or in the big media conglomerates that influence the way you think, the way you react and – as a result – easily warp our common senses. This story is very true. Late last Sunday afternoon, ... (click for more)