U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing paving operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays-Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is December.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Beginning on Saturday at 7 p.m. until Sunday at 7 p.m. the contractor will close the ramp from Dayton Blvd. to U.S. 27 South to set girders on the nearby bridge.  The closure is necessary because the crane needed to do the work would not allow traffic to pass safely.  It is likely that the contactor will not require the total time period to perform the work, and as soon as the work is completed the ramp will be reopened.  This work is weather permitting.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is December.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


East Brainerd Community Meeting To Be Held Feb. 18

The public is invited to join Commissioner Sabrena Smedley and Councilman Larry Grohn for a community meeting on Thursday, Feb. 18 at 6 p.m. at Morris Hill Baptist Church, 1804 Morris Hill Road.  "We will provide updates on issues affecting our community. We will be joined by three of our state representatives. They will be providing updates as well. I Look forward to ... (click for more)

Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County:  U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  During this report period the contractor will be working on weeknights between 7 p.m.-6 a.m.  To continue work ... (click for more)

County School Board Considers "Best Practices Audit" On Compliance With Board Policies

The County School Board is considering carrying out a "Best Practices Audit" to determine if board policies are filtering down to the school level. Board member Greg Martin said members of the Superintendent's Student Leadership Council told him that only a fraction of students are familiar with board policies on bullying and other topics. Steve Highlander, another board member, ... (click for more)

Several Central City Schools Overcrowded, School Board Is Told

All the county school overcrowding is not out in the fast-growing East Brainerd and Ooltewah sections, school board members were told Thursday. Several central city schools are far above capacity. East Lake Elementary - with 655 students and a capacity of 493 students - is at 133 percent occupancy. Calvin Donaldson, Orchard Knob Elementary and East Side Elementary also are ... (click for more)

Innocent Until Proven Guilty, Even Athletes

From reading Randy Smith's column on the lawsuit against UT it is pretty evident that he never took a legal course in his life. I was under the impression that in this country one was innocent until proven guilty in a court of law. It appears this no longer applies to athletes(particularly black athletes) in the U.S. in 2016. I have always said that if I am picked for jury duty ... (click for more)

Roy Exum: Warmth For Cold Days

I come across all sorts of warm things every day and as we burrow out of sub-freezing temperatures for a day or two, shaking off ice and snow, allow me to share a few things for a change that may take the bite out of the winter wind. This is what helps me. * * * Judy Bellenfant, who has been a soul mate ever since we shared jokes in high school classrooms, sends along this ... (click for more)