The Tennessee Valley Authority reports that work on Unit 2 at Watts Bar Nuclear Plant continues to meet targets for safety, quality, cost and schedule as the project prepares to transition from construction to completing and releasing systems for testing.

TVA issued its third quarterly update on Watts Bar 2 progress since the TVA board of directors last year approved continuing with the construction project in accordance with a revised Estimate to Complete by December 2015 with a projected total cost of $4 billion to $4.5 billion. The update report covers November 2012 through January 2013.              

“The update shows that productivity is aligning with the schedule and the pace of installing commodities, such as miscellaneous steel, electrical conduit, large valves and tubing, is on track to support completion milestones,” said Mike Skaggs, TVA senior vice president for Nuclear Construction.

“The Watts Bar Unit 2 team continued to work safely and to do good work during the quarter,” he continued. “Workers achieved almost 18 million work-hours without a lost-time incident, and the overall acceptance rate of quality control inspections was at 96 percent or better. Cost and schedule performance achieved established goals.”

Most of the commodities remaining to be installed include cables, small valves, instruments, and associated pipes and tubing that make up the operating systems for the unit. As a result, the project is beginning the transition from bulk construction activities to completing systems and releasing them for testing. Mr. Skaggs said work on several systems is being accelerated to find and prevent potential problems early in the completion and testing processes so they won’t impede progress later.

“We have not identified any new short-term issues that compromise project completion, but we recognize there are challenges to completing this unit, with regulatory and licensing issues being our primary challenges,” said Mr. Skaggs.

"TVA has invested in nuclear power as a key component to generating safe, reliable, clean, and low-cost energy,” Skaggs said. “Completing Watts Bar Unit 2 safely, on time and within budget will validate this investment and increase confidence across the industry that building new nuclear is the right course of action in preparing for future energy needs.”

When complete, Watts Bar 2 is expected to generate about 1,100 megawatts, enough electricity to supply about 650,000 Tennessee Valley homes.

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Andrew Puzder Says He Will Fiercely Defend American Workers As Secretary Of Labor

President-Elect Donald Trump announced  on Thursday  he intends to nominate fast-food executive Andrew Puzder as Labor Secretary. On Friday, Mr. Puzder released the following statement on American workers, immigration, and his plans for the Labor Department: "My job as a business person is to maximize profits for my company, employees and shareholders. ... (click for more)

Corker, Alexander Say Water Bill Will Strengthen Tennessee Infrastructure And Commerce

Senator Lamar Alexander said on Saturday the Water Infrastructure Improvements for the Nation (WIIN) Act will help protect business and jobs across the country by authorizing funding to build, repair and maintain the country’s water infrastructure. "Improving locks, dams and other water infrastructure projects is one of the best ways the federal government can help protect ... (click for more)

Tennessee Members Of Congress Urge President To Approve Federal Disaster Assistance For Tennessee Counties

Members of Tennessee’s Congressional delegation on Saturday urged President Obama to quickly approve Governor Haslam’s request for a major disaster declaration for the State of Tennessee to help five Tennessee counties impacted by wildfires and severe weather in November rebuild and recover. “Governor Bill Haslam has submitted a request for Public Assistance and Individual ... (click for more)

Grohn Says Integrity And Ethics Lacking In Berke Administration

Mayoral candidate Larry Grohn criticized controversies and instability coming from the mayor’s administration as a sign of unethical leadership and a lack of integrity. He said, "These scandals lay out the simple fact that it is time for new leadership which is accountable to the people." Councilman Grohn’s criticism comes after the independent auditor’s release of a memorandum ... (click for more)

New School Funding Ideas

After reading the article “County Schools Prepare To Set Priorities For Next Round Of School Building Funding,” I could not help but think about how helpful it would be to have the millions of taxpayer dollars given the owners of Walnut Common apartments to build some new schools.   In case you did not know, since 2008 our elected officials have given away millions in taxpayer ... (click for more)

Roy Exum: John Glenn’s ‘Hero’

When John Glenn became the first man to orbit earth, the timing was perfect. I was 13 years old at the time, in need of a hero, and I latched on to the astronaut tighter than a tick. All of us boys knew he’d flown 150 missions in fighters in World War II and Korea and, believe me, he was “The Right Stuff” long before the great movie about the Mercy 7 daredevils came out about 30 ... (click for more)