Watts Bar Nuclear Plant Unit 2 Progress Remains On Track

Thursday, April 11, 2013

The Tennessee Valley Authority reports that work on Unit 2 at Watts Bar Nuclear Plant continues to meet targets for safety, quality, cost and schedule as the project prepares to transition from construction to completing and releasing systems for testing.

TVA issued its third quarterly update on Watts Bar 2 progress since the TVA board of directors last year approved continuing with the construction project in accordance with a revised Estimate to Complete by December 2015 with a projected total cost of $4 billion to $4.5 billion. The update report covers November 2012 through January 2013.              

“The update shows that productivity is aligning with the schedule and the pace of installing commodities, such as miscellaneous steel, electrical conduit, large valves and tubing, is on track to support completion milestones,” said Mike Skaggs, TVA senior vice president for Nuclear Construction.

“The Watts Bar Unit 2 team continued to work safely and to do good work during the quarter,” he continued. “Workers achieved almost 18 million work-hours without a lost-time incident, and the overall acceptance rate of quality control inspections was at 96 percent or better. Cost and schedule performance achieved established goals.”

Most of the commodities remaining to be installed include cables, small valves, instruments, and associated pipes and tubing that make up the operating systems for the unit. As a result, the project is beginning the transition from bulk construction activities to completing systems and releasing them for testing. Mr. Skaggs said work on several systems is being accelerated to find and prevent potential problems early in the completion and testing processes so they won’t impede progress later.

“We have not identified any new short-term issues that compromise project completion, but we recognize there are challenges to completing this unit, with regulatory and licensing issues being our primary challenges,” said Mr. Skaggs.

"TVA has invested in nuclear power as a key component to generating safe, reliable, clean, and low-cost energy,” Skaggs said. “Completing Watts Bar Unit 2 safely, on time and within budget will validate this investment and increase confidence across the industry that building new nuclear is the right course of action in preparing for future energy needs.”

When complete, Watts Bar 2 is expected to generate about 1,100 megawatts, enough electricity to supply about 650,000 Tennessee Valley homes.

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Northwest Georgia’s Unemployment Rate Rises To 7.7 Percent In June

The Georgia Department of Labor announced today that the unemployment rate in the Northwest Georgia region increased to 7.7 percent in June, up four-tenths of a percentage point from 7.3 percent in May. The rate was 8.9 percent in June a year ago. The rate increased because of seasonal factors, such as the summer job loss among non-contract school workers and a rise in the labor ... (click for more)

Metro Dalton’s Unemployment Rate Rises To 9.3 Percent In June

The Georgia Department of Labor announced that Metro Dalton’s unemployment rate increased to 9.3 percent in June, up five-tenths of a percentage point from 8.8 percent in May. The rate was 11.1 percent in June a year ago. The rate increased because of seasonal factors, such as the summer job loss among non-contract school workers and an increase in the labor force as graduates ... (click for more)

EPB Files With FCC To Expand TV, Phone, Internet Offerings Outside Electric Service Area

 EPB announced Thursday that it has filed a petition to the FCC "in an effort to respond to neighboring communities’ requests for access to the company’s gigabit enabled high-speed Internet service." Officials said, "EPB offers high-speed Internet access, video programming and voice services using a fiber optic communications network that allows the company to deliver these ... (click for more)

Black Creek Developers Say They "Followed The Rules" On $9 Million TIF: To Continue Project

The developers of the Black Creek project at Aetna Mountain said Thursday they "complied precisely by the rules when we applied for and received approval of the TIF district." Doug Stein said the group plans to continue on with the project, which he said earlier would include the creation of a small town on a huge undeveloped tract on the mountain above Black Creek (formerly ... (click for more)

Pickle Ball? - And Response

Collegedale has done some wonderful things for its residents.  The Greenway is a perfect example of money well spent on helping to give her residents the opportunity to improve their lives, at least from a health standpoint. Having taught at Wolftever Creek for a decade plus, I was fortunate to have opportunity to take my classes on walks from time to time.  It provided ... (click for more)

Roy Exum: The NCAA’s “Division IV”

Jonathan Jensen and Brian Turner are two very smart guys. Not long ago the two sports researchers at Ohio State authored a story that appeared in the Journal of Quantitative Analysis in Sports that focused on the most successful college football teams in the country and, earlier this week, a writer named Ben Cohen broke it down in understandable terms for a fascinating Wall Street ... (click for more)