Watts Bar Nuclear Plant Unit 2 Progress Remains On Track

Thursday, April 11, 2013

The Tennessee Valley Authority reports that work on Unit 2 at Watts Bar Nuclear Plant continues to meet targets for safety, quality, cost and schedule as the project prepares to transition from construction to completing and releasing systems for testing.

TVA issued its third quarterly update on Watts Bar 2 progress since the TVA board of directors last year approved continuing with the construction project in accordance with a revised Estimate to Complete by December 2015 with a projected total cost of $4 billion to $4.5 billion. The update report covers November 2012 through January 2013.              

“The update shows that productivity is aligning with the schedule and the pace of installing commodities, such as miscellaneous steel, electrical conduit, large valves and tubing, is on track to support completion milestones,” said Mike Skaggs, TVA senior vice president for Nuclear Construction.

“The Watts Bar Unit 2 team continued to work safely and to do good work during the quarter,” he continued. “Workers achieved almost 18 million work-hours without a lost-time incident, and the overall acceptance rate of quality control inspections was at 96 percent or better. Cost and schedule performance achieved established goals.”

Most of the commodities remaining to be installed include cables, small valves, instruments, and associated pipes and tubing that make up the operating systems for the unit. As a result, the project is beginning the transition from bulk construction activities to completing systems and releasing them for testing. Mr. Skaggs said work on several systems is being accelerated to find and prevent potential problems early in the completion and testing processes so they won’t impede progress later.

“We have not identified any new short-term issues that compromise project completion, but we recognize there are challenges to completing this unit, with regulatory and licensing issues being our primary challenges,” said Mr. Skaggs.

"TVA has invested in nuclear power as a key component to generating safe, reliable, clean, and low-cost energy,” Skaggs said. “Completing Watts Bar Unit 2 safely, on time and within budget will validate this investment and increase confidence across the industry that building new nuclear is the right course of action in preparing for future energy needs.”

When complete, Watts Bar 2 is expected to generate about 1,100 megawatts, enough electricity to supply about 650,000 Tennessee Valley homes.

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.



Heigel Named Chief Operating Officer For Elliott Davis

Catherine Heigel, the former director of the South Carolina Department of Health and Environmental Control, has returned to Elliott Davis, LLC as its chief operating officer.  In this role, Ms. Heigel manages the firm’s operational support functions, including legal, information technology, human resource, marketing and communications, and firm administration. In addition, ... (click for more)

Attorney General Slatery Announces $120 Million Settlement With General Motors

Attorney General Herbert H. Slatery III Thursday announced a $120 million settlement with General Motors Company over allegations GM concealed safety issues related to ignition switch-related defects in GM vehicles.  The settlement, reached between GM and the attorneys general of 49 states and the District of Columbia, concludes a multistate investigation into the auto manufacturer’s ... (click for more)

Signal Mountain Committee Says Pulling Away From County Schools Is "Feasible"

After eight months of investigating the viability of Signal Mountain establishing a separate school district, a committee of six has determined that it is feasible and would meet the goal of improving the education provided to students. The committee was also tasked with identifying obstacles and if possible to find ways to overcome them.  Results of the report were presented ... (click for more)

Alexander, Corker Are Among Sponsors Of Bill To Stabilize Premiums And Access To Insurance

A group of 24 senators - 12 Republicans and 12 Democrats led by Senate health committee Chairman Lamar Alexander (R-Tenn.) and Ranking Member Patty Murray (D-Wash.) - on Thursday released short-term bipartisan legislation to stabilize premiums and access to insurance in individual health insurance markets. Senators Alexander and Murray said: “We have reached an agreement ... (click for more)

The Deer Decline At Enterprise South Nature Park

There are now 11 fewer deer to see at Enterprise Nature Park. The hunters snuck another one in secretly so as not to cause controversy.   I go to that park three or four times a week, and haven't seen any deer for months, and I used to see them all the time. They had to put out "salt licks" to attract deer from surrounding areas outside the park. Then they killed them ... (click for more)

Roy Exum: New Schools On Agenda

Hamilton County School Superintendent Bryan Johnson confirmed on Wednesday that a plan for several new public schools will be included on Thursday night’s School Board agenda. Hamilton County has fallen woefully behind other metro school districts in the state and, with an estimated $340 million in deferred repairs, upgrading facilities - that now average over 40 years old - was ... (click for more)