The Tennessee Valley Authority reports that work on Unit 2 at Watts Bar Nuclear Plant continues to meet targets for safety, quality, cost and schedule as the project prepares to transition from construction to completing and releasing systems for testing.

TVA issued its third quarterly update on Watts Bar 2 progress since the TVA board of directors last year approved continuing with the construction project in accordance with a revised Estimate to Complete by December 2015 with a projected total cost of $4 billion to $4.5 billion. The update report covers November 2012 through January 2013.              

“The update shows that productivity is aligning with the schedule and the pace of installing commodities, such as miscellaneous steel, electrical conduit, large valves and tubing, is on track to support completion milestones,” said Mike Skaggs, TVA senior vice president for Nuclear Construction.

“The Watts Bar Unit 2 team continued to work safely and to do good work during the quarter,” he continued. “Workers achieved almost 18 million work-hours without a lost-time incident, and the overall acceptance rate of quality control inspections was at 96 percent or better. Cost and schedule performance achieved established goals.”

Most of the commodities remaining to be installed include cables, small valves, instruments, and associated pipes and tubing that make up the operating systems for the unit. As a result, the project is beginning the transition from bulk construction activities to completing systems and releasing them for testing. Mr. Skaggs said work on several systems is being accelerated to find and prevent potential problems early in the completion and testing processes so they won’t impede progress later.

“We have not identified any new short-term issues that compromise project completion, but we recognize there are challenges to completing this unit, with regulatory and licensing issues being our primary challenges,” said Mr. Skaggs.

"TVA has invested in nuclear power as a key component to generating safe, reliable, clean, and low-cost energy,” Skaggs said. “Completing Watts Bar Unit 2 safely, on time and within budget will validate this investment and increase confidence across the industry that building new nuclear is the right course of action in preparing for future energy needs.”

When complete, Watts Bar 2 is expected to generate about 1,100 megawatts, enough electricity to supply about 650,000 Tennessee Valley homes.

For a copy of the Quarterly Update to the Watts Bar 2 Estimate to Complete, go to http://www.tva.com/power/nuclear/wattsbar_unit2.htm.


Weaver Named BlueCross Director Of Infrastructure Engineering Services

BlueCross BlueShield of Tennessee has named Jennifer Weaver as director of infrastructure engineering services. She was previously director of the office of the chief information officer for BlueCross. In her new role, Weaver is responsible for the company’s infrastructure engineering teams. She will report to David Marckel, vice president of infrastructure and operations within ... (click for more)

Kingston Ash Recovery Project Nears Completion

The TVA is in the final stages of the Kingston recovery project, fulfilling a promise to restore the area surrounding the Kingston Fossil Plant near Harriman, Tenn. following the coal ash spill in December 2008. A milestone was reached in early December, with the completion of the cover for a 240-acre permanent ash retention landfill. The new landfill, which has been fortified ... (click for more)

Erlanger To Proceed With Manager Bonuses In 2 Steps; Considering Employee Performance Incentive Plan

Erlanger President and CEO Kevin Spiegel said Wednesday night that the hospital plans to proceed with $1.7 million in manager bonuses in two steps. Current participants in the incentive program will receive 50 percent of the approved 2014 performance plan this month. The remaining 50 percent will be paid to the management group in July 2015. At the same time, Mr. Spiegel ... (click for more)

Caldwell Arrested In Rapes Of 2 Women Over 60 In Brainerd, Hixson

Investigators have made an arrest in the rape cases that were reported last weekend. Taken into custody was Derrick Dewayne Caldwell, 30. He is charged with two counts of aggravated rape and two counts of aggravated burglary. Police said two women over 60 years old were raped in Brainerd and in Hixson in separate incidents. (click for more)

A Letter To The NAACP

I believe when a "unarmed" man is evil, he will try to beat a police officer on his head in hopes to knock him out, in hopes to kill him. We saw the bruises on the officer's face.  This evil force tried to take his gun away from him , Proof was in the autopsy.  Why did Michael Brown  try to take his gun away from him? Exactly, to kill the officer.  ... (click for more)

Roy Exum: The Last Day Of School

AUTHOR’S NOTE: This story first appeared in the Chattanooga News-Free Press in the early 1980s and every year since then I have been asked repeatedly about it. It is easily the most famous story I have ever written – copies have been sent to me from numerous foreign countries -- and it may be the easiest story I ever wrote. All I did was write what the noted religious psychologist ... (click for more)