Weekly Road Construction Report

Thursday, May 16, 2013

Here is the weekly road construction report for Hamilton County:

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work continues on this project.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m.  THP will be present to assist with traffic control on the project as necessary.  Estimated project completion is June.   

I-75 North at Exit 3A miscellaneous safety improvements at the northbound off ramp to SR 320 (East Brainerd Road):  Work continues on this project.  The contractor may have short term lane closures as needed.  Flaggers will be on site to help with traffic control.  At least one travel lane will remain open to traffic at all times. Estimated project completion date is May. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  Should inclement weather prevent work from being performed, it will be rescheduled to take place at the earliest possible time.  During nighttime work, at least one lane will remain open in each direction.  Beginning on Friday at 7:30 p.m. and ending by 7a.m. on Saturday morning, the contractor will perform a traffic shift to move traffic to the newly-constructed southbound traffic lanes.  During the traffic shift, the southbound Manufacturer’s Road ramps will require periodic and possibly extended closures during the night to prepare for the new traffic pattern.  Once completed, traffic will shift from the previously-closed Whitehall Road slip ramp to the Manning Street Bridge.  The new southbound entrance and exit ramps at Manufacturer’s Road will also be opened with a new traffic signal in place.  Should inclement weather or unforeseen circumstances prevent this traffic shift from occurring as scheduled, it will be rescheduled to take place as soon as possible.  Overhead signs and message boards will be used to prepare drivers of the impending traffic shift and traffic pattern change as well as to assist with the safety of motorists and construction personnel.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.   

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving: The contractor has installed temporary paving for a detour.  They have 300 ft. of pipe remaining to install, and they are performing grade work on the north side of the project in preparation for permanent paving.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is September.  



Roberts Mill Road Is Now Open

The Hamilton County Public works Department has now completed repair work on Roberts Mill Road and the road is now open to the public. Over the last 30 days work crews have worked to stabilize two sections of Roberts Mill Road totaling about 230 feet. The repair work included cement shotcrete slop stabilization and the installation of self–drilling nails beneath the roadway.  ... (click for more)

North River Civic Center Has Call For Artists

The North River Civic Center invites artists to send their work for consideration in an upcoming exhibit.  The invitational group exhibit will focus on the theme, the North River Wildlife Fine Art Exhibit: Camouflage. The subject of the work should be within the scope of camouflaged animals, bugs, birds, nature, etc.  Any work not within this scope will not be considered ... (click for more)

EPB Says "Close To A Wash" On City Street Light Billing

EPB President Harold DePriest denied Wednesday that EPB owes the city over $1 million on street light billing. He stated,  “EPB has never said that we owe the city $1.2 million. When all the facts are taken into account, the financial difference is close to a wash.” Mr. DePriest said, "I regret that this complicated issue has been oversimplified in some reports. As we’ve ... (click for more)

New Red Bank Zoning Ordinance Is Ready For Review

The new Red Bank zoning ordinance is ready for review, City Manager Randall Smith said Tuesday night. It can be seen on www.redbanktn.gov and the link to zoning regulations. The new ordinance will replace one that was created 30 years ago.    The plan will encompass both residential and commercial development and is intended to direct ... (click for more)

Why So Much For A Rail Study?

From the things that make you go hmm department. Ok, so the feds are giving us $400k and the city is kicking in another $300k for a total of $700k to do a study on having in town rail service. Why so much for a study? Don't get me wrong, I'm totally down with Chattanooga having some passenger trains running around. I get that. It's awesome. We've needed it for a long time. I ... (click for more)

Roy Exum: I’m Certainly No Expert

Sometime on Monday night, after I had written a piece on getting swatted with a switch as a kid, I got an email from ESPN Canada asking if I would be a televised guest on “Off the Record,” the most watched daily sports show in Canada. The subject: corporal punishment in America. Are you kidding me? I am hardly an expert. All weekend my world of sports and its excitement was warped ... (click for more)