Weekly Road Construction Report

Thursday, July 25, 2013

Here is the weekly road construction report for Hamilton County:

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work on this project is complete pending addressing of punchlist items.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m.  THP will assist with traffic control.  

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project has begun.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is September.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the temporary paving on the SB side of the project and the contractor is working on road and drainage on the NB side of the project.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is September.  


American Quilter’s Society Presents AQS QuiltWeek - Chattanooga 2015

American Quilter’s Society, the largest quilting membership organization in the world, announces the return of its popular AQS QuiltWeek event in Chattanooga. The Chattanooga AQS QuiltWeek event will run from Sept. 16-19 at the Chattanooga Convention Center, 1150 Carter S. "More than 12,000 people will converge on the Chattanooga area to enjoy four days of the best in international ... (click for more)

Free Meter Parking Offered On Labor Day

The Chattanooga Parking Authority has announced downtown parking meters will not be enforced (and need not be paid) on Monday, in honor of the Labor Day holiday. Paid parking for all street meters will also be suspended for these remaining holidays in 2015: Thanksgiving Day (Thursday, Nov. 26) Day following Thanksgiving (Friday, Nov. 27) Christmas Day (Friday, ... (click for more)

Local Religious Group Condemns Hammond Comments, Asks Apology

A local religious group, Mercy Junction and Peace Center, has condemned comments by Sheriff Jim Hammond on Muslims and asked for an apology. The group said, " People of all faiths, or of no faith, are invited to join Mercy Junction in front of the Islamic Society of Chattanooga for prayers on Friday afternoon. "Prayers In Solidarity" will take place outside the Islamic ... (click for more)

Sheriff's Office Releases Names Of 4 Deputies Involved In Shooting After Pursuit

The Hamilton County Sheriff’s Office has released the names of the four law enforcement personnel involved in the shooting incident of Brent Pickard on Aug. 26. They are Sgt. Gregg Carson, Sgt. Spencer Daniels, Deputy Adam Ty Williams and Deputy Eric Baxter. As per the sheriff's office policy, all four personnel were placed on mandatory administrative leave and have returned ... (click for more)

Who's Responsible For East Ridge's Stadium? - And Response (2)

There just can be no excuse for East Ridge High School's stadium being in such dangerous condition that it has been condemned.   Where is responsible for this? I know there are a few other stadiums like this as well. And there is no excuse for this.  Building new and beautiful schools, state of the art technology. Top athletic facilities as well. Yet, East Ridge ... (click for more)

Roy Exum: Five Straight Days Of Football

If I covered my first high school football game as a fledging sports when I was 16 years old, and I am now 66, I figure that’s darn near about a half-century of passes and punts. The mystifying part is that I still get as big of a kick hovering around the game as I did on my very first time so as we usher in the start of the college season with five straight days of games, here ... (click for more)