Weekly Road Construction Report

Thursday, January 16, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I-75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  During this report period, the contractor will be installing overhead signs that may require short duration lane closures on the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  If needed during this work, the contractor will open lanes to alleviate any backups that may occur on I-75.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is January.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  On the evenings of Monday through Thursday, from 7 p.m.-6 a.m. the following morning, the contractor will have an inside lane closed on U.S. 27 in each direction from the Olgiati Bridge to Manning Street to set bridge girders over Manning Street.  Manning Street will also be closed during this work between Power Corporation Drive and Winchester Street.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is January.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


Marion County Democratic Party To Hold Yard Sale To Raise Funds For Candidates

The Marion County Democratic Party will be assisting its candidates for local elections this fall by raising funds for their campaigns.   There will be a yard sale in The First Volunteer Bank parking lot in downtown Jasper on Saturday, from  9 a.m.-3 p.m.   In addition to the sale, candidates will be on hand for meet and greets from  ... (click for more)

Another Successful Annual Training For HHB, 1-181st

The soldiers of Headquarters and Headquarters Battery, 1-181st Field Artillery Regiment returned to their home station armory in Chattanooga after completing a successful annual training exercise at Volunteer Training Site – Tullahoma.   During the course of the two week annual training the soldiers of HHB, 1-181st, commanded by CPT Justin G. Woodward and 1SG Danny Duncan, ... (click for more)

Strong Thunderstorm Causes Damage, Power Outages In Dalton

Shortly before  5 p.m. , a strong thunderstorm went through downtown Dalton, knocking down numerous trees, causing power outages and also causing damage. At this time, no injuries have been reported.  The Dalton Fire Department and Dalton Police Department responded to multiple reports of damage. The DPD closed several roads due to downed trees and power lines. ... (click for more)

Chattanooga Honors Military Veterans

A Memorial Day service was held at the National Cemetery on Monday. (click for more)

Calling Out Bad Behavior In St. Elmo

I have lived in the St. Elmo community of Chattanooga for practicially all 52 years of my life. My grandmother moved to St. Elmo in 1919. My Dad was literally born in a home in St. Elmo and lived his entire 72 years in this community and my Mom has lived here 60 years of her life. I am very disappointed in what my neighborhood has become. I like people. ... (click for more)

Don't Squander The 2016 Election Opportunity

This is what I don't understand. Christians refusing to vote for anyone who is not squeaky clean and who doesn't live up to our standards. I'm not bashing Christians. I proudly proclaim Jesus as Lord and Savior.  But If we made our voice known more we could have a lot greater influence than we have. And I don't mean just boycotting. I specifically mean the last two ... (click for more)