Weekly Road Construction Report

Thursday, January 16, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I-75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  During this report period, the contractor will be installing overhead signs that may require short duration lane closures on the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  If needed during this work, the contractor will open lanes to alleviate any backups that may occur on I-75.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is January.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  On the evenings of Monday through Thursday, from 7 p.m.-6 a.m. the following morning, the contractor will have an inside lane closed on U.S. 27 in each direction from the Olgiati Bridge to Manning Street to set bridge girders over Manning Street.  Manning Street will also be closed during this work between Power Corporation Drive and Winchester Street.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is January.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


Chattanooga Fire Department Stations Host Halloween Open Houses

There were some early visitors to the Chattanooga Fire Department’s Halloween Open House Friday afternoon. Ashley Kuehn brought her two kids, dressed in Halloween costumes that had a definite firefighter theme. Daughter Crimson wore a Dalmatian costume while Stetson wore custom-made firefighter turnout gear. The department’s Halloween Open House is officially from 6-8 p.m. on ... (click for more)

Bradley County Mobile Command Post To Be At Downtown Block Party In Cleveland

The Bradley County Mobile Command Post will be at Friday night’s Downtown Block Party in Cleveland. The first 3,000 children to stop by the Command Post, at the northwest corner of the courthouse, will receive a Bradley County Sheriff’s Office re-usable treat bag…filled with candy. Sheriff Watson invites one and all to visit.   (click for more)

Chattanooga Area Under Hard Freeze Warning As Winter Comes Early

The Chattanooga area was under a freeze warning as winter rushed in early. The biting weather came as crew members were about to hit the water for the annual Head of the Hooch at Ross's Landing. Here is the warning: ...FREEZE WARNING IN EFFECT FROM 3 AM EST /2 AM CST/ TO 9 AM EST /8 AM CST/ SUNDAY ... THE NATIONAL WEATHER SERVICE IN MORRISTOWN HAS ISSUED ... (click for more)

Downtown Chattanooga Apartment Complex That Brought $3 Million Profit Exempt From Most Taxes Until 2022 Under PILOT

A downtown Chattanooga apartment complex that recently was sold at a $3 million profit is exempt from most property taxes through 2022 under a PILOT (payment in lieu of taxes) agreement.   No payment of school taxes was included in the deal for Walnut Commons at Walnut Street and Aquarium Way.   The only taxes due on the property for the next eight ... (click for more)

Time To Fix The TIFs

What if Chattanooga policy makers and taxpayers used several recent business announcements as a wakeup call to learn more about how our community decides what companies get property tax breaks? If enough people accept this assignment, it just might result in the adoption of some sound policies and procedures to guide us in the future. We read in the newspapers this week that ... (click for more)

Roy Exum: My Garden In November

As the first day of November arrives today, it is cold enough in my garden to officially certify that fall has fell! There are even signs of ice on the ground but there is a bounty crop of acorns so, in keeping with our monthly tradition, some will get shiny acorns and others will get a chunk of cold ice: A SHINY ACORN for Patriots football coach Bill Belichick for scoffing at ... (click for more)