Weekly Road Construction Report

Thursday, January 16, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I-75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  During this report period, the contractor will be installing overhead signs that may require short duration lane closures on the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  If needed during this work, the contractor will open lanes to alleviate any backups that may occur on I-75.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is January.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  On the evenings of Monday through Thursday, from 7 p.m.-6 a.m. the following morning, the contractor will have an inside lane closed on U.S. 27 in each direction from the Olgiati Bridge to Manning Street to set bridge girders over Manning Street.  Manning Street will also be closed during this work between Power Corporation Drive and Winchester Street.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is January.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  



Board Connector Hosts 10 Connectors You Need To Meet

oard Connector, in partnership with Venture Forward, Latina Professionals of Chattanooga, and the Chattanooga Urban League Young Professionals will host “Ten Connectors You Need to Meet” on Wednesday, June 27, from 5:30-7 p.m. at The Camp House, 149 E. Martin Luther King Blvd. The event will give the community an opportunity to network and connect with the following 10 community ... (click for more)

MainStreet Cruise-In Is June 23

The Mainstreet Cruise-In rolls into downtown on Saturday, June 23 from 1 p.m.-6 p.m. and fills the streets surrounding the Courthouse Square.  Car enthusiasts show off their vehicles as all types of cars are displayed from classics to special interest and current models.   Downtown streets will be filled with vehicles and spectators are invited to view the cars, ... (click for more)

Voters May Decide In November On Whether To Eliminate City Court; Paving Fund Also Considered

Chattanooga voters in November may get to vote on whether City Court should be abolished. City Council members indicated during budget talks on Tuesday that may be an upcoming referendum question. Councilman Jerry Mitchell said he, for one, "would vote to eliminate it." However, he said the court would apparently run through 2021 when the eight-year terms of Judges Sherry ... (click for more)

Riverton Development Spurs Talk Of Riverwalk Along The Northshore

Development of the former BlueCross property at Lupton City is spurring talk of a Riverwalk on the Northshore. The City Council discussed the topic on Tuesday night in giving final approval for a Planned Unit Development for Riverton on 210 acres. Officials said there are no specific plans for a Northshore Riverwalk, but several groups are actively working to make a connection ... (click for more)

Never Replacing Claude Ramsey But Following His Example

When Claude made his decision not to seek reelection as the 26th District state representative I made my intention known to seek the office following him.  Immediately opponents from both parties began to qualify for that opportunity.  With Bill Bennett as my campaign manager and many of Claude’s supporters going door to door into the community, as Claude had done in his ... (click for more)

Roy Exum: Please ‘Connect The Dots’

Get your crayons out and let’s play “connect the dots.” Next Thursday (June 28 th ) the Tennessee Educational Equity Coalition, in partnership with Chattanooga’s publicly-flawed non-profit educational foundation, UnifiEd, will hold its regional meeting at Chattanooga’s Bessie Smith Hall. The coalition was formed to advocate for “students of color” in Tennessee, and among those on ... (click for more)