Weekly Road Construction Report

Thursday, January 16, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I-75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  During this report period, the contractor will be installing overhead signs that may require short duration lane closures on the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  If needed during this work, the contractor will open lanes to alleviate any backups that may occur on I-75.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is January.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  On the evenings of Monday through Thursday, from 7 p.m.-6 a.m. the following morning, the contractor will have an inside lane closed on U.S. 27 in each direction from the Olgiati Bridge to Manning Street to set bridge girders over Manning Street.  Manning Street will also be closed during this work between Power Corporation Drive and Winchester Street.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is January.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  



Bradley County Sheriff Office Releases Sobriety Checkpoint Statistics

The Bradley County Sheriff Office’s Public Safety Unit conducted Roadside Sobriety Checkpoints in three locations within Bradley County on Friday from 9 p.m.- 2 a.m. They were held at Eureka Road at Lower River Road, Dalton Pike at Waterville Elementary School, and APD 40 at Benton Pike. The five-hour operation produced (907) vehicles passing through the checkpoint ... (click for more)

Impact Of Hydrofracking To Be Topic Of Public Program

The impact of hydrofracking for the extraction of natural gas will be the topic of a public program hosted by the League of Women Voters and Dalton State College Wednesday, Nov. 29, beginning at 7 p.m.  The free program will be held in Goodroe Auditorium of Gignilliat Memorial Hall.   “Since our area sits above the Conasauga Shale which is believed to contain ... (click for more)

City Council Votes On 1st Reading To Lower Rain Retention Requirement In South Chickamauga Creek Basin

The City Council on Tuesday voted to lower the requirement for rainwater retention in the South Chickamauga Creek basin. The move from holding the first 1.6 inches to one inch had been requested by the Home Builders Association and the Berke administration. Sandy Kurtz, longtime leader of the South Chickamauga Creek Greenway Alliance, said the resolution was "not yet ready ... (click for more)

Former Pilot Regional Account Specialist Says Former President Mark Hazelwood Approved Of Fraud

When well-known attorney Rusty Hardin on Tuesday asked a former Pilot regional account specialist if she believed that former president Mark Hazelwood knew of a plan to cheat trucking firms he didn't get the answer he expected. Holly Radford told a jury in Chattanooga, "I know he had knowledge of the rebate schemes that were going on. "I had conversations with him about it ... (click for more)

Stormwater Fiasco And East Ridge Camping

When did the Chattanooga City Council get replaced by members of the East Ridge City Council? I don't recall a time in Chattanooga where they've voted to shoot the city in the foot more than they have lately.  If this goes through despite the environmental impact warnings and then Camp Jordan has increased flooding after spending millions on sports ball fields, ... (click for more)

Roy Exum: Thanksgiving Eve

I don’t know who was the first to do the Famous Pregnant Turkey prank but I’ll bet you a handful of giblets there will be a lot of copycats who try it today. The trick is finding a Cornish hen that is small enough to stuff inside the larger turkey. Then you skillfully pack the bird with some of that sausage-sage dressing and put your Thanksgiving dinner in the oven. When all ... (click for more)