TDOT Construction Update

Thursday, January 30, 2014

Parts of EAST and MIDDLE TENNESSEE Construction

JANUARY 30, 2014 – FEBRUARY 5, 2014

BRADLEY COUNTY, I-75 construction of a concrete Bulb-Tee Beam Bridge, including grading, drainage and paving at the Exit 20 interchange (U.S. 64 Bypass East, U.S. 74 East, SR-311, APD-40) (LM 4.86) in Cleveland:  Work continues on this project.  The contractor will be working on clearing and drainage during this report period.  APD-40 south going toward I-75 is down to one lane from Exit 20 to the end of the project.  The designated right turn lane on APD-40 will be closed to allow the contractor to begin widening the roadway, and the I-75 northbound on-ramp is reduced to a 16-foot lane.  Signs will be posted and flaggers will assist with traffic control if needed.  Any work requiring interstate lane closures is limited to Sunday through Thursday nights between 7PM - 6AM.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is November 2015. 


BRADLEY COUNTY, Benton Pike, Durkee Road, and Michigan Avenue, grading, drainage, and paving on a State Industrial Access route serving the Whirlpool Corporation:  The contractor continues work on this project at the Whirlpool Corporation plant.  Flaggers will assist with traffic control as needed.  Estimated project completion date is July 2014. 


Hamilton County, U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I-75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is February 2014. 


HAMILTON COUNTY, U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Traffic has now been shifted onto the new northbound Signal Mountain Road exit ramp.  The temporary exit ramp to Signal Mountain Road that had been used by the traveling public was closed to allow construction of a new, permanent ramp.  The northbound Dayton Boulevard exit ramp was also closed, and it will be closed for s

several months to allow the contractor to construct a new bridge.  As a result, traffic accessing Signal Mountain Road and Dayton Boulevard from U.S. 27 North is now routed onto the new ramp that ends in a signalized intersection at Signal Mountain Road.  From there, either a left turn toward Dayton Boulevard or a right turn onto Signal Mountain Road can be made.  The signal-controlled intersection as it is currently configured is only temporary.  When the work is completed in this area, traffic travelling toward Signal Mountain will have two permanent free flowing right turn lanes from U.S. 27 North which will significantly improve the movement of traffic.  However, to construct these new lanes it is necessary to shift traffic to its current position so that work can continue.  The work to complete these new free flowing lanes is scheduled to be completed in approximately sixty days, and TDOT is looking at means to expedite their construction even more quickly if possible.  Meanwhile, we will continue to monitor the traffic and make adjustments to the signal timing along with whatever other temporary improvements we can make to move traffic as smoothly as possible.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015. 


HAMILTON COUNTY, Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is February 2014. 


HAMILTON COUNTY, construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014. 


HAMILTON and BRADLEY COUNTIES, I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014. 

Marion County, u.s. 41 (U.S. 64, U.S. 72, SR-2) replacement of the truss bridge over the Tennessee River at Nickajack Lake (LM 21.14) with a multi-span steel plate girder bridge:  The truss bridge is now closed to all through traffic until the new adjacent bridge currently under construction is completed.  A detour route that adds an additional 1.5 miles to the current route is posted.  Estimated project completion date is February 2014 (this date will be changed soon due to a time extension, but at this time the final completion date has not been determined). 


MCMINN COUNTY, SR-30 widening project, including grading, drainage, paving, construction of a concrete box beam bridge and retaining wall from County Road 609 to the 4-lane section in Etowah:  The contractor is moving dirt in this phase of the project.  County Road 607 is currently closed, and a marked detour is in place.  Flaggers will assist with traffic control as needed.  Traffic is now detoured onto the new traffic lanes starting from east of County Road 609 and detouring back onto the old SR-30 at County Road 623.  Drivers are urged to use caution and pay attention to construction signs in this area.  Estimated project completion is November 2014. 


MCMINN COUNTY, SR-30 Miscellaneous safety improvements at the Tennessee Wesleyan College pedestrian crossing in Athens (LM 10.41):  The contractor continues work on this project.  Please be aware of intermittent lane changes.  Estimated project completion is February 2014. 

MEIGS COUNTY, SR-30 relocation beginning east of the Tennessee River to west of SR-58:  Paving operations have been suspended until the spring.  Traffic should not be interrupted until this starts.  Flaggers will assist with traffic control as needed.  Estimated project completion is spring 2014. 


VAN BUREN COUNTY, SR-111 grading, drainage, and paving from south of Manus Road to south of SR-285 near Double Bridge Road:  Work has begun on this project.  Temporary traffic control signs have been installed, and clearing is currently underway.  Motorists should use caution and be alert to construction equipment and vehicles within the work zone.  Project completion date is November 2015. 




TDOT Celebrates 100 Years Of Transportation

The Tennessee Department of Transportation’s year-long celebration of its centennial culminated today with the burial of a time capsule and installation of a granite memorial at Bicentennial Mall.  The granite memorial is located at the north end of the Bicentennial Mall, and pays tribute to 100 years of transportation in Tennessee. It was designed by Tuck Hinton Architects, ... (click for more)

Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County: South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street (Mid-State Construction Co, Inc.):  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, ... (click for more)

Work Set To Restart On Chickamauga Lock This Year

The U.S. Army Corps of Engineers allocated $3 million that Congress provided for fiscal year 2015 to restart construction on Chickamauga Lock this year, Senator Lamar Alexander and Rep. Chuck Fleischmann announced. “We need to replace Chickamauga Lock before it fails, and I talked with Secretary Darcy today to thank her for making this project a priority by deciding to restart ... (click for more)

Boyd Asks Coppinger For Public Apology; Does Not Get One

County Commissioner Tim Boyd on Wednesday morning read a letter in which he asked County Mayor Jim Coppinger for a public apology. However, he did not get one. Instead, County Mayor Coppinger called remarks last Wednesday by Commissioner Boyd that the county mayor had $4.4 million in discretionary funds "ridiculous." He said that money includes such items as the Humane Educational ... (click for more)

Police Need To Stop The Road Cowboys - And Response

Where is our highway patrol?  If they were known to regularly patrol our interstate highways through our city I don't think it would take long before the "truckers" were aware of it.  There are places in our country where this is the case.   When I have traveled Interstates 24 and 75 I may see the occasional car pulled over but rarely if ever is it an 18-wheeler. ... (click for more)

Roy Exum: Never Disturb The Dead

I’ve got too many things in my life that scare me so I’ve always been real leery of “unnecessary fear.” A guy named Terry wanted to teach me how to catch a live rattlesnake one time but had a tough time telling me what exactly to do with the angry serpent when the time came to let it go. I have the same view of these paranormal societies where otherwise sane people go around looking ... (click for more)