TVA Building On Improvements During Browns Ferry Outage

Tuesday, February 18, 2014

The Tennessee Valley Authority’s Browns Ferry Nuclear Plant Unit 3 has begun a scheduled refueling and maintenance outage that will prepare the unit to generate low-cost, carbon-free electricity for the next two years.

Browns Ferry Unit 3 was taken offline on Friday to begin refueling for its 16th operating cycle. Units 1 and 2 will continue to generate electricity during the Unit 3 outage, a regularly scheduled and carefully planned activity.

“Refueling Unit 3 is an important part of making sure that all three Browns Ferry units continue to safely generate reliable and clean energy for years to come, fulfilling TVA’s vision of being a national leader in the production of low-cost and cleaner power,” said TVA Executive Vice President and Chief Nuclear Officer Joe Grimes.

During the outage, 288 fuel assemblies will be replaced, roughly one third of the reactor core. In addition, maintenance on key equipment and systems will be performed, including work that cannot be done while the unit is online.

More than 900 TVA and contract employees will supplement the site’s regular staff.  In total, about 181,000 work-hours are scheduled during the refueling and maintenance outage.

TVA is committed to improving equipment reliability and operating margins across the nuclear fleet. All six TVA nuclear reactors generated electricity at or near full power during the severe cold in January, supporting the response from all segments of TVA’s generation and transmission system to provide electricity for heating homes and keeping essential services open across the Valley.

At Browns Ferry, TVA’s commitment to improvement achieved a site milestone on Dec. 14, 2013, when the plant marked 223 consecutive days of online operation by all three units. The start of the Unit 3 outage ended a consecutive run of more than 351 days for that particular unit.

At maximum summer capacity, Browns Ferry’s three units generate a combined 3,300 megawatts of electricity, which is 10 percent of TVA’s total generation capacity and enough electricity to power more than two million homes.


Beltone Announces Grand Opening In Hixson

Beltone is celebrating its grand opening for its newest store located at the Walmart Shopping Center, at 5756 Highway 153, Suite 116 in Hixson on  June 8  at 3 p.m. There is no cost to attend. There will be refreshments and snacks after the ceremony.  Officials said, "Come join us for this occasion with the Chattanooga Chamber of Commerce, and ... (click for more)

Chattanooga Women's Leadership Institute To Host Leadership Luncheon

Chattanooga Women’s Leadership Institute (CWLI) will host a Leadership Luncheon highlighting the importance of acknowledging mentors in the workplace on  Friday June 5, at The Chattanoogan from  11:30 a.m. – 1 p.m. One of the themes for 2015: recognizing and acknowledging the importance of mentors – even though our mentors may not look like us. ... (click for more)

Work To Start Later This Year On Major Reworking Of U.S. 27 Downtown; 31 Walls To Be Erected As Cameron Hill Faces More Cuts

Work is set to start later this year on the $80 million reworking of U.S. 27 in downtown Chattanooga. TDOT's Jennifer Flynn said all of the right of way has been acquired and construction bids are tentatively scheduled to be opened in August.  The 1.4-mile project includes U.S. 27 from I-24 to south of the Olgiati Bridge.  Work was completed earlier this year ... (click for more)

2 Hurt At Soddy Daisy In Train/Car Accident

Two people were hurt in a train and car accident in Soddy Daisy. More information will follow as it becomes available.   (click for more)

Erlanger Electronic Medical Records Purchase Doesn't Add Up - And Response (2)

Erlanger has recently announced their decision to purchase a $100,000,000 Electronic Health Information System. Something smells. Erlanger's downtown campus has 760 licensed beds, according to hospital-data. That would equate to $131,578 per bed for this system (now that's a lot of ipads). Please re-read that simple math. I use to manage an Electric Medication Administration ... (click for more)

Roy Exum: City Limits Worry Dogs, Cats

If you are a dog or a cat in the Chattanooga area, it is very important to know exactly where the city limits are. You need to know that if a stray animal is rescued in the city, it is taken to one of the finest animal shelters in all of America. But if the errant pooch or tabby is found in Hamilton County – outside the city limits -- it is taken to arguably the worst animal facility ... (click for more)