Weekly Road Construction Report

Thursday, February 27, 2014

Here is the weekly road construction report:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  On Sunday beginning at 10 a.m. the contractor will be re-striping the roadway and ramps on U.S. 27 to brighten the worn pavement markings in the construction zone.  The work is needed due to all the recent weather that has worn the markings significantly.  The striping of the roadway will be a mobile operation and should be completed quickly.  There will be lane closures for the entire project limits both northbound and southbound during the daylight hours to re-install missing raised pavement markers, which will be the most time-consuming portion of the work.  The majority of the ramps will also require some re-striping, so motorists should anticipate some delays as the ramps are done.  Traffic has now been shifted onto the new northbound Signal Mountain Road exit ramp.  As a result, traffic accessing Signal Mountain Road and Dayton Boulevard from U.S. 27 North is now routed onto the new ramp that ends in a signalized intersection at Signal Mountain Road. The signal-controlled intersection as it is currently configured is only temporary while a new permanent two lane free-flow lane to Signal Mountain Road is constructed.  The work to complete these new free flowing lanes is scheduled to be completed by the end of March.  Meanwhile, we will continue to monitor the traffic and make adjustments to the signal timing along with whatever other temporary improvements we can make to move traffic as smoothly as possible during this phase of the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  

Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County:  South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street:  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga is nearing completion. The bridge remains closed, but the section of East Main Street ... (click for more)

Jazzanooga Events During October

Here are some of the Jazzanooga happenings during October:  Startup Week: Open Dialogues: Defining Inclusion and Diversity As part of Startup Week Chattanooga, the team behind Jazzanooga and Animate MLK will host a workshop led by national consultant, Dr. Linda Wiley on diversity and segregation in Chattanooga's arts, culture and creative communities. This workshop ... (click for more)

Father Killed By Train Just After Pushing Daugter To Safety In East Brainerd

A 31-year-old man was killed just after he pushed his 10-year-old daughter to safety in an encounter with a train on a trestle in East Brainerd on Thursday afternoon. Police said two pedestrians were walking on the train tracks on a trestle at Audubon Acres when a train came around a bend and struck one of them. Justin McCary was struck by the train as he pushed ... (click for more)

Debate Blocked On Bill That Includes Funding To Restart Work On Chickamauga Lock

A bill by Senator Lamar Alexander that includes funding to restart Chickamauga Lock was halted on Thursday. Setting what Senator Alexander called a "dangerous precedent" for the Senate, he said Senate Democrats blocked deba te on th e bipartisan Energy and Water Development Appropriations Bill. Senator Alexander said on the floor, “You don't start the process at the ... (click for more)

  • Ferguson Given 15 Years As "Armed Career Criminal"
  • DesJarlais Welcomes Withdrawal Of McCarthy From House Speaker Race
  • Erlanger Settlement Understandable, But Disgusting

    Re: Erlanger Reaches Settlement With Former CEO Understandable from a legal liability standpoint but disgusting non the less. Gus Bryan (click for more)

    Roy Exum: An Unfortunate Sentence

    There was a most unfortunate line in a recent email written to me and, in retrospect, I should not have included it in some examples of the huge response regarding the bicycle lanes now being installed on Broad Street. I’ll admit I misread the line because I feel certain I know what the writer was trying to convey. As a matter of fact, I received enough of an outcry I want to clarify ... (click for more)