Weekly Road Construction Report

Friday, February 07, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is February. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Traffic has now been shifted onto the new northbound Signal Mountain Road exit ramp.  As a result, traffic accessing Signal Mountain Road and Dayton Boulevard from U.S. 27 North is now routed onto the new ramp that ends in a signalized intersection at Signal Mountain Road. The signal-controlled intersection as it is currently configured is only temporary while a new permanent two lane free-flow lane to Signal Mountain Road is constructed.  The work to complete these new free flowing lanes is scheduled to be completed by the end of March.  Meanwhile, we will continue to monitor the traffic and make adjustments to the signal timing along with whatever other temporary improvements we can make to move traffic as smoothly as possible during this phase of the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor will be paving during this report period as weather and temperatures permit.  Drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is February.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


Chief John Ross Chapter Of DAR Sponsored Genealogy Workshop

The Chief John Ross Chapter of the Daughters of the American Revolution sponsored a beginner genealogy workshop at the Bessie Smith Hall. Basic tips to start a family history, as well as worksheets and online tools to use, were covered.   There was a discussion on how to interview family for information, how to organize material and different organizations and online ... (click for more)

Upcoming Park Closures

The boat ramp at Chester Frost Park will be closed Saturday and Sunday for the County Fair.  The boat ramp at the Tennessee Riverpark and the section of the Riverwalk between River Port Road to the Veteran’s Bridge will be closed Sunday for the Ironman event.   All will re-open to the public on Monday. Please contact Hamilton County Parks and Recreation at 423-842-0177 ... (click for more)

Erlanger Finishes Fiscal Year With $18 Million Profit

After a major loss the year before, Erlanger Health System finished the fiscal year with an $18 million profit, officials announced Monday night. It was well ahead of the $2 million gain that Erlanger had budgeted for, and far better than last year's $8 million loss. The profit was boosted by a first-time $19,587,000 from a Public Hospital Supplemental payment and essential ... (click for more)

Chancellor Rules That IDB Must Reimburse Attorney Fees, Other Legal Costs For Helen Burns Sharp On TIF Lawsuit

Chancellor Pam Fleenor has ruled that Helen Burns Sharp, who sued over the validity of a $9 million Tax Increment Financing (TIF) for a planned major development on Aetna Mountain, should be reimbursed her discretionary costs as well as her attorney fees. Ms. Sharp said in a recent court filing that her legal bills to attorney John Konvalinka were $74,427 at the time. The ... (click for more)

ChattaData Is A Real Advance For The City

This past Tuesday, the city of Chattanooga's new performance management tool called ChattaData was unveiled. As the chairman of the City Council’s Budget & Finance Committee, I am excited to witness the city putting this important information online in a way that is accessible and transparent to all taxpayers. This approach shines light on how we as a city prioritize our ... (click for more)

Roy Exum: It’s ‘Hate The SEC’ Day

The boo birds came out on the fly on the ESPN website Sunday afternoon, this moments after the latest AP College Football “Top 25” included eight teams from the Southeastern Conference.   What set naysayers aglow was Mississippi State, after upsetting LSU 34-29 Saturday night, debuted on the list at No. 14 while Clemson, playing Florida State in an overtime thriller, got tossed ... (click for more)