Weekly Road Construction Report

Thursday, March 20, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work has resumed on this project.  A temporary lane closure is possible on the off-ramp.  Traffic on I-75 southbound should not be affected.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  The new permanent two lane free-flow lane to Signal Mountain Road from U.S. 27 North is open to traffic.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  As soon as possible, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


The Anand-Martin Foundation Hosts Fundraiser On Saturday To House Homeless Vets

The Anand-Martin Foundation will host its first liquidation benefit sale on Saturday from 8 a.m.-7 p.m. to assist in securing emergency housing and placements for veteran and families. "We welcome the community to come out to support our veterans and the mission of the Foundation to house those who have no place to call home, " organizers said. "Come out and enjoy incredible ... (click for more)

Road Closure Extended On South Crest Road Bridge Project

Work on the major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues.  During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge.  Detours are posted for the duration of the project. Estimated project completion date has been extended through Sept. 25. ... (click for more)

Hutcheson Medical Center Unsecured Creditors Committee Asks Trustee Be Appointed For Fort Oglethorpe Hospital; Asks Bankruptcy Not Be Dismissed

The Unsecured Creditors Committee of Hutcheson Medical Center is opposing a motion by U.S. Trustee Guy Gebhardt for a bankruptcy judge to dismiss the bankruptcy for the financially-ailing Fort Oglethorpe hospital.   Instead, the group is asking Judge Paul Bonapfel to appoint a trustee to oversee the Hutcheson finances. In a 16-page motion, the committee said if the bankruptcy ... (click for more)

Developer Says CARTA To Lease 75 Parking Spaces At Renaissance Park Lot For New $14 Million Apartments

A member of the Vision Hospitality Group said Tuesday that CARTA plans to lease 75 spaces at the public parking lot by Renaissance Park for its planned $14 million apartment complex. Drew Hibbard, vice president of finance and investments, told members of the North Chattanooga Council of the Chamber of Commerce that it will be under a 50-year lease with the transit group that ... (click for more)

Sheriff Hammond Is Right On The Muslim Threat - And Response (2)

Sheriff Hammond is exactly correct on the Muslims in Tennessee.  He sees with clear eyes the problem with the Muslims in our state and country.  They do want to take over Tennessee.  Our politicians are selling us down the river and allowing the trouble makers to dig in like tics and suck out the life's blood of our Constitution and take us over.  They ... (click for more)

Roy Exum: The Barners Trounce Who?

There is a website known as Grammarly that just completed a profound study. An automated proof-reading company (who I hope never finds out about me) collected 100 comments that each included over 50 words from the comment blogs of the nation’s preseason Top 25 college football teams. Then they fed them into the company’s huge algorithm computer and checked each fan base for punctuation, ... (click for more)