Weekly Road Construction Report

Thursday, March 20, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work has resumed on this project.  A temporary lane closure is possible on the off-ramp.  Traffic on I-75 southbound should not be affected.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  The new permanent two lane free-flow lane to Signal Mountain Road from U.S. 27 North is open to traffic.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  As soon as possible, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.   

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


Chattanooga Chamber Business Calendar May 28-June 4

WED/6.1- AM Networking at Cohutta Banking Company 8:00 a.m. to 9:00 a.m. Cohutta Banking Company: 800 Market Street Held the first Wednesday of every month, AM Networking brings between 75-135 business people together for an hour of networking and refreshments. AM Networking this month will be sponsored and hosted by Cohutta Banking Company. To RSVP for this event, ... (click for more)

Success Ready: A Free Career Prep And Job Fair For Teens To Be Held June 2-3

First Things First presents Success Ready , a two-day networking event for high school aged teens who are looking for summer employment and beyond. “We’re in the high schools on a regular basis teaching relationship skills,” said Julie Baumgardner, president and CEO of First Things First. “We saw the need for a type of networking and career prep event for ... (click for more)

Attorney Says Lacie Stone, Advisor To Mayor Berke, Is Victim, Not Instigator

The attorney for advisor to Mayor Andy Berke Lacie Stone said she has been thrust into the spotlight, but said she is "the victim of an unprovoked attack" by her husband, Bobby Stone. Attorney John Cavett said it is ridiculous "to suggest that she was the perpetrator." Mr. Stone is facing charges of domestic assault and vandalism. Attorney Cavett said, "It is unfortunate ... (click for more)

Dr. Russell Dyer Chosen As Director Of Schools By Cleveland City School Board

The Cleveland City School board unanimously voted Thursday afternoon to offer the job of director of Schools to Dr. Russell Dyer. Dr. Dyer serves as the chief of staff of schools in Collierville, Tn.  If Dr. Dyer accepts the school board's contract, he will be paid $132,500 a year.  After contract negotiations, the board plans for Dr. Dyer to start at Cleveland City ... (click for more)

Case Handled Like Any Other? - And Response

It is interesting that Chief Fletcher would deem the handling of the Mayor's encounter as typical or normal. Is the Chief asking the public to believe that all misdemeanor domestic violence arrests include a 4-hour taped interrogation, and delayed reporting after a visit to the Chief’s house. Of course, we believe that Chief Fletcher. April Eidson * * *  I ... (click for more)

Roy Exum: The American Dream, 2016

On this, the week of commencement, junior high graduations, and achievement at every level is displayed, we stand with hope and wonder as the next wave of promising Americans gives our nation the reason we pray for our next tomorrow. On Monday, as Vice President Joe Biden addressed 950 cadets who would become 2nd Lieutenants by the end of the day at the United States Military ... (click for more)