Weekly Road Construction Report

Thursday, March 27, 2014

Here is the weekly road construction report for Hamilton County: 

U.S. 41 (SR-8, Ringgold Road) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work has resumed on this project.  A temporary lane closure is possible on the off-ramp.  Traffic on I-75 southbound should not be affected.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is April.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  During this report period the contractor will be paving on Signal Mountain Road during daylight hours.  One lane in each direction will remain open and flaggers will assist with traffic control if required.  The contractor will work around rush hour as paving proceeds.  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  The new permanent two lane free-flow lane to Signal Mountain Road from U.S. 27 North is open to traffic.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.   

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  As soon as possible, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is April.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  


HCSO And CPD Host 2016 Law Enforcement Memorial Ceremony Tuesday

The Hamilton County Sheriff’s Office, in conjunction with the Chattanooga Police Department, will host the 2016 Law Enforcement Memorial Ceremony to honor the deputies and police officers from the community who have fallen in the line of service and their survivors.  This year’s program will take place on Tuesday at 11:30 a.m. at the Law Enforcement Memorial, 600 Market ... (click for more)

700 Block Of Market Street To Be Closed Wednesday Night

The 700 Block of Market Street, between 7th and 8th Streets, will be closed for equipment removal on Wednesday, from 7 p.m. to 12 a.m. Detours will be posted. For a list of all road closures, visit the city's  website .   (click for more)

Federal Government Sues Life Care's Forrest Preston, Saying He Received Millions In Medicare Funds He Was Not Entitled To

Federal attorneys have sued Forrest Preston, founder and chairman of Cleveland, Tn.,-based Life Care Centers of America, claiming that he was "unjustly enriched" by receiving Medicare funds he was not entitled. The civil suit in Chattanooga Federal Court asks for the return of "millions of dollars." The government earlier sue Life Care on similar charges based on allegations ... (click for more)

Developer Plans Single-Family Homes, Townhomes, Apartments, Retail On 7.5 Acres At South Broad Street

A developer is planning single-family homes, apartments, townhomes and retail on a 7.5-acre South Broad Street site. The development by South Broad LLC and DEW LLC is located within several blocks between South Broad Street, W. 26th Street, Long Street and W. 27th Street. It would include a 3-story U-shaped apartment building with ground floor retail at the north end of the ... (click for more)

Thankful For The Vital Role Teachers Played In My Life

Re: Roy Exum: Teachers Day Tomorrow Roy, I am especially appreciative of your poignant column written in tribute to teachers.  It made me tear up, as I have encountered both as a student and a career educator-- teachers like the second-grade teacher who said, "I wish you were my little girl" and teachers like Mrs. Poindexter.   My teachers have played such a vital ... (click for more)

Roy Exum: The DA’s Cold-Case Quest

It is clearly a job nobody can do for over an hour or two, but Neal Pinkston, working in hand with precise professionals from the county’s auditing department, is intent on doing the right thing. As I watched a revolving team of four people at a time open and study envelopes of autopsy photographs on Tuesday, the scene would have made a fascinating television documentary. But ... (click for more)