Weekly Road Construction Report

Thursday, March 6, 2014

Here is the weekly road construction report for Hamilton County: 

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Work has progressed well on the new permanent two lane free-flow ramp to Signal Mountain Road from U.S. 27 North.  The concrete has been poured and must be allowed to cure for several days.  Once it is tested and approved to efficiently carry traffic, the contractor will seal the concrete, complete shoulder and tie-in work, install permanent signs, and place permanent pavement markings.  After this work is successfully accomplished, traffic will be shifted to the new ramp, tentatively scheduled to take place one night during this report period.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.   

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  Currently, the contractor is completing tying in side roads to the main road and laying sod throughout the project.  As soon as temperatures allow, the contractor will place permanent thermoplastic pavement markings on the roadway.  Once all this work is done, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  



Lunch Conversations With The Commissioner Returns June 1

Walker County Sole Commissioner Shannon Whitfield invites you to join him for lunch, as the busy summer season approaches.  Commissioner Whitfield will hold his second Lunch Conversation with the Commissioner on June 1 from 11 a.m.-1 p.m. at Susan's Diner, 3551 Chattanooga Valley Road in Flintstone. The public is encouraged to drop by, purchase a meal and enjoy some friendly ... (click for more)

Special Event Street Closures

Here are the special event street closures for May 26-29 in Chattanooga:  Friday, May 26 Nightfall Concert Series: Closures include Market from 10th to 8th, MLK Boulevard from Broad Street to Georgia Avenue from 5:30-11:59 p.m. The Nightfall Concert Series is free to the public and held each Friday till Aug. 25 (except for June 9 and 16) outdoors in Miller Plaza. This ... (click for more)

Erlanger Expects $5 Million Profit Despite "Very Challenging" Budget

Erlanger Health System officials said they expect a $5 million profit for the upcoming fiscal year despite a "very challenging" budget. Britt Tabor, chief financial officer, said there will be continued top line growth, which has brought a 51 percent rise in patient revenue over the past five years. "This is organic growth. It's not from mergers or acquisitions," Mr. Tabor ... (click for more)

Public Defender Says Another Entity Needs To Continue Funding For New Mental Health Court

Public Defender Steve Smith said another entity needs to take over funding the new Mental Health Court. He said Criminal Court Judge Don Poole has agreed to oversee the court and will make a budget presentation to the County Commission on May 31. Mr. Smith told members of the Pachyderm Club on Monday that he has been funding the program through the services of Anna Protano ... (click for more)

Tennessee Business Expansions On Rise Across State

In 2016, Tennessee was named State of the Year for Economic Development by Southern Business & Development Magazine based on project totals and the variety of industries that invested in the state and created jobs. To a great extent, Bradley and Polk Counties have benefited from that investment.   From February 2015 to February 2016, Cleveland/Bradley County led the ... (click for more)

Roy Exum: The Public Defender And The Mental Health Court

I am holding in my hand a list of the names of 50 very real people who cost the taxpayers of Hamilton County a combined $3,037.090 in incarceration charges before July 2015. These people live in our county and I dare say it is not completely their fault that they were put in the county jail. Each has a professionally-diagnosed mental illness and today, most regretfully, the County ... (click for more)