Weekly Road Construction Report

Thursday, March 6, 2014

Here is the weekly road construction report for Hamilton County: 

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Work has progressed well on the new permanent two lane free-flow ramp to Signal Mountain Road from U.S. 27 North.  The concrete has been poured and must be allowed to cure for several days.  Once it is tested and approved to efficiently carry traffic, the contractor will seal the concrete, complete shoulder and tie-in work, install permanent signs, and place permanent pavement markings.  After this work is successfully accomplished, traffic will be shifted to the new ramp, tentatively scheduled to take place one night during this report period.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.   

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  Currently, the contractor is completing tying in side roads to the main road and laying sod throughout the project.  As soon as temperatures allow, the contractor will place permanent thermoplastic pavement markings on the roadway.  Once all this work is done, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  



Celebration Of Human Rights Day Is Dec. 10

The United Nations adopted the Universal Declaration of Human Rights on Dec. 10, 1948. It represents the universal recognition that basic rights and fundamental freedoms are inherent to all human beings, inalienable and equally applicable to everyone, and that every one of us is born free and equal in dignity and rights. The community is invited to come to the Eastdale Village ... (click for more)

Chattanooga International Human Rights Day 2016 Commemoration To Be Held Dec. 10

The Chattanooga Human Rights Day Committee, in conjunction with the Tennessee Human Rights Commission, will host the Chattanooga International Human Rights Day 2016 Commemoration, on  Saturday, Dec. 10, at 10 a.m. , at the Eastdale Village UMC Church. For more details, call  423 320-8598 . (click for more)

East Ridge Meth Dealer Gets 168 Months In Federal Prison

A man who agents said was dealing large quantities of meth from his East Ridge residence has been sentenced to serve 168 months in federal prison. Kenneth Lemons appeared before Judge Curtis Collier. Agents said they made several controlled drug buys from Lemons at his residence in 2015. On Oct. 27, 2015, he drove up to a residence where DEA agents were making a controlled ... (click for more)

Chattanooga Man With 5 Violent Felonies Gets 30 Years In Prison

A Chattanooga man with five violent felonies on his record has been sentenced to serve 30 years in prison. Demetrius Joiner, 30, was given a 20-year sentence by Judge Curtis Collier after he was ruled to be an Armed Career Criminal. Judge Collier said the term would be consecutive to several state sentences imposed earlier on Joiner, including 10 years for aggravated robbery. ... (click for more)

Signal Mountain Couldn't Manage Public Education

I have been reading the buzz about Signal Mountain and other small municipalities considering a move to form their own school district within their municipal boundaries.  It is quite the comedy hour considering the notion that small cities that for decades could not even manage small sewer systems or 911 districts, are somehow going to do a better job with public education ... (click for more)

Roy Exum: School Board Can’t Wait

It took the Hamilton County School board nine months before the group hired a search firm to find a new superintendent. But you mark my words – the Department of Education will undoubtedly implode if our leaders wait another nine months simply hoping for some type of mystical salvation. In the last week Signal Mountain leaders have all but given notice they will form their own district ... (click for more)