Weekly Road Construction Report

Thursday, March 6, 2014

Here is the weekly road construction report for Hamilton County: 

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  The majority of work on this project has been completed.  There will be no work during this report period.  In the future, the contractor will be installing a traffic signal at the top of the ramp.  Work will take place during non-peak daytime hours on Mondays through Saturdays.  At least one lane on the ramp will remain open at all times.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is March.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  Work has progressed well on the new permanent two lane free-flow ramp to Signal Mountain Road from U.S. 27 North.  The concrete has been poured and must be allowed to cure for several days.  Once it is tested and approved to efficiently carry traffic, the contractor will seal the concrete, complete shoulder and tie-in work, install permanent signs, and place permanent pavement markings.  After this work is successfully accomplished, traffic will be shifted to the new ramp, tentatively scheduled to take place one night during this report period.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.   

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Shallowford Road is now open to traffic.  Currently, the contractor is completing tying in side roads to the main road and laying sod throughout the project.  As soon as temperatures allow, the contractor will place permanent thermoplastic pavement markings on the roadway.  Once all this work is done, TDOT engineers will make a final inspection of the project after which the contractor will address any punchlist items that are found during the final inspection.  Because workers will still be in the construction zone, drivers are urged to be alert and to obey all traffic signs.  Flaggers will be in place to assist with traffic control as necessary.  Estimated project completion date is March.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  



TechTown And Library Sponsor Spring Break Camp

The TechTown Spring Break Camp will be held at the Chattanooga Public Library next week. The camp will run Monday to Friday from 9 a.m.-4 p.m. on the Library's 4th Floor at 1001 Broad St.  Seventy Chattanooga area students ages 10 to 17 attending the sold-out camp will spend the week learning about videography, circuitry and robotics. These hands-on learning opportunities ... (click for more)

3-Month Road Closure On East 10th Street To Begin Monday

East 10 th  Street will be closed between Baldwin Street and Foster Street beginning on  Monday at 8:30 a.m. , for utility work and building construction.   The intersections of East 10 th  Street and University Street, and East 10 th  Street and Douglas Street will be closed as well to facilitate a utility ditch in the middle of East 10 th ... (click for more)

Robber Who Was Shot At Rossville Boulevard Car Lot Dies; No Charges To Be Filed

Police said a person who was shot during a robbery attempt at a car lot at 4314 Rossville Blvd. around 1:50 p.m. on Thursday has died. Police said the shooting has been ruled a "justifiable homicide" and no charges will be brought against 27-year-old Alan Miller. The shooting in which the robbery victim shot the suspect was at Miller Auto Sales. (click for more)

Man Charged In Shooting On Sixth Avenue Had Been Shot Himself Last Week; Police Say Incident "Part Of Gang War"

A man charged with attempted first-degree murder on Sixth Avenue Court on Thursday afternoon was shot himself earlier this month. O'Shae Kadaris Smith, 20, of 2114 E. 12th St., is also charged with reckless endangerment, aggravated assault and possessing a firearm during the commission of a crime. He was one of two people shot on Rawlings Street on March 16. Kendre Allen, ... (click for more)

Finley Stadium Needs To Grow Up - And Response

RE:  Finley Stadium Financial Picture Rosy; Beer And Alcohol Sales Approved; AstroTurf Almost Ready and City, County Pitching In $250,000 Each For New Finley Stadium AstroTurf I read a story here five days ago about a rosy future for Finley stadium. It lead me to believe that the stadium was making money and even improvements with donations.  Then we get a short ... (click for more)

Roy Exum: The Hillman Of Bihar

In the year of our Lord, 1927, there was a very poor child born to a very poor family in a very poor place. His name was Dasrath Manjhi and he was a native of the Musahar community somewhere in India. We know he had no education and, as a member of the lowest Hindu scheduled castes, he didn’t have a cut dog’s chance from the very get go. But after spending considerable time in ... (click for more)