Weekly Road Construction Report

  • Thursday, April 24, 2014

Here is the weekly road construction report for Hamilton County:

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures and short term nighttime outside lane closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  On the evening of Friday the contractor will close the left lane of U.S. 27 North and South between the Olgiati Bridge and Manning Street, along with Manning Street itself, to pour the bridge deck for the bridge over Manning Street.  All work is weather permitting.  If this work is cancelled due to weather, it will be rescheduled to take place on the next available day.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

SR-58 resurfacing from Lakewood Acres Road (LM. 9.20) to Greenwood Road (LM 14.68):  Work on this project is scheduled to begin during this report period.  Milling and paving operations are limited to Sunday through Thursday nights between 7 p.m.-6 a.m.  There will be temporary lane closures as needed on this project.  At least one lane in each direction will remain open at all times.  Estimated completion date is July.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  


Latest Headlines
Happenings
Michael Gerard Receives American Police Hall Of Fame Civilian Medal Of Appreciation
Michael Gerard Receives American Police Hall Of Fame Civilian Medal Of Appreciation
  • 3/18/2024

Collegedale officers responded to Garden Plaza of Greenbriar Cove on Sept. 21, 2023, after receiving a report of a missing elderly resident with dementia. The patient had left the facility approximately ... more

New Hamilton County Marriage Licenses
  • 3/18/2024

Here are the new marriage licenses from the County Clerk's office: SCOTT EDWARD KELLEY JAIMIE LYNN PASTORI 2205 JAMES AVE 4203 TENNESSEE AVE CHATTANOOGA, Tennessee 374156511 CHATTANOOGA, ... more

Chief John Ross DAR Presents Gold ROTC Medal
Chief John Ross DAR Presents Gold ROTC Medal
  • 3/18/2024

Chief John Ross Chapter, NSDAR had their March meeting on the 13th, and the meeting theme was Women’s History Month. Officials said, "Chapter member, Kay Sencabaugh, presented an entertaining ... more