Stantec’s Support Of TVA’s Coal Ash Spill Recovery Earns Awards For Engineering Excellence

Wednesday, June 4, 2014
The Kingston Coal Ash Spill/Failure of 2008
The Kingston Coal Ash Spill/Failure of 2008

Stantec has received the Grand Award from the American Council of Engineering Companies of Kentucky. The award recognizes Stantec for its design and technical solution for the Tennessee Valley Authority’s recovery from the Kingston coal ash spill. The project also received a National Recognition Award at the ACEC 2014 Engineering Excellence Awards competition.  

In December 2008, the dikes at TVA’s power station in Kingston, Tennessee containing wet coal combustion ash failed, and 5.4 million cubic yards of coal ash were released. The ash slurry flowed out from the site, impacting the adjacent Emory River In the aftermath, TVA committed more than $1 billion for the response, clean up, and site restoration. 

Stantec’s team was at Kingston within hours after the spill to assist TVA with emergency actions. As the recovery progressed, Stantec developed a site closure scheme, completed detailed engineering designs for a containment structure, and remained on-site to help with recovery efforts.  

Today, TVA has achieved several key milestones at Kingston. During the first two years after the spill, about three million cubic yards of ash dredged from the river was shipped by rail to a permitted, off-site landfill. Since then, the remainder of the released material has been excavated and stacked back inside the footprint of the failed impoundment facility. A two-mile long perimeter containment structure has been built around the new 240-acre ash landfill, which is being capped with a flexible membrane cover system.  In 2014, Stantec’s design was recognized by ACEC for engineering excellence.

The idea of placing large volumes of ash back within the failed area was met with initial skepticism, said officials. To prove it could be done without causing another failure, a test embankment was built across six acres of the failed dredge cell. Geotechnical instrumentation was installed to measure water pressures and movements within the underlying ash. Stantec established criteria and monitored conditions. In the end, more than 250,000 cubic yards of ash were safely stacked to a height of 45 feet above the failed surface. In addition to restoring confidence, the test program established protocols that would be followed throughout the project.

By far, the most difficult design challenge was how to contain the ash in the event of a large earthquake, said officials. Tennessee regulations require landfill facilities to withstand a 2500-year earthquake. Engineering analyses showed that these events would liquefy the sandy soils underlying the ash landfill.

Borrowing an approach used elsewhere to stabilize large embankment dams, Stantec designed a grid of buried walls that enclose the ash landfill. The engineering design was complex and required advanced numerical modeling of the seismic behavior, using both dynamic 2D and static 3D structural analyses. The design was subject to extensive independent review and regulatory oversight. The completed retaining structure, built to depths of 70 feet, is one of the largest walls of its type ever constructed in the U.S. 

Craig Zeller, EPA’s project manager at the site, sees how far the cleanup project has come. “It was a daunting project at the start. But five years later, after dredging, digging, and stacking ash day after day, week after week, the end is in sight. The project is on schedule. Ash is out of the river. The perimeter walls are done. The environmental restoration is underway. Kingston is a fantastic case study for a large-scale cleanup,” Mr. Zeller says.

TVA’s Kingston, Tennessee, Fossil Plant supplies power that is critical to the regional economy. On-site storage of the recovered ash, made possible with the perimeter containment structure, represents TVA’s best option for meeting both the economic and environmental goals of the project. The result has restored public confidence that a failure like the 2008 event would not happen again at Kingston, not even during a major natural disaster like an earthquake, said officials.



Covenant Transportation Has Increased Revenue For First Quarter

Covenant Transportation Group, Inc. announced Thursday financial and operating results for the first quarter ended March 31. Highlights for the quarter included the following: Total revenue of $167.2 million, an increase of 3.9 percent compared with the first quarter of 2014. Freight revenue of $143.3 million (excludes revenue from fuel surcharges), an increase of 13.5 ... (click for more)

Yoga East Wellness Center To Open Second Studio At Cambridge Square

Yoga East Wellness Center (Yoga East) will open a second location in Cambridge Square, a mixed-use community located at the corner of Ooltewah-Georgetown Road and Lee Hwy. in Ooltewah. Yoga East will be locating in what is now the 2500 square foot Beyoga Ooltewah studio. The proprietors of both studios worked together to facilitate the transition "We would first like to thank ... (click for more)

State Attorney General Says City Council Cannot Make Taxis Not Registered In Hamilton County Go Through Emissions Testing

The state attorney general's office has ruled that the City Council cannot require that taxis not registered in Hamilton County go through emissions testing. The city is dealing with the new Uber taxi service that has an out-of-town owner. Locally-owned cabs have to go through the annual emissions testing. The opinion says that local taxi owners cannot get around the emissions ... (click for more)

Chattanooga Area Bracing For Possibility Of Isolated Severe Storms, Tornadoes Not Ruled Out

The National Weather Service is feeling uncertain about today's weather pattern and has not ruled out the possibility of isolated, severe thunderstorms or an isolated tornado in our area. The greatest threat seems to be between 4 and 7 p.m. this evening. Below is the latest update: HAZARDOUS WEATHER OUTLOOK...UPDATED NATIONAL WEATHER SERVICE MORRISTOWN TN 127 PM EDT SAT ... (click for more)

The Heart Of A Teacher Makes A Difference - And Response (2)

In less than four weeks, I expect to be one of 216 graduating seniors from East Hamilton School. One could say all possible variables help a student rise to the highest levels in school; but a student is more than his environment or genetic code. He is a mixture of his own propensity and dedication to academics, coupled with a systemic team of mentors who give their all as a student’s ... (click for more)

Roy Exum: FBI To Study ‘Lickers’

About 25 years ago there was a terrifying movie called “The Silence of the Lambs.” It was so good it won the Academy Awards in all five categories – Best Picture, Best Actor, Best Actress, Best Director and Adapted Screenplay. Further, Anthony Hopkins and Jodie Foster were brilliant, but do you remember the third “star?” Scott Glenn played a character named “Jack Crawford,” the ... (click for more)