Stantec’s Support Of TVA’s Coal Ash Spill Recovery Earns Awards For Engineering Excellence

Wednesday, June 04, 2014
The Kingston Coal Ash Spill/Failure of 2008
The Kingston Coal Ash Spill/Failure of 2008

Stantec has received the Grand Award from the American Council of Engineering Companies of Kentucky. The award recognizes Stantec for its design and technical solution for the Tennessee Valley Authority’s recovery from the Kingston coal ash spill. The project also received a National Recognition Award at the ACEC 2014 Engineering Excellence Awards competition.  

In December 2008, the dikes at TVA’s power station in Kingston, Tennessee containing wet coal combustion ash failed, and 5.4 million cubic yards of coal ash were released. The ash slurry flowed out from the site, impacting the adjacent Emory River In the aftermath, TVA committed more than $1 billion for the response, clean up, and site restoration. 

Stantec’s team was at Kingston within hours after the spill to assist TVA with emergency actions. As the recovery progressed, Stantec developed a site closure scheme, completed detailed engineering designs for a containment structure, and remained on-site to help with recovery efforts.  

Today, TVA has achieved several key milestones at Kingston. During the first two years after the spill, about three million cubic yards of ash dredged from the river was shipped by rail to a permitted, off-site landfill. Since then, the remainder of the released material has been excavated and stacked back inside the footprint of the failed impoundment facility. A two-mile long perimeter containment structure has been built around the new 240-acre ash landfill, which is being capped with a flexible membrane cover system.  In 2014, Stantec’s design was recognized by ACEC for engineering excellence.

The idea of placing large volumes of ash back within the failed area was met with initial skepticism, said officials. To prove it could be done without causing another failure, a test embankment was built across six acres of the failed dredge cell. Geotechnical instrumentation was installed to measure water pressures and movements within the underlying ash. Stantec established criteria and monitored conditions. In the end, more than 250,000 cubic yards of ash were safely stacked to a height of 45 feet above the failed surface. In addition to restoring confidence, the test program established protocols that would be followed throughout the project.

By far, the most difficult design challenge was how to contain the ash in the event of a large earthquake, said officials. Tennessee regulations require landfill facilities to withstand a 2500-year earthquake. Engineering analyses showed that these events would liquefy the sandy soils underlying the ash landfill.

Borrowing an approach used elsewhere to stabilize large embankment dams, Stantec designed a grid of buried walls that enclose the ash landfill. The engineering design was complex and required advanced numerical modeling of the seismic behavior, using both dynamic 2D and static 3D structural analyses. The design was subject to extensive independent review and regulatory oversight. The completed retaining structure, built to depths of 70 feet, is one of the largest walls of its type ever constructed in the U.S. 

Craig Zeller, EPA’s project manager at the site, sees how far the cleanup project has come. “It was a daunting project at the start. But five years later, after dredging, digging, and stacking ash day after day, week after week, the end is in sight. The project is on schedule. Ash is out of the river. The perimeter walls are done. The environmental restoration is underway. Kingston is a fantastic case study for a large-scale cleanup,” Mr. Zeller says.

TVA’s Kingston, Tennessee, Fossil Plant supplies power that is critical to the regional economy. On-site storage of the recovered ash, made possible with the perimeter containment structure, represents TVA’s best option for meeting both the economic and environmental goals of the project. The result has restored public confidence that a failure like the 2008 event would not happen again at Kingston, not even during a major natural disaster like an earthquake, said officials.



Obedience Club Of Chattanooga Has New Session Starting Jan. 5

The Obedience Club of Chattanooga will begin its next six-week session of obedience, rally, and agility classes for puppies and dogs on Monday, Jan. 5,  at its training facility four miles south of Chattanooga on Highway 193 in Flintstone. Registration will be held on Sunday, Jan. 4, from 1-3 p.m. at the training facility.  During registration, various OCC dog/handler ... (click for more)

Attorneys Batts And Taylor Elected To Lead State Drug Court Association

The Tennessee Association of Drug Court Professionals has elected attorneys Kevin Batts and Richard Taylor to leadership positions in the statewide group. Mr. Batts will serve as president and Mr. Taylor will serve as vice president of the association in 2015. Mr. Batts is director of the Drug Court in the 23rd Judicial District, serving five counties of Middle Tennessee. He ... (click for more)

TVA Sues Cleveland's Allan Jones Over Dock, Retaining Wall, Boat Ramp, Boathouse On Hiwassee River

TVA has sued Cleveland, Tn., Check Into Cash millionaire W. Allan Jones Jr. over the construction of a dock, retaining wall, boat ramp and boathouse on the Hiwassee River. In the lawsuit in Federal Court, TVA said it told Mr. Jones before the construction was finished that he was on TVA property. The complaint says he has refused to move the construction from the river. ... (click for more)

Bobby Dodd Lawsuit Against City Moved To Federal Court

A lawsuit brought by former Chattanooga Police Chief Bobby Dodd against the city of Chattanooga and the Chattanooga Fire and Police Pension Fund over his pension has been moved to Federal Court. The lawsuit was earlier filed in Chancery Court by attorneys Jerry Tidwell and Adam Izell. The suit says former Chief Dodd opted for a plan that would have half of his pension go to ... (click for more)

Please Don't Close The Piccadilly Cafeteria At Hamilton Place - And Response

Oh, no. The Piccadilly Cafeteria at Hamilton Place is closing.  Its last day is Christmas Eve.  I will miss the great food they have there but most of all I will miss their servers, cashiers and waitresses.  They are all so friendly and accommodating.  They make it like it’s a home-style restaurant. I sure wish there was some way that Hamilton Place and ... (click for more)

Roy Exum: The Manger Scene Stays!

When the Freedom From Religion Foundation struck the tiny town of Jay, Fla., earlier this month, the town mayor had a life-sized Nativity scene that had been displayed every Christmas for the past 40 years taken down and sold as “city surplus.” But in Alabama, things are different. When the foundation tried the same thing in Rainbow City, Ala., more people than all those who live ... (click for more)