Stantec’s Support Of TVA’s Coal Ash Spill Recovery Earns Awards For Engineering Excellence

Wednesday, June 4, 2014
The Kingston Coal Ash Spill/Failure of 2008
The Kingston Coal Ash Spill/Failure of 2008

Stantec has received the Grand Award from the American Council of Engineering Companies of Kentucky. The award recognizes Stantec for its design and technical solution for the Tennessee Valley Authority’s recovery from the Kingston coal ash spill. The project also received a National Recognition Award at the ACEC 2014 Engineering Excellence Awards competition.  

In December 2008, the dikes at TVA’s power station in Kingston, Tennessee containing wet coal combustion ash failed, and 5.4 million cubic yards of coal ash were released. The ash slurry flowed out from the site, impacting the adjacent Emory River In the aftermath, TVA committed more than $1 billion for the response, clean up, and site restoration. 

Stantec’s team was at Kingston within hours after the spill to assist TVA with emergency actions. As the recovery progressed, Stantec developed a site closure scheme, completed detailed engineering designs for a containment structure, and remained on-site to help with recovery efforts.  

Today, TVA has achieved several key milestones at Kingston. During the first two years after the spill, about three million cubic yards of ash dredged from the river was shipped by rail to a permitted, off-site landfill. Since then, the remainder of the released material has been excavated and stacked back inside the footprint of the failed impoundment facility. A two-mile long perimeter containment structure has been built around the new 240-acre ash landfill, which is being capped with a flexible membrane cover system.  In 2014, Stantec’s design was recognized by ACEC for engineering excellence.

The idea of placing large volumes of ash back within the failed area was met with initial skepticism, said officials. To prove it could be done without causing another failure, a test embankment was built across six acres of the failed dredge cell. Geotechnical instrumentation was installed to measure water pressures and movements within the underlying ash. Stantec established criteria and monitored conditions. In the end, more than 250,000 cubic yards of ash were safely stacked to a height of 45 feet above the failed surface. In addition to restoring confidence, the test program established protocols that would be followed throughout the project.

By far, the most difficult design challenge was how to contain the ash in the event of a large earthquake, said officials. Tennessee regulations require landfill facilities to withstand a 2500-year earthquake. Engineering analyses showed that these events would liquefy the sandy soils underlying the ash landfill.

Borrowing an approach used elsewhere to stabilize large embankment dams, Stantec designed a grid of buried walls that enclose the ash landfill. The engineering design was complex and required advanced numerical modeling of the seismic behavior, using both dynamic 2D and static 3D structural analyses. The design was subject to extensive independent review and regulatory oversight. The completed retaining structure, built to depths of 70 feet, is one of the largest walls of its type ever constructed in the U.S. 

Craig Zeller, EPA’s project manager at the site, sees how far the cleanup project has come. “It was a daunting project at the start. But five years later, after dredging, digging, and stacking ash day after day, week after week, the end is in sight. The project is on schedule. Ash is out of the river. The perimeter walls are done. The environmental restoration is underway. Kingston is a fantastic case study for a large-scale cleanup,” Mr. Zeller says.

TVA’s Kingston, Tennessee, Fossil Plant supplies power that is critical to the regional economy. On-site storage of the recovered ash, made possible with the perimeter containment structure, represents TVA’s best option for meeting both the economic and environmental goals of the project. The result has restored public confidence that a failure like the 2008 event would not happen again at Kingston, not even during a major natural disaster like an earthquake, said officials.



Grand Celebration Marks Completion Of Coolsprings Galleria

CBL & Associates Properties, Inc. (NYSE: CBL), on Tuesday announced the opening of the redevelopment at CoolSprings Galleria in Nashville (Franklin), Tn. Designed to significantly enhance the offerings at the shopping center, the redevelopment of the former Sears location included adding a new mall entrance as well as retail space for a mix of fashion stores, and fine dining ... (click for more)

Haslam, Boyd Announce Ficosa North America To Build New Facility In Putnam County

Gov. Bill Haslam and Economic and Community Development Commissioner Randy Boyd along with Ficosa North America officials announced today the company will expand its Tennessee presence by building a new state-of-the-art facility at the Highlands Business Park in Cookeville.  The automotive supplier will invest $58 million in the Putnam County facility and create 550 jobs.   ... (click for more)

Cleveland Councilman Banks Critical Of City Manager Casteel, But Several Council Members Come To Her Defense

Cleveland City Councilman Richard Banks on Tuesday afternoon was critical of City Manager Janice Casteel, but several other council members came to her defense.   The council, at the end of the discussion, voted to establish an evaluation process for city employees.   Ben Moore, a retired pharmacist and life-long resident of Cleveland told the council ... (click for more)

City Council Looking Into Need For City Court

City Council Chair Carol Berz on Tuesday brought up the issue of whether, under its charter, the city is required to have a City Court. She also asked Assistant City Attorney Phil Noblett to look into the issue of whether the city is required to have two divisions of City Court. Attorney Noblett said he also will look into the ramifications of the Municipal Court Reform Act ... (click for more)

County Officials Need To Provide A Decent Animal Shelter

Once upon a time, a group of citizens concerned about the decaying building housing the Humane Educational Society on Highland Park raised their voices in an outcry about the deplorable state of the HES facility and the over-population of unwanted and unspayed/unneutered cats and dogs in Hamilton County.   What happened then was that the City Council stepped ... (click for more)

Roy Exum: Two More Kick Out UAW

Woody Hayes, the great Ohio State football coach, used to teach his players to “paralyze resistance with persistence” but, my word, the likable theory has taken quite a beating in the past two years at the NTN-Bower ball-bearing plant in Hamilton, Ala. The workers there voted to decertify from the United Auto Workers union two years ago but getting the UAW out the door has turned ... (click for more)