Stantec’s Support Of TVA’s Coal Ash Spill Recovery Earns Awards For Engineering Excellence

Wednesday, June 4, 2014
The Kingston Coal Ash Spill/Failure of 2008
The Kingston Coal Ash Spill/Failure of 2008

Stantec has received the Grand Award from the American Council of Engineering Companies of Kentucky. The award recognizes Stantec for its design and technical solution for the Tennessee Valley Authority’s recovery from the Kingston coal ash spill. The project also received a National Recognition Award at the ACEC 2014 Engineering Excellence Awards competition.  

In December 2008, the dikes at TVA’s power station in Kingston, Tennessee containing wet coal combustion ash failed, and 5.4 million cubic yards of coal ash were released. The ash slurry flowed out from the site, impacting the adjacent Emory River In the aftermath, TVA committed more than $1 billion for the response, clean up, and site restoration. 

Stantec’s team was at Kingston within hours after the spill to assist TVA with emergency actions. As the recovery progressed, Stantec developed a site closure scheme, completed detailed engineering designs for a containment structure, and remained on-site to help with recovery efforts.  

Today, TVA has achieved several key milestones at Kingston. During the first two years after the spill, about three million cubic yards of ash dredged from the river was shipped by rail to a permitted, off-site landfill. Since then, the remainder of the released material has been excavated and stacked back inside the footprint of the failed impoundment facility. A two-mile long perimeter containment structure has been built around the new 240-acre ash landfill, which is being capped with a flexible membrane cover system.  In 2014, Stantec’s design was recognized by ACEC for engineering excellence.

The idea of placing large volumes of ash back within the failed area was met with initial skepticism, said officials. To prove it could be done without causing another failure, a test embankment was built across six acres of the failed dredge cell. Geotechnical instrumentation was installed to measure water pressures and movements within the underlying ash. Stantec established criteria and monitored conditions. In the end, more than 250,000 cubic yards of ash were safely stacked to a height of 45 feet above the failed surface. In addition to restoring confidence, the test program established protocols that would be followed throughout the project.

By far, the most difficult design challenge was how to contain the ash in the event of a large earthquake, said officials. Tennessee regulations require landfill facilities to withstand a 2500-year earthquake. Engineering analyses showed that these events would liquefy the sandy soils underlying the ash landfill.

Borrowing an approach used elsewhere to stabilize large embankment dams, Stantec designed a grid of buried walls that enclose the ash landfill. The engineering design was complex and required advanced numerical modeling of the seismic behavior, using both dynamic 2D and static 3D structural analyses. The design was subject to extensive independent review and regulatory oversight. The completed retaining structure, built to depths of 70 feet, is one of the largest walls of its type ever constructed in the U.S. 

Craig Zeller, EPA’s project manager at the site, sees how far the cleanup project has come. “It was a daunting project at the start. But five years later, after dredging, digging, and stacking ash day after day, week after week, the end is in sight. The project is on schedule. Ash is out of the river. The perimeter walls are done. The environmental restoration is underway. Kingston is a fantastic case study for a large-scale cleanup,” Mr. Zeller says.

TVA’s Kingston, Tennessee, Fossil Plant supplies power that is critical to the regional economy. On-site storage of the recovered ash, made possible with the perimeter containment structure, represents TVA’s best option for meeting both the economic and environmental goals of the project. The result has restored public confidence that a failure like the 2008 event would not happen again at Kingston, not even during a major natural disaster like an earthquake, said officials.



Patrick, Beard, Schulman And Jacoway, P.C. Attorneys Selected To 2016 Mid-South Super Lawyers List

Patrick, Beard, Schulman and Jacoway, P.C. announces that Richard A. Schulman, Michael A. Anderson, and Jeremy M. Cothern have been selected by their peers for inclusion in the Mid-South Super Lawyers for 2016. Each year, no more than five percent of the lawyers in the states of Arkansas, Mississippi, and Tennessee are selected by the research team at Super Lawyers to receive ... (click for more)

Hamilton County Emergency Communications District Implements Inform CAD, Mobile System

Hamilton County Emergency Communications District has gone live with Inform CAD and Mobile, a step in an upgrade of their emergency communications and response technology. Combining the new technologies in place at Hamilton County which include TriTech 911, which Hamilton County installed in 2014, Inform CAD, and Inform Mobile, provides the district with a modernized communications ... (click for more)

Signal Mountain Council Looking Into Taking Over Schools

A new group of Signal Mountain Town Council members is looking into taking over county schools within the town boundaries.   Two newly elected board members, Amy Speek and Dan Landrum, joined the council Friday afternoon at the first work session after the election. The election of mayor and vice mayor for the next two years came first on the agenda. Dick Gee, mayor ... (click for more)

East Ridge Meth Dealer Gets 168 Months In Federal Prison

A man that agents said was dealing large quantities of meth from his East Ridge residence has been sentenced to serve 168 months in federal prison. Kenneth Lemons appeared before Judge Curtis Collier. Agents said they made several controlled drugs buys from Lemons at his residence in 2015. On Oct. 27, 2015, he drove up to a residence where DEA agents were making a controlled ... (click for more)

Signal Mountain Couldn't Manage Public Education

I have been reading the buzz about Signal Mountain and other small municipalities considering a move to form their own school district within their municipal boundaries.  It is quite the comedy hour considering the notion that small cities that for decades could not even manage small sewer systems or 911 districts, are somehow going to do a better job with public education ... (click for more)

Roy Exum: Among The Worst In U.S.

Bobby Bragan, who was the first manager of Major League Baseball’s Braves when they moved from Milwaukee to Atlanta, had a great view on statistics: “Say you were standing with one foot in the oven and one foot in an ice bucket. According to the percentage people, you should be perfectly comfortable.” I am about to make you uncomfortable with some lousy statistics. Earlier this ... (click for more)