Weekly Road Construction Report

  • Thursday, April 16, 2015

Here is the weekly road construction report for Hamilton County: 

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street (Mid-State Construction Co, Inc.):  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead. This portion of the project is scheduled to be completed by this spring, at which time East Main Street will be reopened to traffic.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m. and 5 a.m. If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./JM/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is substantially complete and all lanes of traffic are open on U.S. 27.  Most of the remaining temperature-sensitive work on the project has been done too, including the paving of most of the local roads and widening the exit ramp from U.S. 27 North to Manufacturers Road.  As the weather improves, the contractor will complete the remaining items on the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is April.  [Wright Brothers Construction Co., Inc./JM/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be clearing, grubbing and installing erosion control measures.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Waterline work on Apison Pike is complete but the existing detours using Old Lee Hwy., Blue Bell Ave. and Bork Memorial Dr. will stay in place for the closure of Pattontown Road.  This closure is for the sewer bypass across Pattontown Road for manhole 2.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /KP/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project is underway.  The contractor will be clearing and installing erosion control measures.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /KP/CNN383] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor will be on eastbound Bonny Oaks Drive installing attenuators, extending the box culvert and installing erosion control measures.  The contractor will also begin clearing and grubbing on Volkswagen Drive at the first roundabout at the Amazon entrance.  There will be one lane of traffic northbound during work hours.  The contractor may have short term lane closures to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August.  [Talley Construction Company, Inc. /KP/CNN304]


Happenings
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
  • 3/28/2024

The Lightfoot Club of Chattanooga and the Mountain City Club of Chattanooga will begin the 2024 season of vintage base ball (yep, two words) on the historic 6th Calvary polo field (6 Barnhardt ... more

4 Bridges Arts Festival Returns April 20-21
  • 3/28/2024

The Association for Visual Arts will present the 24th Annual 4 Bridges Arts Festival at the First Horizon Pavilion on the southside of downtown Chattanooga this April. The festival will take ... more

Volunteers Needed for American Battlefield Trust Park Day
  • 3/28/2024

Chickamauga and Chattanooga National Military Park is seeking volunteers for American Battlefield Trust Park Day. Sign-up will begin at 9 a.m. on Saturday, April 6 at the intersection of Woodland ... more