Weekly Road Construction Report

  • Thursday, June 25, 2015

Here is the weekly road construction report for Hamilton County: 

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street (Mid-State Construction Co, Inc.):  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m.-5 a.m.  If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./JM/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is complete and awaiting final inspection.  Estimated project completion date is July.  [Wright Brothers Construction Co., Inc./JM/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be working on storm drains, conduits and grade work.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /KP/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have intermittent lane closures between 9AM-2PM in both directions on East Brainerd Road between Kinsey Drive and Fuller Road to perform utility work. This work will require installing road crossings and boring underneath the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /KP/CNN383] 

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project has begun.  There will be lane closures on Shepherd Road from 8 p.m.-6 a.m. on Monday through Thursday to allow the contractor to install the lane shift and restripe the project per the traffic control plan.  This will affect traffic northbound on Monday and Tuesday and southbound on Wednesday and Thursday.  Estimated project completion is October 2016.  [Jones Brothers Contractors, Inc./JM/CNP105] 

SR-317 (Bonny Oaks Drive) resurfacing from SR-17 (LM 0.00 near Hillcrest Elementary School) to west of Silverdale Road (LM 4.47):  Work on this project has begun.  The contractor will have lane closures throughout the project area from 6 p.m.-4:30 a.m. to mill for paving operations.  One lane of traffic will be open at all times.  Milling and paving operations are scheduled to begin on Monday evening, June 15, 2015.  Once the project gets started, milling and resurfacing operations will take place in the evenings between the hours of 6 p.m.-4:30 a.m.  Flaggers will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /KP/CNP108] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor will be on eastbound Bonny Oaks Drive at Volkswagen Drive excavating for a retaining wall and installing erosion control measures.  The contractor will also be on Volkswagen Drive working on the entrance and exit driveways to and from Amazon.  The contractor may have short term lane closures to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August.  [Talley Construction Company, Inc. /KP/CNN304] 

Happenings
Pothole Repairs Prompt Lane Closures On I-24 In Coffee County
  • 4/22/2024

Drivers traveling on I-24 in Coffee County should be aware of upcoming road construction activities that will have an impact on traffic. Tuesday and Wednesday, from 9 a.m. to 3 p.m., Tennessee ... more

Rabbit Valley Farmers Market In Ringgold Hosts 4th Annual Wine And Art April 27
  • 4/22/2024

The Rabbit Valley Farmers Market in downtown Ringgold will be hosting their 4th Annual Wine and Art in Ringgold Market this Saturday from 6-9 p.m. at 96 Depot St. in Ringgold. This event ... more

Tennessee Society Of Daughters Of American Colonists Elects Officers For 2024-2027 Term
Tennessee Society Of Daughters Of American Colonists Elects Officers For 2024-2027 Term
  • 4/22/2024

The Tennessee Society of the Daughters of the American Colonists met in Mount Juliet, Tn. for its annual conference. At the conference, the membership elected the slate of officers for the years ... more