Weekly Road Construction Report

  • Thursday, August 13, 2015

Here is the weekly road construction report for Hamilton County:

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street:  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m.-5 a.m.  If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./Micka/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is complete and the contractor is addressing punchlist items.  Additional resurfacing work has been added to this project to address the area of U.S. 27 north of the northern end of the project.  Weather permitting, the contractor will implement ramp closures from Signal Mountain Road north approximately 6,000 ft. between the hours of 7 a.m.-7 p.m. to mill and pave the main line of U.S. 27.  Southbound lane closures will start after 9 a.m. and northbound lane closures will end before 3 p.m. each day.  Estimated project completion date is August.  [Wright Brothers Construction Co., Inc./Micka/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be working on storm drains, conduits and grade work.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have intermittent lane closures between 9 a.m.-2 p.m. in both directions on East Brainerd Road between Kinsey Drive and Fuller Road to perform utility work. This work will require installing road crossings and boring underneath the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /Pruett/CNN383] 

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  One night during this report period, as yet to be determined, there will be nighttime lane closures between 8 p.m.-6 a.m. on SR-153 to allow the contractor to install a lane shift and remove and replace barrier rail as needed to mobilize a crane in the center work zone on SR-153.  The schedule of the closure is unknown pending approval of the FAA.  THP will assist with traffic control as necessary on the project.  Estimated project completion is October 2016.  [Jones Brothers Contractors, Inc./Micka/CNP105] 

SR-317 (Bonny Oaks Drive) resurfacing from SR-17 (LM 0.00 near Hillcrest Elementary School) to west of Silverdale Road (LM 4.47):  Work on this project continues.  The contractor will have lane closures throughout the project area from 6 p.m.-4:30 a.m. to place shoulder stone and final striping.  One lane of traffic will be open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /Pruett/CNP108] 

SR-153 resurfacing from east of Grubb Road (LM 10.85) to U.S. 27 (SR-29, LM 12.87):  Work on this project continues.  The contractor will have lane closures throughout the project area from 8 p.m.-6 a.m. on Sundays through Thursdays for paving operations.  One lane of traffic will be open at all times.  THP will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /Micka/CNP107] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor will be on Volkswagen Drive working on the entrance and exit driveways to and from Amazon.  On Monday through Thursday, the right lane on Volkswagen Drive between the first Amazon truck entrance and the roundabout will be closed to allow the contractor to perform concrete paving.  The contractor may have short term lane closures on eastbound Bonny Oaks Drive at Volkswagen Drive to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is December.  [Talley Construction Company, Inc. /Pruett/CNN304] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes may occur during this report period as necessary. Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2016.  [Diamond Specialized, Inc./Micka/CNP212] 

SR-58 resurfacing from south of SR-60 in Hamilton County (LM 25.97) to north of SR-306 in Meigs County (LM 4.59):  The contractor will have lane closure starting Monday from 7 a.m.-6 p.m. for paving operations.  One lane of traffic will remain open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October.  [Rogers group Inc. /Pruett/CNP156]

Happenings
Weekly Road Construction Report
  • 4/19/2024

Here is the weekly road construction report for District 29: BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will ... more

“GO LIVE” Summer Media Teen Camp Returns
“GO LIVE” Summer Media Teen Camp Returns
  • 4/19/2024

The City of Chattanooga’s Department of Community Development has partnered with Dynamo Studios to host the “GO LIVE” Summer Media Teen Camp, where participants can express their creativity and ... more

Crabtree Farms Plant Sale, Sculpture In The Sky Set This Weekend
  • 4/18/2024

Two annual springtime events will be taking place this weekend in Chattanooga. Crabtree Farms Plant Sale will be on Friday through Sunday from 9 a.m. until 3 p.m. each day. On Friday and Sunday, ... more