Weekly Road Construction Report

  • Thursday, August 27, 2015

Here is the weekly road construction report for Hamilton County:

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street:  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m.-5 a.m.  If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./Micka/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is complete and the contractor is addressing punchlist items.  Additional resurfacing work has been added to this project to address the area of U.S. 27 north of the northern end of the project.  Weather permitting, the contractor will implement ramp closures from Signal Mountain Road north approximately 6,000 feet between the hours of 7 a.m.-7 p.m. to mill and pave the main line of U.S. 27.  Southbound lane closures will start after 9 a.m. and northbound lane closures will end before 3 p.m. each day.  Estimated project completion date is August.  [Wright Brothers Construction Co., Inc./Micka/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be working on storm drains, conduits and grade work.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have intermittent lane closures between 9 a.m.- 2 p.m. in both directions on East Brainerd Road between Kinsey Drive and Fuller Road to perform utility work. This work will require installing road crossings and boring underneath the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /Pruett/CNN383] 

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  There are no scheduled lane closures on SR-153 during this report period.  THP will assist with traffic control as necessary on the project.  Estimated project completion is October 2016.  [Jones Brothers Contractors, Inc./Micka/CNP105] 

SR-317 (Bonny Oaks Drive) resurfacing from SR-17 (LM 0.00 near Hillcrest Elementary School) to west of Silverdale Road (LM 4.47):  Work on this project continues.  The contractor will have lane closures throughout the project area from 6 p.m.-4:30 a.m. for final striping.  One lane of traffic will be open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /Pruett/CNP108] 

SR-153 resurfacing from east of Grubb Road (LM 10.85) to U.S. 27 (SR-29, LM 12.87):  Work on this project continues.  The contractor will have lane closures throughout the project area from 8 p.m.-6 a.m. on Sundays-Thursdays for paving operations.  One lane of traffic will be open at all times.  THP will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /Micka/CNP107] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor will be on Volkswagen Drive working on the entrance and exit driveways to and from Amazon.  On Thursday and Friday the right lane on Volkswagen Drive between the first Amazon truck entrance and the roundabout will be closed to allow the contractor to perform concrete paving.  The contractor may have short term lane closures on eastbound Bonny Oaks Drive at Volkswagen Drive to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is December.  [Talley Construction Company, Inc. /Pruett/CNN304] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes may occur during this report period as necessary. Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2016.  [Diamond Specialized, Inc./Micka/CNP212] 

SR-58 resurfacing from south of SR-60 in Hamilton County (LM 25.97) to north of SR-306 in Meigs County (LM 4.59):  During this report period, the contractor will have lane closures from 7 a.m.-6 p.m. for milling and paving operations.  One lane of traffic will remain open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October.  [Rogers group Inc. /Pruett/CNP156]

Latest Headlines
Happenings
Michael Gerard Receives American Police Hall Of Fame Civilian Medal Of Appreciation
Michael Gerard Receives American Police Hall Of Fame Civilian Medal Of Appreciation
  • 3/18/2024

Collegedale officers responded to Garden Plaza of Greenbriar Cove on Sept. 21, 2023, after receiving a report of a missing elderly resident with dementia. The patient had left the facility approximately ... more

New Hamilton County Marriage Licenses
  • 3/18/2024

Here are the new marriage licenses from the County Clerk's office: SCOTT EDWARD KELLEY JAIMIE LYNN PASTORI 2205 JAMES AVE 4203 TENNESSEE AVE CHATTANOOGA, Tennessee 374156511 CHATTANOOGA, ... more

Chief John Ross DAR Presents Gold ROTC Medal
Chief John Ross DAR Presents Gold ROTC Medal
  • 3/18/2024

Chief John Ross Chapter, NSDAR had their March meeting on the 13th, and the meeting theme was Women’s History Month. Officials said, "Chapter member, Kay Sencabaugh, presented an entertaining ... more