Weekly Road Construction Report

  • Thursday, January 14, 2016

Here is the weekly road construction report for Hamilton County: 

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  On Thursday between 7 p.m.-6 a.m. the contractor will be paving between 12th Street and the Olgiati Bridge.  This work will require the left lane to be closed on U.S. 27 North and South. Once this is completed, traffic will be shifted toward the median on a semi-permanent basis to facilitate new construction along the outside shoulder in these areas.

 Also, pile driving is expected to get underway during this report period on the bridge over Riverfront Parkway (20th Street) on the south end of the project.  During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  Also, in order to continue work on the current phase project, TDOT contract crews have disconnected the street lighting within the 1.6 mile project area from the I 24 interchange to south of the Olgiati Bridge..  U.S. 27 in the project area will remain without street lighting until new lights are installed and activated during the latter stages of the project.  Motorists are advised to use caution as they travel through the construction area, particularly during nighttime hours.   THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  On the evenings of Wednesday and Thursday, Jan. 21, between 7 p.m.-6 a.m., Apison Pike will be closed near Blue Planet Foods to allow the contractor to install water services adjacent to the new roadway.  With excavation depths reaching 10 to 12 feet, a closure is necessary to ensure the safety of employees and the traveling public.  During this work, local residents who live within the work area and emergency vehicles will be allowed through.  A detour will be posted for all others.  Also during this report period, the contractor will be working on storm drains, conduits and grade work.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017.  [Mountain State Contractors, LLC /Pruett/CNN383] 

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  The old Shepherd Road bridge was demolished in November and traffic was switched to a portion of the newly-constructed bridge.  Traffic will be maintained and controlled by a temporary signal for the safety of the traveling public until February, when it is scheduled to be opened to two lanes.  On Wednesday and Thursday, Jan. 21, the contractor will be conducting daytime concrete pours on the Shepherd Road Bridge between 9 a.m.-3 p.m. that will require the bridge to be closed.  During this work, a pump truck and concrete trucks will be staging on the current bridge so no traffic can access the area until the work is completed.  SR-153 will remain open during this work.  Those wishing to get to the airport from SR-153 South will be able to use the Shepherd Road exit.  Those wishing to access the airport from SR-153 North will use the Shallowford Road exit.  Through January there will be intermittent nighttime lane closures as necessary in both directions on SR-153 between 8 p.m.-6 a.m.  THP will assist with traffic control as necessary on the project.  Estimated project completion is October.  [Jones Brothers Contractors, Inc./Micka/CNP105] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor may have short term lane closures on eastbound Bonny Oaks Drive at Volkswagen Drive to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is February.  [Talley Construction Company, Inc. /Pruett/CNN304] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  There will be no tunnel cleaning this week.  Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June.  [Diamond Specialized, Inc./Micka/CNP212]


Happenings
Alan Shuptrine Is Speaker At Moccasin Bend Chapter Of The NSDAR
Alan Shuptrine Is Speaker At Moccasin Bend Chapter Of The NSDAR
  • 4/16/2024

The Moccasin Bend Chapter of the National Society of the Daughters of the American Revolution held their monthly meeting at the Mountain Creek Church of Christ. Acclaimed watercolor artist ... more

North River Civic Center Has New Exhibit, Spring Into 2024
North River Civic Center Has New Exhibit, Spring Into 2024
  • 4/16/2024

The Spring Into 2024 Art Exhibit features local artists who participate in various art programs offered by the North River Civic Center, Department Of Community Development. There will be a grand ... more

Bidders For Critters Auction To Support Chattanooga Zoo Expansion
Bidders For Critters Auction To Support Chattanooga Zoo Expansion
  • 4/15/2024

The Chattanooga Zoo is hosting their inaugural Bidders for Critters online auction to raise funds for the Zoo’s ongoing Cape of Africa expansion. The auction, running from April 21-27, features ... more