Weekly Road Construction Report

  • Thursday, April 21, 2016

Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone has been lowered to 45 MPH.  The contractor may have temporary lane closures on U.S. 27 between 7PM-6AM.  

On Thursday evening, the contractor will implement temporary lane closures on U.S.

27 South from the Olgiati Bridge to the 12th Street Bridge and on U.S. 27 North from Market Street to the 12th Street Bridge between 7PM-6AM for repairing asphalt and restriping travel lanes.  This work will require multiple lane shifts and traffic will be moved around throughout the night to facilitate the paving.  All exit and entrance ramps will remain open.  

On Monday evening, April 25 and Tuesday evening, April 27, the contractor will implement temporary ramp closures at MLK Blvd. between 7PM-6AM to install storm drains under MLK Blvd. The on-ramp to U.S. 27 North from westbound MLK Blvd. and the on-ramp to U.S. 27 South from westbound MLK Blvd. will be affected.  Westbound MLK Blvd will be closed from Chestnut Street to west of U.S. 27, and traffic can detour via Chestnut Street – 6th Street – Gateway Avenue. Eastbound MLK Blvd. will have a temporary left lane closure from the U.S. 27 overpass to Chestnut Street.  The Northbound US 27 off-ramp to MLK Blvd will allow right turns only.  Motorists can also use the 4th Street interchange as an alternate route to/from the downtown area.

On Wednesday evening, April 28, and Tuesday evening, April 27, the contractor will implement temporary ramp closures at MLK Blvd. between 7PM-6AM to install storm drains under MLK Blvd. The off-ramp from U.S. 27 South to eastbound MLK Blvd. and the on-ramp to U.S. 27 North from eastbound MLK Blvd. will be affected.  Eastbound MLK Blvd. will be closed from west of the U.S. 27 overpass to Chestnut Street, and traffic can detour via Chestnut Street – 6th Street – Gateway Avenue.  The U.S. 27 North off-ramp to MLK Blvd will allow right turns only.  Motorists can also use the 4th Street interchange as an alternate route to/from the downtown area.  Traffic on U.S. 27 North will detour to the 4th Street ramp.   

As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230]

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will close a portion of Apison Pike to through traffic near LaCollina Way beginning on Wednesday April 27, 2016 at 7PM through Friday April 29, 2016 at noon to install box culverts under Apison Pike. Detours will be posted.  Any emergency vehicles that need access through the work zone area will be allowed through.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279]

SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have intermittent lane closures during this report period between 9AM-2PM.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017.  [Mountain State Contractors, LLC /Pruett/CNN383]

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  The bridge has returned to two lanes of traffic.  During this report period, the contractor will continue retaining wall and widening work on the Airport Connector Road west of the Shepherd Road Bridge.  This work will require that the shoulder and right travel lane heading to the airport on Shepherd Road be closed.  This change should only affect those turning right at the top of the ramp from SR-153 South, as they will not have a designated lane to the airport during this work.  In the coming week or weeks we may need to close the right shoulder and lane of eastbound Airport Connector Rd. (leaving the airport and going toward SR-153). Traffic should not be impacted other than flagging to let trucks enter and exit the work zone.  We will have signs and a message board alerting motorists to the change in traffic pattern.  The through lane from the bridge will remain unobstructed except for the occasional flagging for equipment to move in and out.  During the project, there may be intermittent nighttime lane closures as necessary in both directions on SR-153 between 8PM-6AM EST.  THP will assist with traffic control as necessary on the project. Estimated project completion is October 2016.  [Jones Brothers Contractors, Inc./Micka/CNP105]

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures on Bonny Oaks Drive at Volkswagen Drive to perform pavement stabilization operations between 8:30AM and 4PM. The contractor may have short term lane closures on eastbound Bonny Oaks Drive at Volkswagen Drive to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is April 2016.  [Talley Construction Company, Inc. /Pruett/CNN304]

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  There will be no tunnel cleaning this week.  Work hours are between 8PM-6AM.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2016.  [Diamond Specialized, Inc./Micka/CNP212]


Happenings
Gallery At Blackwell Announces Summer Show And Opening Reception May 10
  • 4/23/2024

The Photographic Society of Chattanooga will hold a reception at the Gallery at Blackwell on Friday, May 10 from 6-8 p.m. to present the summer show. Refreshments will be provided and the public ... more

In-Town Gallery 50th All Member Show Featured In May
In-Town Gallery 50th All Member Show Featured In May
  • 4/23/2024

In-Town Gallery has many events planned during this, their 50th anniversary year. In May, Art After Hours features In-Town Gallery’s All Member Show. Each May and November, the artists of ... more

Pothole Repairs Prompt Lane Closures On I-24 In Coffee County
  • 4/22/2024

Drivers traveling on I-24 in Coffee County should be aware of upcoming road construction activities that will have an impact on traffic. Tuesday and Wednesday, from 9 a.m. to 3 p.m., Tennessee ... more