TDOT Region Two Weekly Roadway Activity Report

  • Thursday, June 16, 2016

Weekly Roadway Activity Report for TDOT Region 2 (Parts of East and Middle Tennessee)
June 16, 2016 – June 22, 2016

Construction Projects
Maintenance / Regionwide / On-Call / Multi-County Contracts

Bledsoe County, SR-30 slide repair project near log mile 7.5:  Work on this project will begin during this report period.  The contract includes excavating, stabilizing and rebuilding the road at the site of a recent slope failure.  Due to the magnitude of the project, the contractor will close SR-30 to all traffic at the project site beginning on Monday, June 20, 2016.  The closure will be in effect through July 31, 2016 to allow the contractor enough room to make the necessary repairs to the road.  Detours will be posted during the closure of SR-30.  On August 1, 2016, the road will be opened to one lane under the control of a temporary traffic signal.  The road will remain in this configuration through the month of August, after which it will be reopened to two lanes.  The estimated completion date for the entire project is August 2016.  [Dement Construction Co., LLC/Voiles/CNQ219]

Bradley and McMinn counties, I-75 resurfacing from north of Hooper Gap Road overhead bridges in Bradley County (MM 31) to south of the bridge over County Road 50 in McMinn County (MM 39):  Work on this project continues.  During this report period, there will be temporary lane closures on I-75 North and South for milling and paving operations.  Temporary lane closures for paving operations will only be allowed from Sunday through Thursday evenings between 7PM and 6AM.

 One lane will remain open at all times during the work. 
Temporary lane closures for bridge work will be allowed on weekends from 7PM Friday until 6AM Monday.  The contractor will be allowed eight weekends to complete the bridge repairs.  No lane closures will be allowed on holiday weekends or during local festivals or events.  THP will assist with traffic control on the project as necessary.  Estimated project completion is August 2016.  [Rogers Group, Inc./Curtis/CNP278]

Bradley County, I-75 grading, drainage, construction of retaining walls and paving at Exit 25 (State Route 60) interchange in Cleveland, including the installation of traffic signals:  Work on this project continues.  During this report period, there will be intermittent lane closures as the contractor works on the soil nail retaining wall.  Estimated project completion is summer 2016.  [Steve Williams Construction, LLC./Curtis/CNN323]

Bradley County, U.S. 74 (SR-311, APD-40) construction of a new interchange between I-75 (Exit 20) and U.S. 11/64 (SR-2) at Stone Lake Extension in Cleveland:  Work on this project continues.  Traffic has been shifted onto the right shoulder on APD-40.  The speed limit on SR-311 in the construction zone has been lowered to 45 MPH.  Traffic needs to be aware of trucks entering and exiting on the southbound lanes of APD-40.  Flaggers will assist with traffic control as needed.  Estimated project completion date is October 2016.  [Talley Construction Co., Inc./Curtis/CNN307]

Cannon County, SR-145 (Auburntown Rd.) bridge repair over Rush Creek (LM 1.43):  Work on this project continues.  The contractor closed the bridge to traffic on Wednesday, June 8, 2016, and it is expected to reopen by June 29, 2016.  Message boards are in place to give information on detours throughout the closure.  Motorists should use caution and be alert to construction equipment and vehicles within the work zone.  Estimated project completion date is July 2016.  [Jones Brothers Construction, LLC/Parnham/CNQ046]

Coffee County, I-24 grading, drainage, retaining/barrier walls and paving with Portland Cement concrete at the SR-55 interchange near MM 111:  Work on this project continues.  The outside shoulder on I-24 East will be closed on Monday through Saturday between the hours of 6AM and 6PM.  SR-55 in the area of the project will also be reduced from two lanes to one lane every day.  Estimated project completion date is July 2016.  [Civil Constructors, LLC./Parnham/CNP265]

Coffee County, grading, drainage and paving on a State Industrial Access route serving Omar, Inc. at the Joint Industrial Park:  This project is in final clean up and the contractor is doing pre-final work for inspection.  Estimated project completion date is June 2016.  [Rogers Group, Inc./Parnham/CNP262]

Coffee, Grundy and Marion counties, I-24 expansion of rural TDOT SmartWay Intelligent Transportation System (ITS) from MM 109 to MM 157:  Work on this project continues.  There will be no lane of shoulder closures during this report period.  There may be daytime or nighttime shoulder and short term lane closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is June 2016.  [Stansell Electric Company, Inc./Parnham/CNN205]

Cumberland County, I-40 cold planing/resurfacing (mm 317.87 to mm 322.38) including Obed River Bridge repair (LM 13.54) and installation of traffic count station loops:  Work on this project continues.  Construction signs have been installed.  The speed limit on I-40 will be reduced from 70 mph to 60 mph for the duration of the project.  The contractor will be performing resurfacing and bridge repair activities and will temporarily close one lane to traffic during these operations.  Temporary lane closures for resurfacing activities will only be allowed from Sunday through Thursday evenings between 7PM and 6AM.  No lane closures will be allowed on holiday weekends or during local festivals or events.  All lane closures will be supported by State Troopers and queue trucks.  Estimated project completion date is August 2016.  [Rogers Group, Inc./Bradley/CNP299]

Cumberland County, SR-101 (Peavine Road) utility relocation from Firetower Road to east of Westchester Drive/Catoosa Boulevard:  Work on this project has begun.  The first phases of work for this project will involve erosion control and clearing activities which will have only minor impact to traffic on SR-101 (Peavine Road).  Estimated project completion date is June 2017.  [Davis H. Elliot Construction Company, Inc./Bradley/CNQ922]

DeKalb County, SR-26 (U.S. 70) construction of a welded steel plate girder bridge and three retaining walls over the Caney Fork River and Sligo Road (LM 24.58):  This project is complete pending final inspection.  Estimated project completion date is June 2016.  [Massman Construction Co./Sorrelle/CNM073]

DeKalb County, SR-141 slide repair between log mile 0.93 and log mile 1.10, including grading, drainage and paving:  Work on this project continues.  The roadway is closed to traffic for the safety of the traveling public due to the instability of the roadway.  The contractor has completed the placement of the binder mix and will be completing the barrier wall during this period.  The contractor will be placing topping mix, erecting guardrail and placing final layer of shoulder stone from June 16, 2016 through June 26, 2016.  Estimated project completion date is June 2016.  Estimated project completion date is June 2016.  [Jones Brothers, Inc./Sorrelle/CNP006]

District 27 (Cumberland, Fentress, Overton, Pickett, Putnam, and White counties) crack sealing on various state routes:  Work on this project is underway.  Short term lane closures will be established with flaggers and other traffic control devices as necessary during crack sealing operations.  Estimated project completion date is July 2016.  [American Stripers, LLC/Bradley/CNQ067]

FENTRESS COUNTY, SIA route serving Clarkrange Regional Business Park:  A Notice of Termination has been obtained for this project and final inspection will be scheduled.  Traffic will not be affected at this time.  Estimated project completion is June 2016.  [Twin K Construction,/Bradley/CNP228]

Franklin county, U.S. 41A (SR-16) bridge repair over Boiling Fork Creek at log mile 12.73 (near downtown square, Winchester):  Work on this project continues.  Continuing until July 15, 2016, the bridge will be reduced from two lanes in each direction to one lane in each direction to allow the contractor an area in which to safely work.  Traffic will be affected on U.S. 41A (SR-16) between Porter Street and Sharp Springs Road.  Estimated project completion date is August 2016 [Mid-State Construction Co., Inc./Parnham/CNP311]

Franklin County, SR-50 grading, drainage, and paving from SR-50 to U.S. 64 (SR-15) in Winchester:  Work on this project continues.  The ramps leading from SR-16 to U.S. 64 (SR-15) at the four-way stop are closed to aid in the construction of the roundabout.  The construction of concrete islands and curbs for the roundabout at the intersection of State Route 50 and State Route 16 are currently underway.  In the meantime, traffic has be diverted onto SR-16 and then onto U.S.64, making for a detour of approximately ¼ mile in length.  Traffic has also been diverted onto the new tie-in to Joyce Lane.  Grading activities are ongoing from Wilton Circle to State Route 50.  In the coming month construction activities for the retaining walls, one in front of the National Guard Armory and one in front of the Justice Center, will commence.   Estimated project completion date is April 2017.  [Dement Construction Co., LLC./Parnham/CNP097]

Grundy and Putnam counties, longitudinal joint stabilization on various interstate routes:  Beginning on May 22, 2016 the contractor will be performing joint stabilization on I 24 in Grundy County from MM 131.56 – MM 134.27.  They will then move to I40 in Putnam County from MM 281.32 – MM 286.92.  The work will be done between 6PM – 6AM.  This will be a mobile operation.  THP will assist with traffic control.  Estimated project completion date is July 2016.  [Pavement Technology, Inc./Voiles/CNP281]

HAMILTON COUNTY, U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone has been lowered to 45 MPH.  The contractor may have temporary lane closures on U.S. 27 between 7PM-6AM.  As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230]

Hamilton County, SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period, the contractor will be working on storm drains, conduits and grade work.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as neededEstimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279]

Hamilton County, SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have one lane of East Brainerd Road closed between Grays Road and McNichol Lane on Friday evening June 17, 2016 at 8PM until Saturday, June 18, 2016 at noon to install a box culvert.  A flagging operation will be in place to assist with traffic control.  The contractor will have intermittent lane closures during this report period between 9AM-2PM.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017.  [Mountain State Contractors, LLC /Pruett/CNN383]

Hamilton County, Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  The bridge has returned to two lanes of traffic.  During this report period, the contractor will continue retaining wall and widening work on the Airport Connector Road west of the Shepherd Road Bridge.  This work will require that the shoulder and right travel lane heading to the airport on Shepherd Road be closed.  This change should only affect those turning right at the top of the ramp from SR-153 South, as they will not have a designated lane to the airport during this work.  In the coming week or weeks we may need to close the right shoulder and lane of eastbound Airport Connector Rd. (leaving the airport and going toward SR-153). Traffic should not be impacted other than flagging to let trucks enter and exit the work zone.  We will have signs and a message board alerting motorists to the change in traffic pattern.  The through lane from the bridge will remain unobstructed except for the occasional flagging for equipment to move in and out.  During the project, there may be intermittent nighttime lane closures as necessary in both directions on SR-153 between 8PM-6AM EST.  THP will assist with traffic control as necessary on the project.  Estimated project completion is October 2016.  [Jones Brothers Contractors, Inc./Micka/CNP105]

Hamilton County, the tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  There will be no tunnel cleaning this week.  Work hours are between 8PM-6AM.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2016.  [Diamond Specialized, Inc./Micka/CNP212]

McMinn County, SR-39 construction of a concrete box beam bridge over Chestuee Creek (LM 15.68), including grading, drainage and paving:  Work on this project continues.  Traffic has been restored to two lanes on the bridge.  The project is complete pending completion of the punchlist items.  Estimated project completion is June 2016.  [Simpson Construction Co., Inc./Curtis/CNP011]

McMinn County, SR-163 construction of a State Industrial Access road serving Resolute Forest Products in Calhoun, including grading, drainage and paving:  Work on this project continues.  There will be flaggers on SR-163 as the contractor works to install barrier rails and to shift traffic.  Also the contractor will be clearing the roadway.  Estimated project completion is July 2016.  [Greenstar LLC/Curtis/CNP309]

Overton County, SR-52 grading, drainage, signals and paving from near Oakley-Allons Road (LM 6.58) to DR-111 (LM 10.23):  Work on this project continues.  The contractor may have short term lane closures on the project to perform various operations on as-needed basis.  Estimated project completion date is July 2018.  [J&M Grading Division, LLC/Ray/CNP114]

Polk County, U.S. 64 (SR-40) construction of a concrete bulb-tee beam bridge over Maddens Branch (LM 11.06), including grading, drainage and paving:  Work on this project continues.  The temporary traffic signal has been removed from the project and traffic has been restored to two lanes.  Traffic has been shifted onto the new bridge at Maddens Branch to start on the second phase of the new Maddens Branch Bridge.  The travel lanes across the phase 1 Maddens Branch Bridge are 10 feet wide.  Drivers are urged to slow down and use caution in this area because of the narrow lanes.  Estimated project completion is October 2016.  [Simpson Construction Co., Inc./Curtis/CNP016]

Putnam County, I-40 grading, drainage, construction of two concrete Bulb-Tee beam bridges, signals and paving at Mine Lick Creek Road (L.M. 15.56) and construction of a State Industrial Access Road (Mine Lick Creek Road) serving Project Victor, including grading, drainage and paving:  Work on this project continues. The contractor continues with grading operations on the north section of the project that includes Bennett Road, Hawkins Crawford Road and Mine Lick Creek Road.  The contractor is placing falsework forms and tying rebar for the box bridges at Bennett Road.  Work continues on the box culverts on Mine Lick Creek Road and a nearby ramp.  The contractor has completed placement of steel H piles for Bridges 1 & 2.  The contractor will continue to pour the abutments for Bridge 1, Phase 1 on I-40 East during this period.  All motorists are advised to observe the posted reduced speeds when entering the work zone and be alert to construction personnel, equipment and vehicles.  Flaggers will assist with traffic control as necessary.  Estimated project completion date is October 2017.  [Charles Blalock & Sons, Inc./Sorrelle/CNP247]

Putnam County, Construction of a State Industrial Access Road (Bennett Road) serving Project Victor, including grading, drainage and paving:  Work on this project continues.  The traffic shift at Bennett Road has been completed.  Lee Seminary Road is now closed to traffic at the intersection of Bennett Road.  All motorists are advised to use the detour from Lee Seminary Road to Highland Park Boulevard.  All motorists should use caution and be alert to construction equipment and vehicles on the project.  Estimated project completion is June 2016.  [Vaughn Contractors, Inc./Sorrelle/CNP195]

Van Buren County, SR-111 grading, drainage, and paving from south of Manus Road to south of SR-285 near Double Bridge Road:  Work on this project continues.  Grading and blasting operations continue and the contractor is addressing the slope with removal of unsuitable material and installing graded solid rock within the construction zone.  Motorists should expect periodic delays.  As part of the progression of the project, the contractor has implemented a new traffic control plan that has reduced the highway from three lanes to two lanes within the construction zone.  The lanes are 12 ft. wide with little to no shoulder.  Flaggers will be present during progression of work.  Motorists should use caution and be alert to construction equipment and vehicles within the work zone. The speed limit has been reduced to 45 MPH and is being enforced.  Estimated project completion date is December 2016.  [Jones Bros., Inc./Parnham & Price/CNM266]

WArren County, U.S. 70S (SR-1) resurfacing from SR-55 (LM. 10.69) to west of the bridge over the Collins River (LM 14.90) in McMinnville;  There will be no lane closures during this report period.  Estimated completion date for the project is June 2016.  [Tinsley Asphalt, LLC/Parnham/CNP161]

White County, SR-84 repair of bridge over Calfkiller River (LM 1.58):  Work on this project continues.  The contractor has completed Phase 1 of the bridge repair and will begin work on Phase 2 during this period.  All motorists should use caution and be alert to construction equipment and vehicles on the project.  Estimated project completion date is July 2016.  [Mid-State Construction Co., Inc./Sorrelle/CNP302]

Region 2-random on-call pavement marking on various interstate and state routes:  The contractor has completed the pavement marking and reflectivity testing portions of this contract.  An additional call-out will be administered for various locations in Putnam and Cumberland counties and is to be completed by June 30, 2016.  Contract completion date is June 2016.  [Reynolds Sealing and Striping, Inc./Sorrelle/CNP021]

REGION 2 random on-call pavement marking on various interstate and state routes:  Work on this project is expected to begin shortly after July 4, 2016.  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 at nighttime or during non-peak daytime hours in order to install pavement markings.  Contract completion date is September 2016.  [Reynolds Sealing & Striping, Inc./Sorrelle/CNQ063]

REGION 2 retracing of painted pavement marking lines on various Interstate and State Routes:  Work on this project is expected to begin around July 6, 2016.  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 at nighttime or during non-peak daytime hours in order to retrace painted pavement markings.  Contract completion date is September 2016.  [Reynolds Sealing & Striping, Inc./Sorrelle/CNQ063]

Region 2-on-call cable guardrail repair:  The contractor may have short term shoulder and/or lane closures in order to perform cable barrier system repair.  Work hours are 7PM-6AM.  At least one travel lane will remain open to traffic at all times.  Contract completion date is December 2016.  [R.D. Construction, LLC/Pruett/CNP274]

Region 2-on-call guardrail repair: The contractor may have short term shoulder and/or lane closures in order to perform guardrail installation. The contractor may also have short term daytime shoulder and/or lane closures during non-peak hours to perform random on-call repairs in various counties.  At least one travel lane will remain open to traffic at all times.  Contract completion date is June 2016.  [Cumberland Guardrail, Inc./Pruett/CNP143]

Region 2-on-call sweeping and drain cleaning on various interstates and state routes:  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 at nighttime or during non-peak daytime hours in order to sweep and clean drains.  Contract completion date is February 2017.  [Blevins Enterprises, Inc./Micka/CNP325]

Region 2-on-call concrete repair on various interstates and state routes:  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 as necessary to perform concrete repair work.  Contract completion date is March 2017.  [Palmertree Construction Co., Inc./Voiles/CNP327]

Region 2 random on-call sign repair on various interstates and state routes:  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 in order to install new signs.  THP will assist with traffic control as necessary.  Contract completion date is June 2016.  [Law Signs, LLC/Voiles/CNP213]

Region 2 installation of emergency reference markers on interstates:  The contractor will have short term shoulder and/or lane closures at various locations in Region 2 in order to install emergency reference markers.  A minimum of one lane will remain open in each direction.  All lane closures will no more than 2 miles long, per closure, as per TDOT requirements.  Contract completion date is July 2016.  [Superior Traffic Control/Voiles/CNP329]

 

TDOT Operations/Maintenance Work and TDOT Bridge Inspections (TDOT Forces)

Bradley and McMinn counties, I-75 North and South from mile marker 16 to mile marker 60 chemical weed control:  TDOT Operations crews will perform chemical weed control during this weekend on I-75 North and South between mile markers 16 and 60 (from the Bradley County Line to the Monroe County Line in both directions).  On Saturday, June 18, 2016 the operation will consist of a mobile operation in the inside lane.  The work will take place beginning at 7AM and ending at 1PM or earlier if traffic gets too heavy. In addition to performing the work, regional Operations crews will also provide traffic control.  [Patterson]

Hamilton County, I-75 North and South concrete slab stabilization from MM 6 to MM 10:  TDOT Operations crews will be performing nighttime concrete slab stabilization on I-75 between mile markers 6 and 10.  Work will begin on Sunday night, June 5, 2016 on I-75 North.  Once work is completed on the northbound side, the contractor will work on I-75 South.  Temporary lane closures for slab stabilization operations will only be allowed from Sunday through Thursday evenings between 9PM and 5AM.  Two lanes will remain open at all times during the work.  THP will assist with traffic control.  The work should be completed in two weeks.  Estimated project completion is June 16, 2016.  [AFS/TDOT Operations]

 Putnam County, I-40 East and West at mile marker 267.27 and mile marker 291.43 bridge inspection:  The TDOT Region 2 Bridge Inspection team will conduct regular inspections of the bridges on I-40 East and West in Putnam County during this report period.  On Monday, June 20, 2016, they will be at the bridges at mile marker 267.27.  On Tuesday, June 21, 2016 they will be at the bridges at mile marker 291.43.  This work will take place each day between 9AM – 11:30AM.  The team will begin their inspections on the westbound side of the interstate, and then continue their inspections on the eastbound side.  During the inspections, the team will require the outside (right) lane to be closed near the bridge that is under inspection.  This work is weather dependent.  Should this work be postponed by weather, it will be rescheduled to take place on the next available day.  TDOT Operations will assist with traffic control.  [TDOT Bridge Inspection]

Rhea County, SR-68 slide repair and soil stabilization at log mile 5.6:  Work on this project continues.  The roadway is one lane signal controlled until the project is complete.  [GSI]

Region 2-Mowing and Brush Removal: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to perform contract mowing and brush removal on an as-needed basis.  In addition to performing the work, regional Operations crews will also provide traffic control.

Region 2-Drainage Work:  There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis.  One lane will be maintained at all times.  In addition to performing the work, regional Operations crews will also provide traffic control.

Region 2-Pothole Repair and Pavement Patching:  There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis.  Depending on location and severity these repairs may be done during the day or at night.  In addition to performing the work, regional Operations crews will also provide traffic control.

 

Non-TDOT Work

None to report.

 

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors.  Most work is weather dependent and subject to change due to inclement weather.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT’s other Twitter pages

As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination.  Drivers should never tweet, text or talk on a cell phone while behind the wheel.

  

Latest Headlines
Happenings
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
  • 3/28/2024

The Lightfoot Club of Chattanooga and the Mountain City Club of Chattanooga will begin the 2024 season of vintage base ball (yep, two words) on the historic 6th Calvary polo field (6 Barnhardt ... more

4 Bridges Arts Festival Returns April 20-21
  • 3/28/2024

The Association for Visual Arts will present the 24th Annual 4 Bridges Arts Festival at the First Horizon Pavilion on the southside of downtown Chattanooga this April. The festival will take ... more

Volunteers Needed for American Battlefield Trust Park Day
  • 3/28/2024

Chickamauga and Chattanooga National Military Park is seeking volunteers for American Battlefield Trust Park Day. Sign-up will begin at 9 a.m. on Saturday, April 6 at the intersection of Woodland ... more