Weekly Road Construction Report

  • Thursday, July 14, 2016

Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues.  The speed limit on U.S. 27 in the construction zone has been lowered to 45 MPH. The contractor may have temporary lane closures on U.S. 27 between 7PM-6AM. As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area. Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges. Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North. Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street. At least one lane will remain open in each direction on U.S. 27. THP will assist with traffic control on the project as necessary. Estimated project completion date is July 2019. For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga. [Dement Construction Co., LLC/JM/CNP230]

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84): Work on this project continues. During this report period, the contractor will have nighttime closures on Apison Pike between Ooltewah-Ringgold Road (SR-321) Little Debbie Parkway between the hours of 8PM and 6AM the following morning on the evenings of Thursday and Friday to install water and sewer lines. McKee tractor trailers will be allowed through the work zone during this work. Detours for all other traffic will be marked. Also during this report period the contractor may have intermittent lane closures from 9 a.m.-4 p.m. Flaggers will assist with traffic control as needed. Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279]

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road: Work on this project continues. Beginning on Friday at 8 p.m. through Saturday at noon, the contractor will have one lane closed on East Brainerd Road between Grays Road and McNichol Lane for box culvert installation. The contractor will have intermittent lane closures during this report period between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings. The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed. Estimated project completion is June 2017.  [Mountain State Contractors, LLC /Pruett/CNN383]

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Road to Shaw Avenue in Chattanooga, including grading, drainage and paving: Work on this project continues. The bridge has returned to two lanes of traffic. On weekdays during this report period, the contractor will be doing asphalt paving on the Airport Connector Road west of the Shepherd Road Bridge and at the ramp intersections. The work will take place during daytime hours and traffic will be maintained through the work zone with flaggers and lane shifts. This paving will allow the contractor to shift traffic onto the concrete ramp pavement in the coming weeks so that they can construct phase 2 of the ramps. Please anticipate short delays and use extra caution though the work zone. Estimated project completion is October. [Jones Brothers Contractors, Inc./Micka/CNP105]


Happenings
Gallery At Blackwell Announces Summer Show And Opening Reception May 10
  • 4/23/2024

The Photographic Society of Chattanooga will hold a reception at the Gallery at Blackwell on Friday, May 10 from 6-8 p.m. to present the summer show. Refreshments will be provided and the public ... more

In-Town Gallery 50th All Member Show Featured In May
In-Town Gallery 50th All Member Show Featured In May
  • 4/23/2024

In-Town Gallery has many events planned during this, their 50th anniversary year. In May, Art After Hours features In-Town Gallery’s All Member Show. Each May and November, the artists of ... more

Pothole Repairs Prompt Lane Closures On I-24 In Coffee County
  • 4/22/2024

Drivers traveling on I-24 in Coffee County should be aware of upcoming road construction activities that will have an impact on traffic. Tuesday and Wednesday, from 9 a.m. to 3 p.m., Tennessee ... more