Weekly Road Construction Report

  • Thursday, August 18, 2016

Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone has been lowered to 45 MPH.  The contractor may have temporary lane closures on U.S. 27 between 7 p.m.-6 a.m.PM-6AM.  The contractor will be setting bridge beams on the project during the next two weeks.

 Prior to beams being set, the contractor will need to stage the trucks carrying the bridge beams, and this will require a shoulder closure on U.S. 27 North from Market Street to Broad Street.  On Tuesday night, from 7 p.m.-6 a.m., the contractor will have temporary road and ramp closures to set bridge beams over MLK Blvd.  Motorists should use the 4th Street interchange as an alternate route to/from the downtown area.  Local street detours will be posted via Broad Street – 6th Street – Gateway Avenue.  As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures from 9 a.m.-4 p.m.   Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017.  [Mountain State Contractors, LLC /Pruett/CNN383] 

Shepherd Road over SR-153 construction of a rolled steel girder bridge from West Shepherd Rd. to Shaw Avenue in Chattanooga, including grading, drainage and paving:  Work on this project continues.  The bridge has returned to two lanes of traffic.  Traffic has now been shifted onto the south side of the new bridge.  During the project, there may be intermittent nighttime lane closures as necessary in both directions on SR-153 between 8 p.m.-6 a.m.  THP will assist with traffic control as necessary on the project.  On weekdays during this report period, the contractor will be doing asphalt paving on the Airport Connector Road west of the Shepherd Road Bridge and at the ramp intersections.  The work will take place during daytime hours and traffic will be maintained through the work zone with flaggers and lane shifts.  This paving will allow the contractor to shift traffic onto the concrete ramp pavement in the coming weeks so that they can construct phase 2 of the ramps.  Please anticipate short delays and use extra caution though the work zone.  Estimated project completion is October.  [Jones Brothers Contractors, Inc./Micka/CNP105]


Happenings
Crabtree Farms Plant Sale, Sculpture In The Sky Set This Weekend
  • 4/18/2024

Two annual springtime events will be taking place this weekend in Chattanooga. Crabtree Farms Plant Sale will be on Friday through Sunday from 9 a.m. until 3 p.m. each day. On Friday and Sunday, ... more

Hamilton County Sheriff Gives Update At Friends Of Hixson Coffee Meeting
Hamilton County Sheriff Gives Update At Friends Of Hixson Coffee Meeting
  • 4/18/2024

At the Friends of Hixson Coffee Meeting, Hamilton County Sheriff Austin Garrett updated a large crowd on his first two years as Sheriff and his recent visit to the southern border. Sheriff ... more

Review: The Unvanquished: The Untold Story Of Lincoln's Special Forces, The Manhunt For Mosby's Rangers, And The Shadow War That Forged America's Special Operations By Patrick O'Donnell
Review: The Unvanquished: The Untold Story Of Lincoln's Special Forces, The Manhunt For Mosby's Rangers, And The Shadow War That Forged America's Special Operations By Patrick O'Donnell
  • 4/18/2024

Anyone who has read any of Patrick K. O'Donnell's narrative histories knows that he does very deep research, much of it on the front lines and at the sites, as well as reading volumes in little-known ... more