Weekly Road Construction Report

Friday, May 19, 2017

Here is the weekly road construction report for Hamilton County: 

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  On weekdays during this report period between the hours of 9 a.m.3-p.m., the contractor will have a temporary right lane closure on eastbound MLK Blvd. between the U.S. 27 North exit ramp and Carter St. and on westbound MLK Blvd. between Chestnut St. and the U.S. 27 North entrance ramp to work on new signals.  Ramp traffic will not be affected.  This work is weather permitting.  As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m. Flaggers will assist with traffic control as needed.  Estimated project completion date is May. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.- 2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Road/East Brainerd Road intersection, allowing the contractor to work on the other side of the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Original completion date is June. Estimated project completion date is December. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues. The outside lanes in both directions on the bridge on Hixson Pike over SR-153 are now closed.  This lane closure will be in place until late November.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 p.m.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

U.S. 27 (SR-29) resurfacing from north of Signal Mountain Road (LM. 3.02) to north of SR-29 (MM. 6.0/LM 6.07):  Work on this project has begun.  The contractor will have temporary intermittent lane closures on Sundays through Thursdays between the hours of 8 p.m. each evening to 6 a.m. the following morning to mill and pave the roadway.  THP and flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is June. [Wright Brothers Construction Co, Inc./Micka/CNQ189] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June.  [Diamond Specialized, Inc./Micka/CNQ174]




Hospice Of Chattanooga Hosts Memorial Service For Those Grieving Loss Of Loved Ones

Hospice of Chattanooga is hosting a memorial service on  Sunday, Aug. 26, for anyone who has gone through the death of a loved one. This service is for all in the community, who are experiencing grief, regardless of whether their loved one died under hospice's care or not.  The service will begin at  2 p.m  at First Christian ... (click for more)

John Shearer: Seeing New Green Space And Building At Baylor

In recent years, I have occasionally enjoyed taking a jog at my alma mater of Baylor School during school vacation times or weekends to reminisce a little and enjoy again the pretty campus I love by the Tennessee River.   But late  Friday  afternoon when I was over there before the onslaught of students, I wanted to see something new – the former quadrangle/quad ... (click for more)

City To Delay Proposal To Surplus 3 Buildings Near City Hall

City officials said Tuesday they will delay action on the proposal to surplus three buildings near City Hall. Stacy Richardson, chief of staff to Mayor Andy Berke, said the staff still does not have all the answers to questions raised about the plan. She said the staff is still convinced that moving the buildings to the private market as part of the Innovation District would ... (click for more)

Hearing Delay On Suit Brought By State Democrats To Keep Robin Smith Off Ballot

A hearing has been delayed on a lawsuit brought by the Tennessee Democratic Party seeking to keep Republican Robin Smith off the ballot in House District 26. Ms. Smith was the only candidate after longtime Rep. Gerald McCormick abruptly announced he was leaving his post to move to Nashville. Chancellor Jeff Atherton on Monday afternoon said he could not take the case until ... (click for more)

Make One Of The Proposed Surplus City Buildings Into A Local History Museum - And Response

The city of Chattanooga currently has no history center or museum. That is because several years ago it was conveyed to the public, in the blinking of an eye, that $9 million that had been raised mysteriously vanished for reasons unexplainable to this date. In the meantime, valuable artifacts and collections are sitting in cellars, basements and storage facilities instead of being ... (click for more)

Roy Exum: No Cell Phones Allowed

There was a time, not so long ago, when school-aged children would learn lessons from a prescribed text, such as a textbook. Today texting is far, far different and, as any of our teachers will tell us, cell phones have become the scourge of education. In almost every classroom, kids will silently text in the shadow of the desk in front of them rather than focus on the lesson. Yet ... (click for more)