Weekly Road Construction Report

Thursday, September 28, 2017

Here is the weekly road construction report for Hamilton County: 

 I-24 East bridge repair over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange and safety improvements on the bridges over the CSX Railroad and over U.S. 27:  Work on this project continues.  This project will repair the bridge on I 24 East over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange.  The project will also make safety improvements on two other bridges in the same area, one over the CSX Railroad and one over U.S. 27.  In addition to making major bridge deck repairs to the bridge over Chestnut Street, this project includes the installation of high-friction surface treatment on all of the bridge decks.  During the project, the bridge on I-24 East will be completely closed to traffic and a detour using the Lookout Mountain/Broad Street ramp (Exit 178) will be used to move traffic around the work zone and allow it to continue on I-24 East.  All repair operations will be done using a continuous daily operation (seven days per week) until necessary repairs are completed and/or all lanes are open to the free, unrestricted flow of traffic.  Additionally, traffic accessing Lookout Mountain/Broad Street from U.S. 27 South will be detoured until completion of the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is November.  [Dement Construction Co., LLC/Pruett/CNR031] 

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  On Thursday, between 7 p.m.-6 a.m., there will be a temporary right lane closure on U.S. 27 North from I-24 Main Street to extend the I-24 East ramp to the U.S. 27 North merge lane.  Ramp traffic from I-24 East to U.S. 27 North will be affected with a temporary yield situation.  Recently, as part of Phase 2 of the project, traffic on U.S. 27 was shifted to the outside in both directions to allow the contractor access to the middle portion of U.S. 27 for the next construction phase.  As a result of traffic shifting to the outside, the ramps at MLK Boulevard in both directions and the 4th St. ramp on U.S. 27 South were shortened and originally required traffic to yield when entering U.S. 27.  The yield signs have now been changed to stop signs because of the increase in traffic crashes in the work zone.  All traffic must stop at the following locations before entering onto U.S. 27:  4th Street ramp onto U.S. 27 South, westbound MLK Boulevard ramp onto U.S. 27 South, eastbound MLK Boulevard ramp onto U.S. 27 South and eastbound MLK Boulevard ramp onto U.S. 27 North.  Drivers are encouraged to obey the signage and pay close attention to changing conditions in the work zone.  There will be increased law enforcement presence within the project limits.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor may have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road.  Flaggers will assist with traffic control as needed.  Estimated project completion date is June 2018. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues.  The contractor will be working on the inside lanes of the bridge.  The outside lanes in both directions are open to traffic.  This lane closure will be in place until late November 2017.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 p.m.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

SR-153 resurfacing from L.M. 7.11 (Chickamauga Dam) to LM 8.89 (Hixson Pike):  Work on this project continues.  Lane closures are limited to Sunday night thru Thursday night from 9 p.m.-6 a.m.  Estimated project completion date is October.  [Wright Brothers Construction Co, Inc./Micka/CNR133] 

U.S. 11 (SR-2/Brainerd Road) resurfacing from McCallie Tunnel (LM 11.83) to east of Moore Road (LM 13.85):  Work on this project continues.  During the project, the contractor will have intermittent lane closures between 9 p.m.-6 a.m. Sunday night thru Thursday night. The contractor will be milling, paving, and installing pavement markings. At least one travel lane will remain open to traffic at all times. This work may affect either direction of Brainerd Road or side streets from Moore Rd. to the McCallie Tunnel.  Motorists should be alert for construction personnel and equipment. THP will assist with traffic control as needed. Estimated project completion date is November. [Talley Construction/Pruett/CNR218] 

U.S. 27 (S.R. 29 resurfacing from south of the bridge over Sale Creek (L.M. 28.25) to the Rhea County line (L.M. 30.84):  Construction signs have been installed.  The contractor should begin the work any time now and will begin with clipping shoulders, adjusting guardrail and putting up new end treatments, and then the milling and the paving.  There will be lane closures with one lane in each direction open to traffic when work begins.  Estimated project completion date is October.  [Rogers Group, Inc./Micka/CNR109] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2018.  [ETI Environmental, Inc./Micka/CNR223]
 



PHOTOS: Sequoyah's Community Day

Sequoyah’s Community Day drew about 1,500 people from the community who came out to learn about the nuclear plant right in their back yard. (click for more)

Clint Powell Interviews TV Icon David Carroll

Clint Powell, the owner of Connect Marketing, interviewed TV icon David Carroll. Click here to listen. (click for more)

Chancellor Fleenor Sets Aug. 6 Hearing In Democratic Suit To Keep Robin Smith Off The Ballot; Ms. Smith Was Former Campaign Advisor To Judge

Hamilton County Chancellor Pam McNutt Fleenor has set a hearing for Aug. 6 at 1:30 p.m. on a lawsuit brought by the Tennessee Democratic Party seeking to keep former state GOP Chairman Robin Smith off the ballot. Ms. Smith was a campaign advisor for Ms. McNutt Fleenor when she ran for judge in 2014. Her Rivers Edge Alliance was paid $13,546.86 by the McNutt Fleenor campaign, ... (click for more)

Police Say One Gang Member Shot Another After Both Just Left Gang Meeting At Mayor's Office

Police said one gang member shot another after both had just left a meeting at the mayor's office aimed at quelling gang violence. Kevin Dewayne Bush was arrested for shooting Keyshawn Kidd on May 29. Bush, 20, of 17th Street, is charged with attempted first-degree murder, reckless endangerment and unlawful possession of a firearm. Police said Kidd was returning to his ... (click for more)

Not My University: Why I’m Not Okay With Mike Pence Coming To Lee University - And Response (2)

As a student of Lee University, who is well-aware of the Lee administration’s more conservative stance in politics, I am upset about Mike Pence visiting the university and being welcomed on our campus. Although I respect that Pence is in a position of authority as our nation’s Vice President, and that he likewise deserves the right to hold his own opinions in regards to the issues ... (click for more)

Employee Who Stole From East Ridge Should Be Prosecuted

Why has the East Ridge employee who was fired for theft not been charged with theft?    City Manager Scott Miller made the statement that the employee had problems and that the stolen items were returned.  What does that have to do with the employee stealing ?   He has had a history of abuse of city resources. Why is he not being prosecuted? ... (click for more)