Weekly Road Construction Report

Thursday, January 25, 2018

Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues. The contractor has closed the 12th Street tie-in ramp to U.S. 27 South. This closure will be in place until April. Traffic from 12th Street will be detoured to Carter Street and then to Westbound MLK where motorists may access the U.S. 27 South on-ramp.

Detours are posted. Motorists should exercise caution when traveling through the construction zone and pay close attention to the detour signage posted. Last week, new ramp configurations were implemented on the northbound lanes of US 27 between MLK Blvd. and Fourth Street. These changes affected the on-ramp to U.S. 27 North from MLK Blvd., and the off-ramp (Exit 1C) from U.S. 27 North to 4th Street. Traffic coming from downtown Chattanooga and using the on-ramp to U.S. 27 North from MLK Blvd. is now required to come to a complete stop at the top of the ramp. Traffic wishing to access 4th Street at Exit 1C from U.S. 27 North is now directed to a new temporary exit ramp before crossing the 6th Street overpass. This new temporary exit ramp is narrow and posted for 15 MPH. This new traffic pattern will be in place for approximately two months. Motorists are encouraged to seek alternate routes due to the increased congestion between MLK Blvd. and 4th Street. The speed limit has also been reduced from 45 MPH to 35 MPH between Main Street and 4th Street on U.S. 27 North. The speed limit on U.S. 27 in the rest of the construction zone remains 45 MPH. Motorists should exercise caution when traveling through the construction zone and pay close attention to the signage posted. On Thursday the contractor will implement a night time right lane closure on Northbound US27, from I-24 to the Olgiati Bridge, from 7 p.m.-6 a.m. Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 p.m.-6 a.m. At least one lane will remain open in each direction on U.S. 27. THP will assist with traffic control on the project as necessary. Estimated project completion date is July 2019. [Dement Construction Company, LLC / Micka / CNP230] RESTRICTIONS: I 124 (US-27) Northbound Exit 1C 4th Street Off Ramp. No oversize/over-dimensional loads. Width Limit is 11 feet.

I-75 North Exit 1 interchange reconfiguration project at mile marker 1: Work on this project continues. The project will result in a reconfiguration of the exit ramps and will combine both northbound exits (1A & 1B) into one, which will allow drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Pkwy., and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Pkwy.)is now controlled by a new traffic signal. The contractor is planning on Jan. 31 and Feb. 1 (weather pending) on closing the existing I-75 NB Off-Ramp Exit 1B and re-signing I-75 NB traffic unto the new I-75 NB Exit 1 ramp. Traffic delays will be minimal but the new intersection (I-75 NB off Ramp and SR-8/Camp Jordan will be controlled by a new traffic signal).  Estimated project completion date is May 2018. [C.W. Matthews Contracting/City Of East Ridge/LCLPRGM] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153: There could be lane closures on SR153 during non-peak hours (9 a.m.-3 p.m.) starting this Thursday to support punchlist activity on the project.  Hixson Pike will have lane closures each direction beginning Thursday. These lane closures will be in place until further notification. Estimated project completion date is January. [Mid-State Construction Company, Inc./Micka/CNQ941]  

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road: During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed. Estimated project completion date is June. [Jones Bros. Contractors, LLC/Pruett/CNN383] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8): The McCallie tunnel and Stringer's Ridge tunnels are scheduled to be cleaned this Friday night/ Saturday morning. The Bachman tunnels are scheduled to be cleaned this Saturday night/ Sunday morning. Detours will be set up to address traffic. The rescheduling is necessary to account for the bitter weather when it is not advisable to clean the tunnels. Estimated project completion date is June. [ETI Environmental, Inc./Micka/CNR223] 



Rotaract Of Chattanooga Announces Leadership Updates For 2018-2019

Rotaract of Chattanooga has selected its 2018–2019 board of directors to lead the organization into its sixth year and announced the appointment of President Caroline Walker. “I am honored to serve as this year’s Rotaract president. We have such a motivated, passionate and diverse  group of people in this club who are always looking for ways connect others, personally and professionally, ... (click for more)

Weekly Road Construction Report

Here is the weekly road construction report for Hamilton County: I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan ... (click for more)

Price Has Risen To $143 Million For State's Most Expensive Road Project - Downtown Chattanooga Freeway

The cost of Chattanooga's downtown freeway makeover - estimated at $85 million in 2006 and bid at $126.3 million when it got underway in November 2015 - has climbed to $143 million as issues were encountered along the way, TDOT's Ken Flynn said Monday. The Highway 27 project to provide three lanes in each direction from the I-24 split to the river was already the most expensive ... (click for more)

Signal Mayor Chris Howley Not Running Again; Man Suing Town To Be On Ballot For Council

Signal Mountain Mayor Chris Howley has decided not to seek re-election. He had until noon today to return the petition that he picked up earlier. Rick Saputa, who is suing the city but also picked up a petition for the council, did qualify just before the deadline. Others running for the Town Council include former Mayor Bill Lusk, Councilman Dan Landrum and new-comers ... (click for more)

Jeff Styles, I Believe You - And Response (5)

I am glad that Jeff Styles presented the details of the event on his website.  Just because the government alleges a crime does not mean guilty. A criminal charge is an allegation by government. Sure, that allegation can be very serious, but the charge is still an unproven allegation until a court of law and Lady Justice has her review of the proof.  A person gets ... (click for more)

Roy Exum: The Political Dark Side

If ever there becomes a movie that reveals the rotten side of politics, the script has just been written. My goodness, it has all of the hot words: liberals, Muslims, bedroom beds, spouse abuse, non-transparency (or is it collusion,) kids in shock, a seated member of Congress, vulgar language, the Democratic National Committee, a woman scorned, and – best of all – an election. ... (click for more)