Weekly Road Construction Report

Thursday, September 20, 2018

Here is the weekly road construction report for Hamilton County: 

I-24 East and West drainage improvement from MM 173 to 175:   The drainage improvement project at Exit 174 is underway. There will be lane closures along US-41 in the vicinity of the interchange.  Ramps will remain open but could be subject to width and lane restrictions.  Estimated project completion date is November. [Talley Construction Company/Micka/CNS324]  

I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Parkway, and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Parkway) is now controlled by a traffic signal. Estimated project completion date is September.[C.W. Matthews Contracting/City Of East Ridge/LCLPRGM] 

US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge Work on this project continues with numerous activities occurring in the median of US-27. Motorists should be alert for construction vehicles entering and leaving the left traffic lane in both the northbound and southbound directions.
The 12th Street tie-in ramp to US-27 South has been temporarily closed through September and detours are posted. 

On Thursday and Friday between 9 a.m.-4 p.m., the contractor will have a lane closure on the outside lanes of the Olgiati Bridge on U.S. 27 North and South to work on the bridge struts underneath the bridge. Traffic will use the two inside lanes in each direction.  In addition to the outside lane closures on the Olgiati Bridge, some ramps will be affected during the work.
On Thursday from 7 p.m.-6 a.m. and Friday from 7 p.m. through Saturday at noon, there will be temporary ramp closures in the vicinity of 4th Street for removing the center island between the southbound 4th Street off- and on-ramps and installing temporary paving. Detours will be posted.
Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 p.m.-6 a.m. At least one lane will remain open in each direction on US-27. Motorists should pay close attention to any detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. THP will assist with traffic control on the project as necessary.  Estimated project completion date is January 2020. [Dement Construction Company, LLC/Micka/CNP230] 

US-127 (SR-8) slope repair of Signal Mountain Blvd. at log mile 15.9:   During this report period, the contractor will have one lane closed while performing slope stabilization operations. Temporary traffic signals are in place on either end of the project to control traffic. Additionally the speed limit has been lowered to 20 MPH in the construction zone. Additional flaggers will assist with traffic control as needed.  Estimated project completion date is October. [GSI/Maintenance/MAINT] 

Utility Work on SR-8 (Signal Mountain Road) both directions from LM 12.8 to LM 12.8:   Lane closures to perform utility work on Signal Mountain Road at the intersection of Old Signal Mountain Rd/Raider Lane. Work will occur nightly from 9 p.m.-4 a.m. Sept. 20-28. Motorists should use extreme caution and be alert to construction equipment and workers. 

SR-153 resurfacing from I-75 (LM 0.00) to Shallowford Road (LM 2.60), including bridge deck repair:   This project will involve nightly lane closures (8 p.m.-6 a.m.) to support the project activities. This will involve both northbound and southbound lane closures, Sunday through Thursday. Additionally, a ramp and bridge repair activity may require lane closures through the entire weekend starting Friday at 8 p.m.  Estimated project completion date is November. [Wright Brothers Construction Company, Inc./Micka/CNS251] 

Cleaning of the Bachman Tubes on US-41 (US-76, SR-8):   Bachman Tubes will be cleaned on Thursday from 8 p.m.-6 a.m. The Bachman Tube cleaning will have a signed detour to direct traffic.  Estimated project completion date is June 2019. [Diamond Specialized, Inc./Micka/CNS206] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:   During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed.  Estimated project completion date is October. [Jones Bros. Contractors, LLC/Pruett/CNN383] 

US-11/64 SR-2 (Brainerd Road/Lee Highway) resurfacing from east of Moore Road (LM 13.85) to east of Airport Road (LM 15.84):   The contractor has begun lowering manholes and catch basins. This will take place Monday through Friday between 9 a.m.-3 p.m. This work may affect either direction of US-11/64 (Brainerd Road/Lee Highway) between Moore Road and Airport Road. The contractor has begun milling operations and will continue through Sunday in which the contractor will have intermittent lane closures for resurfacing operations Sunday through Thursday from 8 p.m.-6 a.m. Flaggers will assist with traffic control as needed.  Estimated project completion date is November. [Wright Brothers Construction Co., Inc./Pruett/CNS228] 



U.S. Congressional District 3 Forum Scheduled For Monday Is Canceled

The candidate forum for U.S. Congressional District 3 scheduled for Monday, Oct. 22, has been canceled. Congressman Chuck Fleischmann and Dr. Danielle Mitchell were invited to participate and give input on possible dates back in September. Dr. Mitchell responded, but Rep. Fleischmann did not. After a month without a commitment, a date was announced last week. Rep. Fleischmann’s ... (click for more)

Rotary Club of Chattanooga Hamilton Place Hosts 2018 Miss TN Outstanding Teen And Helps With Local Service Project At HES

The Rotary Club of Chattanooga Hamilton Place recently hosted Mary Humphrey, the 2018 Miss Tennessee Outstanding Teen.  Ms. Humphrey spoke about the pageants she has participated in and the inspiration she received from her grandmother.  "Her passion and platform, Pages with a Purpose, helps promote literacy among children similar to the literacy program sponsored ... (click for more)

Soddy Daisy High ROTC Instructor Denies He Had Gun In Road Rage Incident, But Judge Sends Case To Grand Jury

A Soddy Daisy ROTC instructor has denied having a gun in a road rage incident with a 17-year-old girl at Northgate Mall, but General Sessions Court Judge Gary Starnes bound the case to the Grand Jury. The judge said,"It's a very close issue. It's he said, she said. I don't think it's going to get out of the Grand Jury, but I am going to find there is probable cause." The girl ... (click for more)

Federal Judge In Nashville Tells State To Halt Suspension Of Drivers Licenses Of Those Who Cannot Pay

 A Nashville federal judge has directed that the state halt suspension of the drivers licenses of people who cannot afford to pay fines and court costs. The ruling was from District Judge Aleta Trauger. Officials of the Department of Safety and Homeland Security said, "The department has received the order.  It will stop suspensions of licenses, as the Court requires, ... (click for more)

Drink Up, Chattanooga

I attended the meeting to discuss the placement of the sewage treatment plant at the Cambridge Center in Ooltewah today. My problem with the meeting (aka) dog and pony show, is that the meeting started out with the agenda of the Ooltewah Community Council.  After living in this area for 45+ years I have never heard of this group.  I would like for someone to answer ... (click for more)

Roy Exum: Dear Faux Pelini

It has been my experience that of all the tribes and herds of different people on earth, sports writers are among the funniest people of all. Oh, there isn’t anything real sexy about Villanova beating Georgetown or a baseball player hitting for the cycle. Now, if a player hits a single, double, triple and homer in that order, that’s “a natural cycle,” and that is kind of fun to ... (click for more)