Weekly Road Construction Report

Thursday, September 12, 2013

Here is the weekly road construction report for Hamilton County: 

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work on this project is complete pending addressing of punchlist items.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m.  THP will assist with traffic control.  

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is September.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  On Thursday the contractor will have a right lane closure from the Oligati Bridge to Manning Street beginning at 7 p.m. on U.S. 27 North to implement a new traffic shift.  Beginning Friday morning, traffic traveling north on U.S. 27 will be doing so on the new bridges and pavement.  This alignment will be in place until the contractor completes work on the center section of U.S. 27.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  Traffic has been switched to the temporary paving on the SB side of the project and the contractor is working on road and drainage on the NB side of the project.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project has begun.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  There will be one lane closed this weekend to allow the contractor to work on intersections.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

SR-312 (Mahan Gap Rd.) (LM 14.27) from SR-58 to the Bradley County Line (LM 17.75):  Work on this project has begun.  During this report period the contractor will have paving operations on SR-312 from 8 a.m.-5 p.m.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is October.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

I-75 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs soil boring for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Obedience Club Of Chattanooga Begins New 6-Week Session July 20

The Obedience Club of Chattanooga will begin its next 6-week session of obedience, rally, and agility classes for puppies and dogs on Monday, July 20, at its training facility 4 miles south of Chattanooga on Highway 193 in Flintstone, Ga. Registration will be held on Sunday, July 19, from 1-3 p.m. at the training facility.  During registration, various OCC dog/handler ... (click for more)

Lake Winnie Reschedules Fireworks

Due to the current weather and this evening's forecast, Lake Winnie will be closing early on Friday, at 6 p.m.  The Fireworks Display originally scheduled for 10 p.m. tonight  will be rescheduled for a later date. (click for more)

Plumbers Bring Complaints To WWTA; Told New Contracts Are Ready

Several plumbers on Thursday brought complaints to a committee of the Hamilton County Water and Wastewater Treatment Authority (WWTA) and got little response other than being told that new contracts are ready. Kay Keefe of Keefe Plumbing said the small number of plumbing companies still participating in the program to repair leaky lines to homes, have long been operating without ... (click for more)

Commissioner Haynes Calls For Public Meetings On Discretionary Funds; Says Public Against Keeping Them

County Commissioner Marty Haynes on Thursday called for public meetings on the subject of the commissioners continuing to have $100,000 each in discretionary money. He said he had already been meeting with Hixson leaders on the topic. Commissioner Haynes was one of three commissioners who supported a move by County Mayor Jim Coppinger to remove $900,000 in discretionary funds ... (click for more)

Could The Marriage Decision Spark A New Independence Day?

I confess that this year I am having a hard time with the idea of celebrating the 4th of July Independence Day. It is not because I am not thankful to God for what was done on that day, what it represents, and the blessings I’ve experienced that flow from it. On the other hand, I want to think that maybe this year’s celebration will mark a period in our history in which a new movement ... (click for more)

Roy Exum: My Pre-Fourth Observations

I hate to do this, right on the heels of my monthly ‘Walk in the Garden,’ but I have more things on my desk that I dare not leave unnoticed before tomorrow’s Star-Spangled celebration. Foremost is the plea to anyone who shoots off firecrackers to please wear eye protection and ask watchers to stand back. Our eye doctors say firecracker-related injuries have doubled in the last three ... (click for more)