Here is the weekly road construction report: 

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work on this project is complete pending addressing of punchlist items.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m. THP will assist with traffic control.  

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is September.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will have a nighttime left lane closure on U.S. 27 North from Dayton Blvd. to Signal Mtn. Rd. beginning at 7 p.m. to remove existing concrete barrier to prepare for a future traffic shift.  On the nights of Monday Tuesday Signal Mountain Road will be closed under the bridge (between the ramps) to pour the bridge deck for the U.S. 27 North exit ramp over Signal Mountain Road.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor has scheduled a traffic shift to take place on Monday.  Traffic will be switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Should weather or unforeseen circumstances postpone this work, it will be rescheduled to take place on the first available day.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project has begun.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  There will be one lane closed this weekend to allow the contractor to work on intersections.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

I-75 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs soil boring for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Medal Of Honor Heritage Trail Dedication

The National Medal of Honor Museum of Military History will dedicate the first sign in its Medal of Honor Heritage Trail at the Lee & Gordon’s Mills in Chickamauga on Saturday from 1-2 p.m.  the public is invited to attend. The sign will honor three of the nine recipients of the Medal of Honor awarded during the Battle of Chickamauga in September 1863 to include Bugler ... (click for more)

Chief John Ross Chapter Of DAR Sponsored Genealogy Workshop

The Chief John Ross Chapter of the Daughters of the American Revolution sponsored a beginner genealogy workshop at the Bessie Smith Hall. Basic tips to start a family history, as well as worksheets and online tools to use, were covered.   There was a discussion on how to interview family for information, how to organize material and different organizations and online ... (click for more)

Erlanger Finishes Fiscal Year With $18 Million Profit

After a major loss the year before, Erlanger Health System finished the fiscal year with an $18 million profit, officials announced Monday night. It was well ahead of the $2 million gain that Erlanger had budgeted for, and far better than last year's $8 million loss. The profit was boosted by a first-time $19,587,000 from a Public Hospital Supplemental payment and essential ... (click for more)

Chancellor Rules That IDB Must Reimburse Attorney Fees, Other Legal Costs For Helen Burns Sharp On TIF Lawsuit

Chancellor Pam Fleenor has ruled that Helen Burns Sharp, who sued over the validity of a $9 million Tax Increment Financing (TIF) for a planned major development on Aetna Mountain, should be reimbursed her discretionary costs as well as her attorney fees. Ms. Sharp said in a recent court filing that her legal bills to attorney John Konvalinka were $74,427 at the time. The ... (click for more)

ChattaData Is A Real Advance For The City

This past Tuesday, the city of Chattanooga's new performance management tool called ChattaData was unveiled. As the chairman of the City Council’s Budget & Finance Committee, I am excited to witness the city putting this important information online in a way that is accessible and transparent to all taxpayers. This approach shines light on how we as a city prioritize our ... (click for more)

Roy Exum: It’s ‘Hate The SEC’ Day

The boo birds came out on the fly on the ESPN website Sunday afternoon, this moments after the latest AP College Football “Top 25” included eight teams from the Southeastern Conference.   What set naysayers aglow was Mississippi State, after upsetting LSU 34-29 Saturday night, debuted on the list at No. 14 while Clemson, playing Florida State in an overtime thriller, got tossed ... (click for more)