Weekly Road Construction Report

Thursday, September 19, 2013

Here is the weekly road construction report: 

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work on this project is complete pending addressing of punchlist items.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m. THP will assist with traffic control.  

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is September.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will have a nighttime left lane closure on U.S. 27 North from Dayton Blvd. to Signal Mtn. Rd. beginning at 7 p.m. to remove existing concrete barrier to prepare for a future traffic shift.  On the nights of Monday Tuesday Signal Mountain Road will be closed under the bridge (between the ramps) to pour the bridge deck for the U.S. 27 North exit ramp over Signal Mountain Road.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor has scheduled a traffic shift to take place on Monday.  Traffic will be switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Should weather or unforeseen circumstances postpone this work, it will be rescheduled to take place on the first available day.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project has begun.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  There will be one lane closed this weekend to allow the contractor to work on intersections.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

I-75 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs soil boring for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  



Chattanooga Eagles To Host Charity Benefit September 19

Chattanooga Fraternal Order of Eagles #945 and Ladies Auxiliary invite the community to hit the links in support of various local and international charities at its 6th Annual Charity Golf Tournament Friday, Sept. 19, at the Brown Acres Golf Course, 406 Brown Rd. The event is open to the public at a cost of $100 per-player or $400 per-four person team if registered by Sept. ... (click for more)

Dance At American Legion In East Ridge Saturday

The American Legion, 3397 Ringgold Road in East Ridge will host its monthly dance on Saturday.  Cover charge is $5 per person, and hours are 7 - 10 p.m.  Light refreshments will be served.  All are welcome to dance, or just sit and listen to the Legionnaires big band playing tunes of Woody Herman, Glenn Miller, and many others. (click for more)

Rhasean Lowry, 34, Charged In Death of 3-Year-Old Girl

Rhasean Lowry, 34, was arrested for abusing a three-year-old girl, and then criminal homicide after she died. Last Tuesday, the Chattanooga Police Department was called on a suspected child abuse case. Lowry took the victim to a local hospital and he stated the victim fell down steps. Doctors advised that the victim’s injuries were the result of blunt force trauma consistent ... (click for more)

City IDB Member Who Made Motion For $9 Million Black Creek TIF Had Not Lived In City For Years

A City Industrial Development Board (IDB) member who made the motion to approve a controversial $9 million Black Creek Tax Increment Financing (TIF) had not lived in the city for years, City Attorney Wade Hinton confirmed. Chris Ramsey, a BlueCross BlueShield official, was not present at an IDB meeting on Tuesday morning. Five other board members were. Citizen Helen Burns ... (click for more)

Decimating The Chattanooga Public Library - And Response

Corinne Hill claims that the library is just undergoing a normal weeding process for eliminating books.  She has bragged that she's responsible for the elimination of over 100,000 books - with more to go. "Normal" weeding is not rampant throwing away.  Yes, books go to the Friends for their sale - where they get $2 for a $75 book and thousands wind up being recycled ... (click for more)

The Many Lessons I Learned From Helen McDonald Exum

Helen McDonald Exum was my friend and mentor. As I think of her passing I can only imagine the celebration that is happening in heaven as the news of her arrival is being told. I am sure that there is a party that not only has she organized but that there is not a detail that has been left to chance. I am sure that it is the grandest of events, for you see, she has been planing ... (click for more)