Due to unforeseen subsurface conditions found during construction, the schedule for repairing Northpoint Blvd. has been altered. The work will now be done in three phases, with varying closures during each phase. A full schedule of these closures is below: 

Phase 1: July 31 - Aug. 4:
CDOT will begin working on Northpoint Boulevard at Highway 153.
The road will be closed from Highway 153 to Bank of America. All of these businesses will have secondary access points. 


Phase 2: Aug. 7-11:
BOA / HomeAway area
The only business with one entrance is HomeAway Extended stay, CDOT will work with the manager to ensure access by their customers. 

Phase 3: Aug. 14-23: 
Northpoint Boulevard will be fully closed from Bank of America to Hixson Pike. All businesses within the closure will have secondary access points.

In order to view a map of these closures, visit: http://www.chattanooga.gov/transportation/traffic-engineering-a-operations/special-events-a-street-closures

Happenings
Collegedale Airport To Host Movie Night April 27
  • 4/25/2024

The Collegedale Airport is reviving its popular movie night. The public is invited to the airport to enjoy the feature movie, Disney’s "Planes," along with yard games and a static aircraft display. ... more

East Ridge Hosts Craft Fair Benefiting East Ridge City Library
East Ridge Hosts Craft Fair Benefiting East Ridge City Library
  • 4/25/2024

The public is invited to join the “Friends of the East Ridge Library” as they host the first-ever Craft Fair to benefit East Ridge City Library this Saturday from 10 a.m.-5 p.m. at the library ... more

Jerry Summers: Gun Fight At St. Elmo Corral
Jerry Summers: Gun Fight At St. Elmo Corral
  • 4/25/2024

The Senate division of the Tennessee General Assembly on Tuesday, April 9, 2024, passed Senate Bill 7019 by a vote of 26-5 legislation that would allow teachers and school administrators to carry ... more