Weekly Road Construction Report

  • Thursday, April 9, 2015

Here is the weekly road construction report for Hamilton County:

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street (Mid-State Construction Co, Inc.):  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead. This portion of the project is scheduled to be completed by this spring, at which time East Main Street will be reopened to traffic.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m.-5 a.m.  If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./JM/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is substantially complete and all lanes of traffic are open on U.S. 27.  Most of the remaining temperature-sensitive work on the project has been done too, including the paving of most of the local roads and widening the exit ramp from U.S. 27 North to Manufacturers Road.  As the weather improves, the contractor will complete the remaining items on the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is April.  [Wright Brothers Construction Co., Inc./JM/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be clearing, grubbing and installing environmental measures.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Waterline work on Pattontown Road is complete, but the existing detours using Old Lee Highway, Blue Bell Avenue and Bork Memorial Drive will stay in place for the closure on Apison Pike that began on Monday when Apison Pike at Pattontown Road was closed to allow Eastside Utility District to install casing for the sewer line across Apison Pike.  The sewer line work is scheduled to be complete by Tuesday.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /KP/CNN279] 

SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project has started.  The contractor will be clearing and installing erosion control measures.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /KP/CNN383] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project has started.  The contractor will be on eastbound Bonny Oaks Drive installing attenuators, extending the box culvert and installing erosion control measures.  The contractor will also begin clearing and grubbing on Volkswagen Drive at the first roundabout at the Amazon entrance.  There will be one lane of traffic northbound during work hours.  The contractor may have short term lane closures to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August 2015.  [Talley Construction Company, Inc. /KP/CNN304]

Happenings
Collegedale Airport To Host Movie Night April 27
  • 4/25/2024

The Collegedale Airport is reviving its popular movie night. The public is invited to the airport to enjoy the feature movie, Disney’s "Planes," along with yard games and a static aircraft display. ... more

East Ridge Hosts Craft Fair Benefiting East Ridge City Library
East Ridge Hosts Craft Fair Benefiting East Ridge City Library
  • 4/25/2024

The public is invited to join the “Friends of the East Ridge Library” as they host the first-ever Craft Fair to benefit East Ridge City Library this Saturday from 10 a.m.-5 p.m. at the library ... more

Jerry Summers: Gun Fight At St. Elmo Corral
Jerry Summers: Gun Fight At St. Elmo Corral
  • 4/25/2024

The Senate division of the Tennessee General Assembly on Tuesday, April 9, 2024, passed Senate Bill 7019 by a vote of 26-5 legislation that would allow teachers and school administrators to carry ... more