Weekly Road Construction Report

  • Thursday, June 4, 2015

Here is the weekly road construction report for Hamilton County:

South Crest Road Bridge repair project over I-24 (between MM 182.3 – 182.4) and East Main Street (Mid-State Construction Co, Inc.):  Work on this major bridge repair project on the South Crest Road Bridge over I-24 and East Main Street in Chattanooga continues. During the project, the bridge itself is closed, as well as the section of East Main Street beneath the bridge, while the contractor removes and replaces the bridge deck on the portion of the bridge directly overhead.  Detours will be posted for the duration of the project.  Additionally, there will be times during the project when work will require temporary lane closures on I-24 beneath the South Crest Road Bridge.  These interstate lane closures will only be allowed at nighttime on Sundays through Thursdays between the hours of 8 p.m.-5 a.m.  If weather allows, the contractor will have lane closures on I-24 East and West beneath the bridge during this report period for the safety of the traveling public as the contractor works overhead.  THP will assist with traffic control as necessary during interstate lane closures.  Estimated project completion date is August.  [Mid-State Construction Co, Inc./JM/CNN294] 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  This project is complete and awaiting final inspection.  Estimated project completion date is June.  [Wright Brothers Construction Co., Inc./JM/CNK233] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will be clearing, grubbing, installing erosion control measures, and installing sewer line.  The contractor may have short term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /KP/CNN279] 

SR-320 (East Brainerd Rd.) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  The contractor will have intermittent lane closures between 9 a.m.-2 p.m. in both directions on East Brainerd Road between Kinsey Drive and Fuller Road to perform utility work. This work will require installing road crossings and boring underneath the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017. [Mountain State Contractors, LLC /KP/CNN383] 

SR-317 (Bonny Oaks Drive) resurfacing from SR-17 (LM 0.00 near Hillcrest Elementary School) to west of Silverdale Road (LM 4.47):  Work on this project is slated to begin during this report period.  On Wednesday, June 10 the contractor will have an eastbound lane closure at the intersections of Bonny Oaks Drive with SR 153 and Jersey Pike from 6 p.m.-4:30 a.m. to mill for signal loops.  One lane of traffic will be open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion is September. [Wright Brothers Const. Co. /KP/CNP108] 

SR-317 (Bonny Oaks Drive) improvement of the intersection with Volkswagen Drive (LM 3.85) serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor will be on eastbound Bonny Oaks Drive at Volkswagen Drive extending the box culvert and installing erosion control measures.  The contractor will also be on Volkswagen Drive working on the entrance to Amazon.  The contractor may have short term lane closures to perform various operations on as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August.  [Talley Construction Company, Inc. /KP/CNN304]

Happenings
Chattanooga Zoo Hosts Spirits In The Wild 21+ Event
  • 5/1/2024

The Chattanooga Zoo is once again hosting their signature 21+ event, Spirits in the Wild on May 18 from 6-9 p.m. The after-hours event features beers, wines and spirits from around the world, ... more

Did You Know? Tribe
Did You Know? Tribe
  • 5/1/2024

The recent surprise announcement that the only opposition to the current “Chief Conductor” on the proposed “Choo Choo Express” in the next mayoral race and future in our booming municipality ... more

Lily Hughes, Local 19-Year-Old Equestrian, To Compete In Mustang Champions Competitions
Lily Hughes, Local 19-Year-Old Equestrian, To Compete In Mustang Champions Competitions
  • 4/30/2024

Lily Hughes, a 19-year-old equestrian from Flat Top Mountain, will compete in two major Mustang Champions competitions this year: the Mustang Challenge in Las Vegas, Nv., and the Mustang Classic ... more