Weekly Road Construction Report

  • Thursday, August 10, 2017

Here is the weekly road construction report for Hamilton County: 

I-24 East bridge repair over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange and safety improvements on the bridges over the CSX Railroad and over U.S. 27:  Work will begin this week on a project to repair the bridge on I 24 East over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange.  The project will also make safety improvements on two other bridges in the same area, one over the CSX Railroad and one over U.S. 27.  In addition to making major bridge deck repairs to the bridge over Chestnut Street, this project includes the installation of high-friction surface treatment on all of the bridge decks.  On Thursday and Friday nights, between 7 p.m.-6 a.m. EDT, the contractor will begin shifting traffic and reworking overhead signs.  Once the traffic is shifted and the signs reworked, work on the project will begin.  If rain postpones this work, it will be rescheduled to take place as soon as possible.  During the project, the bridge on I-24 East will be completely closed to traffic and a detour using the Lookout Mountain/Broad Street ramp (Exit 178) will be used to move traffic around the work zone and allow it to continue on I-24 East.  Once I-24 East is closed for bridge repairs, all repair operations will be done using a continuous daily operation (seven days per week) until necessary repairs are completed and/or all lanes are open to the free, unrestricted flow of traffic.  Additionally, traffic accessing Lookout Mountain/Broad Street from U.S. 27 South will be detoured until completion of the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is November.  [Dement Construction Co., LLC/Pruett/CNR031] 

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  On weeknights during this report period between 7 p.m.-6 a.m., the contractor will have a temporary left lane closure on U.S. 27 South from Manufacturers Road to I-24 for beam removal.  Southbound Exit 1A will be closed during this time due to Eastbound Martin Luther King Boulevard being closed.  On U.S. 27 South, traffic has been shifted to the right on U.S. 27 South from 4th Street to MLK Boulevard to allow the contractor to safely work in the middle portion of the road.  Traffic is impacted by the loss of acceleration/merge areas onto U.S. 27 South from the on ramps at 4th Street and MLK Boulevard.  On U.S. 27 North, traffic has been shifted to the right on U.S. 27 North from I-24 to MLK Boulevard to allow the contractor to safely work in the middle portion of the road.  Traffic is impacted by the loss of acceleration/merge areas onto U.S. 27 North from the on ramp at MLK Boulevard.  The new loop ramp from eastbound MLK Blvd. to U.S. 27 North is open and the previous left turn to the northbound ramp is closed.  Ramp traffic must yield at these locations.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m.   Flaggers will assist with traffic control as needed.  Estimated project completion date is August. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Road/East Brainerd Road intersection, allowing the contractor to work on the other side of the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is June 2018. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues.  The contractor will be working on the inside lanes of the bridge.  The outside lanes in both directions are open to traffic.  This lane closure will be in place until late November.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 p.m.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

U.S. 27 (SR-29) resurfacing from north of Signal Mountain Road (LM. 3.02) to north of SR-29 (MM. 6.0/LM 6.07):  This project is complete.  There are a few minor punch list items to be corrected.  However, no lane closures will be required.  Contractor has been authorized to remove all signs.  Estimated project completion date is August. [Wright Brothers Construction Co, Inc./Micka/CNQ189] 

SR-153 resurfacing from L.M. 7.11 (Chickamauga Dam) to LM 8.89 (Hixson Pike):  Work on this project continues.  Milling operation will require lane closures from 9 p.m.-6 a.m.   Lane closures are limited to Sunday night thru Thursday night from 9 p.m.-6 a.m.  Estimated project completion date is September.  [Wright Brothers Construction Co, Inc./Micka/CNR133]

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2018.  [ETI Environmental, Inc./Micka/CNR223]


Happenings
North River Civic Center's Community Plant Swap Is May 11
North River Civic Center's Community Plant Swap Is May 11
  • 5/2/2024

The public is invited to bring your plants and exchange them with another person who enjoys the art of gardening on Saturday, May 11 from 1-3 p.m. at North River Civic Center. Only healthy ... more

Volunteers Needed For Raising Of Memorial Day Flags In Ringgold
Volunteers Needed For Raising Of Memorial Day Flags In Ringgold
  • 5/2/2024

Volunteers are needed to raise and lower Memorial Day flags honoring the deceased veterans of Catoosa County. "This year there will be 2,076 flags and crosses flying throughout the city ... more

Crabtree Farms Of Chattanooga’s Annual 100 Dinner & Auction Set For June 22
  • 5/2/2024

Crabtree Farms will hold their annual 100 Dinner & Auction on Saturday June 22 from 6-9 p.m. at 1000 E. 30th St. in Chattanooga. "The Annual 100 Dinner & Auction is Crabtree Farms' ... more