Weekly Road Construction Report

  • Thursday, May 15, 2014

Here is the weekly road construction report for Hamilton County. 

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures and short term nighttime outside lane closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May.  

Reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  On Wednesday, May 14 through Saturday from 7 p.m.-6 a.m. each evening the contractor will demolish the old exit ramp bridge from U.S. 27 North to Dayton Boulevard.  For the safety of the traveling public, Dayton Blvd. will be closed to traffic traveling from Red Bank during this work.  Traffic will be detoured to U.S. 27 South then onto Manufacturers Road and Cherokee Boulevard.  Traffic traveling to Red Bank on Dayton Boulevard from the Stringers Ridge tunnel to Signal Mountain Road will be restricted to one lane with periodic delays.  All work is weather permitting.  If this work is cancelled due to weather, it will be rescheduled to take place on the next available day.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February.  

SR-58 resurfacing from Lakewood Acres Road (LM. 9.20) to Greenwood Road (LM 14.68):  Work on this continues.  Milling and paving operations are limited to Sunday through Thursday nights between 7 p.m.-6 a.m.  There will be temporary lane closures as needed on this project.  At least one lane in each direction will remain open at all times.  Estimated completion date is July.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  


Happenings
Free Movie Night At Chester Frost Park Features Finding Nemo May 10
  • 5/3/2024

A free movie night will be held at Chester Frost Park on Friday, May 10, from 8-11 p.m. The movie featured will be Finding Nemo. The public is invited to bring chairs/blankets and non-alcoholic ... more

The Hunter Museum Presents Art Deco Glass From The David Huchthausen Collection
The Hunter Museum Presents Art Deco Glass From The David Huchthausen Collection
  • 5/3/2024

The Hunter Museum announces its upcoming special exhibition Art Deco Glass from the David Huchthausen Collection. Opening the evening of May 23 at 6 p.m., this exhibition showcases the characteristic ... more

Chickamauga and Chattanooga National Military Park And Outdoor Chattanooga To Provide Bike/Hike At Moccasin Bend National Archeological District
  • 5/3/2024

Chickamauga and Chattanooga National Military Park and Outdoor Chattanooga will offer a free historical bike/hike at Moccasin Bend National Archeological District on Saturday, May 18. The ... more