Weekly Road Construction Report

  • Thursday, September 6, 2018

Here is the weekly road construction report for Hamilton County: 

I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Pkwy., and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Pkwy.) is now controlled by a traffic signal. Estimated project completion date is September. [C.W. Matthews Contracting/City Of East Ridge/LCLPRGM]  

US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:   Work on this project continues with numerous activities occurring in the median of US-27. Motorists should be alert for construction vehicles entering and leaving the left traffic lane in both the northbound and southbound directions. The 12th Street tie-in ramp to US-27 South has been temporarily closed. This closure will be in place through 09/18. Detours are posted. Motorists should exercise caution when traveling through the construction zone and pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. THP will assist with traffic control on the project as necessary. RESTRICTIONS: Northbound US-27 off-ramp Exit 1C to 4th Street is restricted to a maximum width of 11 Feet. Estimated project completion date is January 2020.
[Dement Construction Company, LLC/Micka/CNP230]  

TDOT Maintenance on I-24 both directions at MM 183.2:   Removal of concrete forms from 9 p.m. Monday to 2 a.m. Tuesday. Left lane will be closed. 

TDOT Maintenance on SR-29 (US-27) southbound at LM 22.5:   Right lane will be closed for erosion repair on Wednesday. 

US-127 (SR-8) slope repair of Signal Mountain Blvd. at log mile 15.9:   During this report period, the contractor will have one lane closed while performing slope stabilization operations. Temporary traffic signals are in place on either end of the project to control traffic. Additionally the speed limit has been lowered to 20 MPH in the construction zone. Additional flaggers will assist with traffic control as needed.  Estimated project completion date is September. [GSI/Maintenance/MAINT]  

SR-153 resurfacing from I-75 (LM 0.00) to Shallowford Road (LM 2.60), including bridge deck repair:   This project will involve nightly lane closures (8 PM to 6AM) to support the project activities. This will involve both NB & SB lane closures, Sunday through Thursday. Estimated project completion date is November. [Wright Brothers Construction Company, Inc./Micka/CNS251]  

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:   During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed.  Estimated project completion date is October. [Jones Bros. Contractors, LLC/Pruett/CNN383]  

US-11/64 SR-2 (Brainerd Road/Lee Highway) resurfacing from east of Moore Road (LM 13.85) to east of Airport Road (LM 15.84):   The contractor has begun lowering manholes and catch basins. This will take place Monday through Friday between 9 a.m.- 3 p.m. This work may affect either direction of US-11/64 (Brainerd Road/Lee Highway) between Moore Road and Airport Road. The contractor will begin milling and paving on Sept. 4, after which the contractor will have intermittent lane closures for resurfacing operations Sunday through Thursday from 8 p.m.-6 a.m. Flaggers will assist with traffic control as needed Estimated project completion date is November. [Wright Brothers Construction Co., Inc./Pruett/CNS228] 


Happenings
Collegedale Airport To Host Movie Night April 27
  • 4/25/2024

The Collegedale Airport is reviving its popular movie night. The public is invited to the airport to enjoy the feature movie, Disney’s "Planes," along with yard games and a static aircraft display. ... more

East Ridge Hosts Craft Fair Benefiting East Ridge City Library
East Ridge Hosts Craft Fair Benefiting East Ridge City Library
  • 4/25/2024

The public is invited to join the “Friends of the East Ridge Library” as they host the first-ever Craft Fair to benefit East Ridge City Library this Saturday from 10 a.m.-5 p.m. at the library ... more

Jerry Summers: Gun Fight At St. Elmo Corral
Jerry Summers: Gun Fight At St. Elmo Corral
  • 4/25/2024

The Senate division of the Tennessee General Assembly on Tuesday, April 9, 2024, passed Senate Bill 7019 by a vote of 26-5 legislation that would allow teachers and school administrators to carry ... more