U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During this report period, the contractor will have a nighttime right lane closure on U.S. 27 North and South throughout the entire project area to install anchored barrier rail.  Also on either Thursday or Friday, Manufacturers Road will be closed from 7 a.m.-6 p.m. between the old entrance and exit ramps to U.S. 27 to allow the contractor to conduct a bridge deck pour.  The Manufacturers Road entrance ramp onto US 27 North has been closed until spring 2013 to allow for construction of several retaining walls and portions of new bridges.  Detours are posted.  The Manning Street entrance ramp to U.S. 27 North and the Manning Street and Whitehall Road exit ramps from U.S. 27 North have been permanently closed.  All work is weather permitting.  Should inclement weather prevent work from being performed, it will be rescheduled to take place at the earliest possible time.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.  

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving: The contractor will be laying pipe across the roadway at several locations.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is September.   

SR-60 construction of concrete slab bridge over branch (LM 0.44):  (This project is near the Meigs County Line.)  This project is complete with the exception of addressing punchlist items.  Estimated project completion date is February. 


Happenings
PHOTOS: Armed Forces Day Parade
  • 5/3/2024

Chattanooga once again paid tribute to our armed forces with a luncheon and downtown parade more

The Hunter Museum Presents Art Deco Glass From The David Huchthausen Collection
The Hunter Museum Presents Art Deco Glass From The David Huchthausen Collection
  • 5/3/2024

The Hunter Museum announces its upcoming special exhibition Art Deco Glass from the David Huchthausen Collection. Opening the evening of May 23 at 6 p.m., this exhibition showcases the characteristic ... more