Crews Continue Work Slicing Through Concrete On Chickamauga Dam

  • Friday, January 8, 2021

Crews are working around the clock at the Chickamauga Dam to complete a slice approximately 100 feet down through the dam to allow concrete growth to continue without impacting the function of the lift gates and generators.

The team is more than half way through the project which should wrap up around the end of the month. 

This is the third time TVA Dam Safety has taken a slice out of Chickamauga to allow for concrete growth since it was completed in 1940. Doing so ensures the continued safe operation of the dam, providing flood control and clean hydro generation, said officials.

Here is a link to a drone video of the project. 

Business
INCubator Of Chattanooga Launches INC Connect To Support Early-Stage Manufacturing & Product Startups
  • 7/16/2025

The INCubator at the Hamilton County Business Development Center, a program of the Chattanooga Chamber of Commerce, announces the launch of INC Connect, a new makerspace initiative created in ... more

3686 Pitch Competition Returns
3686 Pitch Competition Returns
  • 7/15/2025

Launch Tennessee is calling for standout startups in the state to apply for its upcoming pitch competition, presented by Amazon, for a chance to win the grand prize of $10,000 cash. Tennessee-located ... more

Smith + Howard Appoints Travis Shears As Managing Partner Of Its Chattanooga Office
Smith + Howard Appoints Travis Shears As Managing Partner Of Its Chattanooga Office
  • 7/15/2025

Smith + Howard accounting and advisory firm announced today the appointment of Travis Shears, CPA, as office managing partner of its Chattanooga location, formerly Market Street Partners. ... more