Walker County Plans Significant Road Improvements

  • Tuesday, January 28, 2020

Walker County residents will notice a significant investment in the county’s road system this summer. Contractor bids are now being accepted to make improvements to 36 miles of roads in the unincorporated areas of the county, officials said.

 

Joe Legge of the office of Commissioner Shannon Whitfield, said, "The 2020 road project list represents the largest number of miles to be resurfaced in several years.  Much of the work will be funded by the voter-approved TSPLOST.

Walker County was one of the first counties in the state to adopt a transportation special purpose local option sales tax and remains one of only two in northwest Georgia with this dedicated funding source for transportation projects.

 

"The project will include deep base patching, leveling, resurfacing and center and fog line striping and new centerline reflectors."

 

The following roads make up the 2020 project list:

 

·         Hog Jowl Road (11.30 miles in the Pigeon Mountain area)

·         E. Armuchee Road (7.10 miles in the Armuchee Valley area)

·         Chattanooga Valley Road (5.00 miles in the Flintstone/Chattanooga Valley area)

·         Old Bethel Road (4.00 miles in the Chickamauga area)

·         Happy Valley Road from Dry Valley Road to James Street (4.00 in the Rossville area)

·         Long Hollow Road (2.30 miles in the Rock Spring area)

·         Ringgold Road Phase #2 (2.30 miles in the Rock Spring area)

 

Sealed bids will be accepted until 11:45 a.m. on March 2 at the Commissioner’s Office.  Bids will be opened at noon on March 2 at the Commissioner’s Office.

 

The contract will be awarded at the Commissioner’s Regular Meeting at 6 p.m. on March 12.  The meeting will be held in the Walker County Courthouse Annex III, 201 South Main Street, LaFayette.

 

Once complete, TSPLOST will have helped resurface nearly 65 miles of county roads in just three years. Dry Valley Road and West Schmitt Road, which were approved and funded in 2019, were delayed last year due to underground utility work. Those two roads are scheduled for completion in early spring.



Breaking News
Sheriff's Office Says Man On Vulcan Lane Was Shot While Assaulting Son, Neighbor
  • 5/3/2024

The Sheriff's Office said a man who was shot Thursday night on Vulcan Lane was assaulting his son and neighbor, and no charges would be filed against the shooter. Gregory Burnett was charged ... more

Hamilton County Sheriff’s Office Investigation Disrupts Jail Smuggling Operation
Hamilton County Sheriff’s Office Investigation Disrupts Jail Smuggling Operation
  • 5/3/2024

In a joint investigation between Hamilton County Sheriff’s Office Criminal Investigative Services and Hamilton County Corrections Services, an organized attempt to smuggle contraband into the ... more

Arrest Made In April Shooting At Tunnel Boulevard Convenience Store
Arrest Made In April Shooting At Tunnel Boulevard Convenience Store
  • 5/3/2024

The Chattanooga Police Department has arrested Geonta Gaines, 29, in relation to the shooting in the 600 block of Tunnel Boulevard. On April 11, at 1:23 p.m., Chattanooga Police responded ... more