Weekly Road Construction Report

  • Thursday, September 19, 2013

Here is the weekly road construction report: 

I-24 and I-75 resurfacing project:  I-24 resurfacing from west of Spring Creek Rd. (MM 185) to I-75 (MM 185.7); I-75 resurfacing from the Georgia State Line (MM 0.00) to south of Chickamauga Creek (MM 1.91):  Work on this project is complete pending addressing of punchlist items.  Any work requiring lane closures is limited to Sunday through Thursday nights between 9 p.m.-6 a.m. THP will assist with traffic control.  

U.S. 41 (SR-8, Ringgold Rd.) grading, drainage and paving at the intersection of I 75 South off-ramp (LM 1.07) at Exit 1:  Work on this project continues.  The contractor will be working on Exit 1 on I-75 South at East Ridge performing temporary lane shifts and lane reduction operations during this report period.  Work will take place between the hours of 7 a.m.-6 p.m. on Mondays through Saturdays.  Unless a major backup occurs, traffic on I-75 should not be affected.  In the future this job could require a temporary lane/shoulder closure on I-75 South.  THP and flaggers will assist with traffic control as necessary.  Estimated project completion date is September.  

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights from 7 p.m.-6 a.m. to perform road work.  During this report period, the contractor will have a nighttime left lane closure on U.S. 27 North from Dayton Blvd. to Signal Mtn. Rd. beginning at 7 p.m. to remove existing concrete barrier to prepare for a future traffic shift.  On the nights of Monday Tuesday Signal Mountain Road will be closed under the bridge (between the ramps) to pour the bridge deck for the U.S. 27 North exit ramp over Signal Mountain Road.  Should weather or unforeseen circumstances prevent this work from taking place, it will be rescheduled for the next available night.  During this report period, the contractor will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is December 2014.

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving:  Work continues on this project.  The contractor has scheduled a traffic shift to take place on Monday.  Traffic will be switched to the new pavement on the north side of the roadway to will allow the contractor access to work on the south side of the roadway.  Drivers are urged to be alert to the new pattern and obey all traffic signs.  Should weather or unforeseen circumstances postpone this work, it will be rescheduled to take place on the first available day.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is November.   

U.S. 27 (Rossville Blvd.) resurfacing from Foust Street (LM 5.62) to the Georgia State Line (LM 7.93):  Work on this project has begun.  During this project, lane closures for asphalt paving will only be allowed on Sunday through Thursday nights between the hours of 7 p.m.-6 a.m. Concrete replacement work will only be allowed on weekends from 9 p.m. on Friday through 6 a.m. on Monday.  There will be one lane closed this weekend to allow the contractor to work on intersections.  THP will be present to assist with traffic control as necessary.  Estimated project completion date is November.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September 2014.  

I-75 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures throughout the project area as the contractor performs soil boring for future traffic cameras and dynamic message signs.  Estimated completion date is May 2014.  


Happenings
Read & Ride: CARTA-Library Partnership Offers Free Bus Passes For Area Students
Read & Ride: CARTA-Library Partnership Offers Free Bus Passes For Area Students
  • 5/7/2024

Chattanooga Area Regional Transportation Authority and Chattanooga Public Library announce a new incentive for students who participate in the Library’s summer reading program: Read & Ride ... more

"Mark Thrash – Local Legend, Civil Rights After The Civil War" Exhibit Begins May 7
  • 5/7/2024

Chickamauga and Chattanooga National Military Park will be hosting two new temporary exhibits beginning today showcasing artifacts recovered from the home and dump site of Mark Thrash and his ... more

“Louder Than The Song Of Southern Katydids:” The Role Of Artillery At Chickamauga Program Is May 18
  • 5/7/2024

Chickamauga and Chattanooga National Military Park will present artillery firing demonstrations at the Chickamauga Battlefield Visitor Center on Saturday, May 18 at 10:30 a.m., 11:30 a.m., 1:30 ... more