CANNON COUNTY SR-1 (US-70S) construction from near Barker Road (LM 1.2) to east of Hoover Road (LM 2.5): Right lane closures in both directions of SR-1 will remain in place while the contractor is completing grade work. Flaggers may be present to load and unload equipment. Motorists should use caution through the work zone and watch for workers.
[Tinsley Asphalt, LLC /Harris/CNW348]
CANNON COUNTY SR-1 (US-70S) installation of a flashing beacon at the intersection of SR-281 (Center Hill Road, LM 12.4): The contractor will be utilizing right lane closures through the work zone to complete underground work. Motorists should use caution through the work zone and watch for flaggers that may be present.
[Stansell Electric Company, Inc./Harris/CNW229]
CANNON AND WARREN COUNTY SR-1 (US-70S) bridge repair and paving from east of Lincoln Lane (LM 11) in Cannon County to Robinson Road (LM 9.4) in Warren County: The contractor may utilize short term lane closures and flagging operations to complete any remaining work. Motorists should use caution through the work zone and watch for flaggers.
[American Pavements, Inc./Harris/CNV075]
COFFEE COUNTY SR-55 (TULLAHOMA-MANCHESTER HWY.) Utility Work northbound from LM 9.2 to LM 13.94: Mobile shoulder and single lane closures from Emerson Drive to Jack Welch Drive. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 02/23/23 through 03/24/23 from 9 am – 2 pm. [2022-693]
FRANKLIN COUNTY SR-50 repair of bridge over the Elk River (LM 1.6): The roadway will be reduced to one lane being controlled with a traffic signal. One lane will be open to traffic with the restriction of all wide loads, the maximum lane width is 11.5’. Motorists should be alert to a new traffic pattern throughout the duration of the project and encouraged to use caution while being alert to construction personnel and equipment.
[Mid-State Construction Company, Inc./Hussein/CNW220]
GRUNDY COUNTY SR-15 (US-41A) construction of pedestrian facilities from north of Clifftops Avenue (LM 1.3) to I-24 (LM 1.8) in Monteagle: During this reporting period the contractor will continue implementing a lane shift that will be in place for the duration of the project. Motorists are encouraged to use caution daily. The contractor will be performing various operations.
[Rowe Construction Group, Inc./Hussein/CNW917]
MARION COUNTY I-24 (US-64) rockfall mitigation westbound between MM 136.2 and MM 140.3: The contractor will be working on I-24 WB at MM 141 – 140, MM 139.0 – 137.0, and MM 136.0 – 135.0 to perform rockfall mitigation activities. On Wednesday 03/01/23 and Thursday 03/02/23 from 1 PM - 4 PM, the contractor will be performing rolling roadblocks to cut down and clear trees from the top bench at site 3 MM 137.2. The rolling roadblock will last approximately 20 minutes then traffic will be released. Also, Monday 03/06/23 through Friday 03/10/23 from 8 AM - 4 PM beginning near MM 141 a single left lane closure will be setup to remove barrier rail and restripe lanes. Please use caution when traveling through the work zones.
[Wright Brothers Construction Company, Inc./Voiles/CNV912]
MARION COUNTY I-24 TDOT Bridge Maintenance both directions from MM 160.3 to MM 160.4: Region 2 Bridge Repair will be performing nighttime concrete repairs to the median wall on Tuesday, March 7, on I-24 over the Tennessee River. One lane will be closed with traffic control in place.
MARION COUNTY SR- 2 (US-41, US-64, US-72) miscellaneous safety improvements from the Jasper city limits (LM 19.1) to SR-27 (LM 19.23): The contractor will be working in Marion County on SR-2 from LM 19 to LM 21. They will be installing guardrail and painting using a single lane closure. Please use caution when driving through the work zone.
[Superior Traffic Control, LLC/Inc./Voiles/CNW349]
MARION COUNTY SR-27 between LM 26.9 and LM 27.9 slide repair and bridge and retaining wall construction: The contractor will be working on SR-27 (Suck Creek Road) at LM 26.9 and LM 27.9 to construct a new bridge and repair a slide. Both work zones, at LM 26.9 and LM 27.9, have the travel lanes reduced to one lane controlled by temporary traffic lights. On Friday 03/03/23 there will be one 15-minute total road closure near LM 27.9 sometime in the time between 9 AM and 12 PM. During this time, one bridge beam will be installed. Once the beam is lifted off the truck, and equipment moved off site, the traffic signals will resume normal operations. Please use caution when traveling through each work zone.
[Dement Construction Company, LLC/Voiles/CNV307]
MARION COUNTY SR-283 (ALVIN YORK HWY.) Utility Work southbound from LM 6.37 to LM 7.32: Mobile lane closures along SR-283 between Pickett Cemetery Road and Panorama Trail. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 03/07/23 through 03/31/23 from 8:00 am - 5:00 pm [2022-395]
WARREN COUNTY SR-1 (US-70S) and SR-380 intersection improvement and S.I.A. to Motlow Advanced Robotics with intersection: The contractor will be staking and installing signs start the week of 03/06/23. Motorist should use caution in the area and watch for workers. The contractor may need to use intermittent lane closures and flagging operations to install construction signs.
[Dement Construction Company, LLC/Harris/CNW212]
DISTRICT 29
BRADLEY COUNTY SR-2 (N. LEE HWY.) TDOT Contractor both directions from LM 14.8 to LM 19.8: During this reporting period, TDOT contractors will have short-term intermittent closures with flaggers for utility location work. Work will begin at 8:30 AM and continue until 5:00 PM daily. One lane of traffic will be open at all times under a flagging operation. [JMT Consultants/FORD]
BRADLEY COUNTY SR-2 (N. LEE HWY.) Utility Work northbound at LM 13.88: Shoulder and single lane closures from Sequoia Road NW and Cromwell Circle. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 03/02/23 through 03/16/23 from 9 am – 2 pm. [2022-622]
BRADLEY COUNTY SR-40 (WATERLEVEL HWY.) Utility Work westbound from LM 2.04 to LM 8.62: Shoulder and single lane closures from Hancock Road NE to Durkee Road NE. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums/cones, and flaggers will be present, 02/23/23 through 03/27/23 from 9 am – 2 pm. [2022-263]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period the contractor will have short term intermittent lane closures throughout the project for utility relocation and moving equipment as work continues on new roadway alignments and a new bridge over Candies Creek. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.
[Summers-Taylor, Inc./Wagner/CNV130]
HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US 27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. The US 27 N on-ramp at William St. has been closed and it will remain closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US 27 on-ramp. The contractor has opened up the new Broad St exit off I-24 and closed the existing exit to the Broad St that is off the US 27 S exit. Traffic from US 27 S that needs to access Broad St. will have to use the Williams St. exit. There will be detour signs to direct traffic off the Williams St. exit to Broad St. The motoring public needs to be aware of the changes. The US 27 South ramp onto I 24 East will be down to 2 lanes with the Williams St. exit still open. This ramp will be this way for several months and the motoring traffic is advised to drive with caution in this area.
[Wright Brothers Construction Company, Inc./Curtis/CNU011]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Weather permitting, the contractor will implement single lane closures between the hours of 9 PM until 6 AM Sunday through Thursday, at following locations: I-24 WB MM 185 to MM 183 and North Terrace, I-75 NB MM 2 to MM 4, I-75 SB MM 4 to MM 2.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY I-75 concrete repair from MM 6.6 to MM 12.8: During this reporting period, the contractor will be having lane closures in both directions on I-75 from 9 PM - 6 AM on Sunday thru out the week. During these lane closures, the contractor might have to temporary close some of the ramps so that they can work on the ramp.
[Summers-Taylor, Inc./Curtis/CNW046]
HAMILTON COUNTY I-75 Utility Work eastbound from MM 0 to MM 1.0: Shoulder and single lane closure on the I-75 on ramp from SR-8 (Ringgold Road) towards the Tennessee Welcome Center. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 03/07/23 through 03/15/23 from 9 am – 4 pm. [2019-578]
HAMILTON COUNTY SR-17 resurfacing from the Georgia state line (LM 0) to SR-2 (US-11, US-64, US-72, LM 2.2): During this reporting period, there will be lane closures during the day as the contractor will be starting to mill the roadway. There will be flaggers stopping traffic as this work is being done. The motoring public needs to expect possible long delays as this work is going on.
[Talley Construction Company, Inc./Curtis/CNW213]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work westbound at LM 13.28: Shoulder and single lane closures from N. Tuxedo Avenue to Woodvale Avenue. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 03/06/23 through 03/08/23 from 9 am – 2 pm. [2022-772]
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions at LM 20.01: Shoulder and single lane closures from Bonny Oaks Drive to Tyner Road. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 02/27/23 through 03/10/23 from 9 am – 2 pm. [2023-095]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility work. The flagging operations will be performed on 03/02/23, 03/03/23, 03/06/23, 03/07/23 and 03/08/23 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work eastbound from LM 5.94 to LM 6.38: Shoulder and single lane closures from S. Orchard Knob Ave and S. Watkins Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels will be present, 12/01/22 through 03/31/23 from 9 am - 2 pm. [2022-754]
HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work eastbound from LM 7.52 to LM 7.48: Shoulder and single lane closures from Madison Street to Slayton Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums/cones, and flaggers will be present, 02/16/23 through 03/08/23 from 9 am – 2 pm. [2022-797]
HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work westbound at LM 1.44: Shoulder and single lane closures from Adair Avenue to Castleberry Avenue. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, drums/cones, and flaggers will be present, 02/27/23 through 03/01/23 from 9 am – 2 pm. [2023-092]
HAMILTON COUNTY SR-8 (US-127) construction near Palisades Road (LM 15.2) to near Sunset Drive (LM 15.4): The contractor has closed the right lane going up the Signal Mountain Road from LM 15 (about 1/2 Mi from Palisades Road) to past Sunset Drive. This closure will be in effect for several months during the duration of this project. There will be intermittent lane closures on Signal Mountain Road as the contractor will have flaggers out as they work. Due to the possibility of flaggers stopping traffic, traffic should be aware of possible delays in this area.
[Wright Brothers Construction Company, Inc./Curtis/CNW001]
MCMINN COUNTY SR-163 bridge repair over Chestuee Creek (LM 11.7): During this reporting period, the contractor will continue bridge repairs on the bridge over Chestuee Creek. Traffic on the bridge over Chestuee Creek on SR-163 at LM 11.74 will be reduced to a single lane controlled by a traffic signal. Maximum horizontal clearance will be limited to 11’. Wide load detour routes will be posted. Motorists are advised to reduce speed in the work zone. RESTRICTIONS: Horizontal clearance maximum 11’.
[Jamison Construction, LLC/Wagner/CNW282]
MCMINN COUNTY SR-2 (CONGRESS PKWY.) Utility Work westbound from LM 12.93 to LM 12.1: Mobile shoulder closure along SR-2 between the intersection of Congress Pkwy and Dennis Street and the intersection of Congress Pkwy and Rocky Mount Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 08/15/22 through 04/12/23 from 7:30 am – 5:00 pm. [2022-019]
MCMINN COUNTY SR-30 (LILLARD HWY.) Utility Work both directions from LM 16.5 to LM 16.61: Shoulder and single lane closures from Casey Gap Zion Hill Road to Foreman Branch Road to assist with an all stop at Blair Branch Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums/cones, and flaggers will be present, 03/01/23 from 9 am - 2 pm, with a rain date of 03/03/23. [2022-580]
MEIGS COUNTY SR-58 (STATE HWY. 58) Utility Work southbound from LM 14.22 to LM 9.35: Mobile shoulder and single lane closures from Goodfield Road to Cottonport Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 01/26/23 through 03/17/23 from 9 am – 2 pm. [2022-366]
RHEA COUNTY SR-302 (OLD DIXIE HWY.) Utility Work both directions from LM 0.01 to LM 2.5: Mobile shoulder and lane closures on SR-302 as crews transition work zones between SR-30 and Taylor Road. Motorists should reduce speed and be prepared to stop. Signage and flaggers will be present, 10/06/22 through 03/25/23 from 9 AM - 2:30 PM. [2022-643]
REGION WIDE
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed.
[NABCO Electric Company, Inc./Osbonlighter/CNT354]
REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.
[TDOT Operations/Maintenance/R2MAINT]
REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.
[TDOT Operations/Maintenance/R2MAINT]
REGION 2 TDOT mowing operations: There will be possible short-term lane closures at various locations on interstates and state routes in Region 2 in order to perform mowing activities on an as-needed basis. In addition to performing the work, regional Operations crews will also provide traffic control.
[TDOT/Maintenance/R2MAINT]
REGION 2 The drain cleaning on various Interstate and State Routes: During this reporting period from Sunday thru Thursday night from 8 PM-6 AM the contractor will have 1 lane closed on I75 from MM 2 - MM18 as they work to clean various drains in this area. If they get finished in this area, they will move to I24 and from MM184 - MM176 work to clean those drains.
[Blevins Enterprises, Inc./Curtis/CNW335]
REGION 2 The on-call concrete pavement repair on various interstates and state routes: During the daytime the contractor will be repairing concrete pavement at several ramp locations along SR-29 in Soddy Daisy in Hamilton County. First location: The on and off-ramps at SR-29 and SR-319. Half the width of the ramps will be closed during repairs leaving a 10-foot minimum lane width. Second location: The SR-29 SB exit to Thrasher Pike and the Thrasher Pike on-ramp to SR-29 SB. On Thursday 03/02/23 and Friday 03/03/23, from 8 AM - 4 PM, a single right lane closure will be setup near the SR-29 exit to Thrasher Pike and run just passed the Thrasher Pike on-ramp to SR-29 SB. Once concrete has been poured the lane closure will be picked up. Third location: The SR-29 exit to SR-153 SB. Half the width of the ramp will be closed during repairs leaving a 10-foot minimum lane width. Please slow down and use caution when driving through the work zones.
[Vulcan Construction Materials, LLC/Voiles/CNV341]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Cumberland Guardrail, Inc./Harris/CNW127]
REGION 2 The random on-call attenuator repair on various Interstate and State Routes: The contractor will be utilizing inside lane closures or shoulder closures during nonpeak travel times on SR-311/US-64 at LM 2.505 in Bradley County to make repairs to the damaged attenuator. Motorist should use caution in the area and watch for workers.
[Site-Safe, LLC/Harris/CNW120]
REGION 2 The random on-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will always remain open to traffic on the interstate during any work that is performed.
[Tennessee Guardrail, Inc./Harris/cnw283]
REGION 2 The sweeping on various Interstate and State Routes: There will be an area wide sweeping operation on selected regional state routes and interstates. This activity will be supported by a mobile lane closure. Hours of activity are Sunday through Thursday night between 8 PM and 6 AM during this reporting period.
[Blevins Enterprises, Inc./Curtis/CNW334]
RESTRICTIONS
MCMINN COUNTY - CNW282: Horizontal clearance maximum 11’.