Here is the weekly road construction report for District 29:
BRADLEY COUNTY I-75 resurfacing from north of SR-311 (US-74 / MM 21) to north of SR-60 (MM 25.5): During this reporting period, the contractor will have intermittent lane and shoulder closures from 7 PM to 6 AM to perform final cleanup work and to remove construction signs. Motorists are advised to reduce speed in the work zone.
[Talley Construction Company, Inc./Wagner/CNW045]
BRADLEY COUNTY SR-2 (US-11) resurfacing from Old Highway 11(LM 18.2) to near the Hiwassee River (LM 20.9): During this reporting period, the contractor will have daily lane closures on SR-2 (US-11) to perform resurfacing operations. These closures will be in place from 8 AM to 5:30 PM. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Wright Brothers Construction Company, Inc./Wagner/CNW158]
BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will be performing earthmoving operations, utility relocation and storm drainage installation. Motorists are advised to reduce speed in the work zone, watch for flaggers assisting with traffic control and for trucks entering/leaving the highway. Speed limit through work zone will be reduced from 45 MPH to 35 MPH.
[Summers-Taylor, Inc./Wagner/CNV130]
BRADLEY COUNTY SR-74 (OCOEE ST. N.E.) Utility Work northbound at LM 14.16: Shoulder and single lane closures from 6th Street NE and 8th Street NE. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums, and flaggers will be present, 09/22/22 through 10/21/22 from 9 am – 2 pm. [2022-331]
BRADLEY AND HAMILTON COUNTY SR-312 microsurfacing from the Hamilton County line (LM 0) to west of White Oak Road (LM 4.8), and SR-312 microsurfacing from east of SR-58 (LM 14.3) to the Bradley County line (LM 17.7): During this reporting period, there will be intermittent lane closures on SR312 as the contractor begins work on this project. Flaggers will be directing traffic as the work is occuring during the day with the possibility of pilot cars being used. Expect possible long delays as the flaggers stop traffic. If at all possible, seek alternative route.
[Asphalt Paving Systems, Inc./Curtis/CNW105]
HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. Chestnut Street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted. The US-27 NB On-Ramp at William St. has been closed and it will be closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US-27 on-ramp. On Friday night (September 30th) there will be a lane closure on I24 W MM 176-178 from 9 PM-3 AM and then will switch to I24 E and have a lane closure on I24 E at MM176-178 from 3 AM-10 AM Saturday morning to work on pouring the overhead sign footers, weather permitting. On Sunday night, October 2nd, from 9 PM-6 AM the contractor will close the right lane on I24 E from MM176-178 to remove barrier wall on the shoulder. On Monday October 3rd from 9 PM-6 AM, the contractor will close the left lane on I24 E from MM176-178 to remove the barrier walls in the median of I24. On Tuesday October 4th from 9 PM-6 AM, the contractor plans to close the left lane on I24 W from MM177-178 so they can remove the barrier wall in the median of I24.
[Wright Brothers Construction Company, Inc./Curtis/CNU011]
HAMILTON COUNTY I-24 TDOT Maintenance both directions from MM 181.6 to MM 184.8: Beginning Thursday 09/29/22 at 9 PM through Friday 09/30/22 at 4 AM, TDOT Maintenance forces will have right lane and ramp shoulder closures on I-24 in both directions to perform slope mowing operations between Moore Rd and Germantown Rd. Motorists are advised to reduce speed in the work zone.
HAMILTON COUNTY I-75 concrete repair from MM 6.6 to MM 12.8: During this reporting period, the contractor will be having lane closures in both directions on I-75 from 9 PM-6 AM. During these lane closures, the contractor might have to temporarily close some of the ramps so that they can work on the ramp.
[Summers-Taylor, Inc./Curtis/CNW046]
HAMILTON COUNTY SR-153 resurfacing from LM 3.5 to LM 3.7, including bridge expansion joint repair on the railroad overpass bridge (LM 3.6); SR-2 resurfacing on (US-11, US-64) from the NB interstate ramps (LM 20.6) to the Bradley County line (LM 24.4): During this reporting period, the contractor will be performing resurfacing operations between 7 PM and 6 AM. Also, starting 09/23/2022 there will be intermittent lane closures on SR-153, LM 3.6 to perform the bridge expansion joint repairs between 7 PM and 6 AM. Drivers are encouraged to be aware of safety personnel and construction vehicles entering and exiting the jobsite.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNW131]
HAMILTON COUNTY SR-17 resurfacing from the Georgia state line (LM 0) to SR-2 (US-11, US-64, US-72, LM 2.2): During this reporting period, the contractor will have intermittent lane closures as they start working on this project.
[Talley Construction Company, Inc./Curtis/CNW213]
HAMILTON COUNTY SR-29 (US-27) slide repair between LM 29 and LM 30: During this reporting period, TDOT Maintenance and contract forces will have traffic reduced to one lane in each direction on US-27 (SR-29) to continue work on a new retaining wall and slope stabilization. Motorists are advised to reduce speed in the work zone.
[GeoStabilization International, LLC /Maint - Chattanooga/MAINT]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 09/29/22, 09/30/22, 10/03/22, 10/04/22, and 10/05/22 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. A portion of Tucker Road has been closed from Spalding Drive to 5400 Tucker Road to allow for grading and utility operations. A portion of Chestnut Creek Road has been shifted to its new alignment to allow for grading and utility operations.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-317 (BONNY OAKS DR.) Utility Work westbound from LM 4.55 to LM 4.54: Shoulder and single lane closures from Lee Hwy and Silverdale Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums, and flaggers will be present, 09/22/22 through 10/21/22 from 9 am – 2 pm. [2022-475]
HAMILTON COUNTY SR-58 slide repair near LM 17: During this reporting period, the contractor will have SR-58 North at LM 17 reduced to one lane for the duration of the project as the contractor begin work.
[Talley Construction Company, Inc./Curtis/CNW199]
HAMILTON COUNTY SR-8 (CHEROKEE BLVD.) Utility Work southbound from LM 10.48 to LM 10.43: Shoulder and single lane closures from W. Manning Street and Minor Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums, and flaggers will be present, 09/28/22 through 09/30/22 from 9 am – 3 pm, with a rain date of 10/05/22. [2022-116]
HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work eastbound from LM 1.29 to LM .8: Mobile shoulder and lane closures on Ringgold Road as crews transition work zones between Mack Smith Road and Camp Jordan Parkway. This will also impact the Northbound and Southbound on ramps to I-75. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 09/13/22 through 10/05/22 from 9 AM - 2 PM. [2019-578]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be performing operations at the intersection connecting the S.I.A. route, Ferdinand Piech Way, & Volkswagen Dr. The new 4-way signalized intersection has begun operation & traffic has been shifted to the new alignment. Ferdinand Piech Way will still be closed to through traffic. Drivers should be cautious of the new traffic pattern in effect including a lowered speed limit. Drivers should also be alert to the entrance and exit of construction vehicles & staff on and around the jobsite and the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]
MCMINN COUNTY SR-163 resurfacing from near SR-2 (US-11 / LM 2.5) to west of County Road 750 (LM 8.9): During this reporting period, the contractor will have daily lane closures from 7 AM to 7 PM to perform roadway striping and guardrail repair. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Wright Brothers Construction Company, Inc./Wagner/CNW112]
MCMINN COUNTY SR-2 (CONGRESS PKWY.) Utility Work westbound from LM 12.93 to LM 12.1: Mobile shoulder closure along SR-2 between the intersection of Congress Pkwy and Dennis Street and the intersection of Congress Pkwy and Rocky Mount Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 08/15/22 through 04/12/23 from 7:30 am – 5:00 pm. [2022-019]
POLK COUNTY SR-33 (US-411) resurfacing from the Georgia state line (LM 0.0) to south of Lowery Road (LM 9.3): During this reporting period, daily lane closures will be in place from 8 AM to 5:30 PM starting Tuesday 09/20/22 as the contractor continues resurfacing operations. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Talley Construction Company, Inc./Wagner/CNW188]
POLK COUNTY SR-40 (US-64) bridge over the Ocoee River: On Thursday 09/29/22 from 8 AM to 5:30 PM the contractor will have lane closures in place on US-64 (SR-40) to perform repair to the shoulder of the roadway. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Charles Blalock and Sons, Inc./Wagner/DB1802]