Weekly Road Construction Report

Thursday, November 21, 2019

Here is the weekly road construction report for Hamilton County:

I-75 at I-24 Interchange Reconstruction: Phase 1 traffic shifts have been implemented. Traffic should expect multiple lane shifts when traveling through the interchange. Lane closures will occur Sunday nights through Thursdays night between 9 p.m.-6 a.m. at the following locations: I-75 NB at state line, I-75 NB MM 2, I-75 SB MM 3, I-75 SB MM 1, I-24 EB MM 185, and I-24 WB MM 185. Traffic pacing will also occur for I-75 NB and I-75 SB. Additionally, shoulders may be closed at various locations between 9 a.m.-3 p.m. for access to the median and roadside areas. The speed limit has been reduced to 45 MPH throughout the interchange. HOLIDAY RESTRICTIONS: Closures/Traffic pacing will not occur from Wednesday before Thanksgiving through Sunday following Thanksgiving. [C.W. Matthews Contracting Company, Inc./Blevins/DB1801]

US-27 (I-124) Widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues with activities occurring on the west side of southbound US-27. Motorists should be alert for construction vehicles entering and exiting the area along the access ramps for eastbound and westbound M. L. King Boulevard. The speed limit for the access ramp is 35 MPH. In addition, the southbound ramp from W. Main St.to southbound US-27 has been temporarily closed and will remain so until further notice. Detours are posted. Motorists should pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting; the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. RESTRICTIONS: I-124 (US-27)Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27)Southbound Exit 1C 4th St Of Ramp: On oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1A-B Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads. [Dement Construction Company, LLC/Micka/CNP230]

Utility Work on SR-2 (Brainerd Road) in both directions from LM 13.8 to LM 15.3: Arrow boards, signage and flaggers will be present on Brainerd Road/Lee Highway between Moore Road and East Brainerd Road for utility work. Both eastbound and westbound lanes will be affected nightly, 8 p.m.-6 a.m. from Thursday through Tuesday.

Utility Work on SR-2 (Cummins Highway) westbound from LM 2.6 to LM 2.6: A single lane closure will occur westbound between Myrtle Ave and Hemlock Circle. Signage and cones will be present. Motorists should use caution through the area, be aware of personnel and equipment from 9 a.m.-2 p.m. with an estimated completion date of Tuesday.

Utility Work on SR-319 (Dupont Parkway) southbound from LM 1.9 to LM 2.4: A night time southbound lane closure will occur along Dupont Parkway/CB Robinson Bridge. Arrow boards, signage and barrels will be present. Motorists should reduce speed and use caution through the area. Work will take place between 9 p.m.-6 a.m. with an estimated completion date of Sunday.

Utility Work on SR-8 (Cherokee Boulevard)in  both directions from LM 10.4 to LM 10.6: Single lane closures of northbound and southbound lanes will occur between Minor St and Spring St. Arrow boards, barrels and signage will be present. Motorists should seek alternate route for West Manning St/Harper St. Work will take place between 9 a.m.-2 p.m. with an estimated completion date of Tuesday. 

Cleaning of the McCallie Tunnel on SR-2 (US-64, US-11), the Stringers Ridge Tunnel on SR-8 (US-127), and the Bachman Tubes on SR-8 (US-76, US-41): On Thursday from 8 p.m.-6 a.m. the Bachman tubes (East Ridge tunnels)will be cleaned under a signed detour traffic control. Estimated project completion date is June 2020. [Diamond Specialized, Inc./Micka/CNT196]

SR-153 Resurfacing from north of Shallowford Road (LM 2.6) to north of SR-58 (LM 4.8), including bridge deck repair: No lane closures scheduled this period. Job awaiting final inspection. Estimated project completion date is November. [Wright Brothers Construction Company, Inc./Micka/CNT087]



Fashionetta 2019 Will Be Dec. 14

Christmas At The Courthouse School Performances Continue Next Week

CDOT Announces Events And Road Closures For Dec. 7-8


The Ivy Rose Foundation, Inc. and the Pi Omega Chapter of Alpha Kappa Alpha Sorority, Inc.’s triennial production of Fashionetta will be held Saturday, Dec. 14, at the Chattanooga Convention ... (click for more)

The annual Christmas at the Courthouse concert series showcase will continue next week with student ensembles from 11 more Hamilton County Schools set to perform. “This decades-old tradition ... (click for more)

Chattanooga Department of Transportation announces the following events and road closures for Dec. 7-8: MainX24 MainX24 Parade - East and West Main Street between Stayton Street and ... (click for more)


Happenings

Fashionetta 2019 Will Be Dec. 14

The Ivy Rose Foundation, Inc. and the Pi Omega Chapter of Alpha Kappa Alpha Sorority, Inc.’s triennial production of Fashionetta will be held Saturday, Dec. 14, at the Chattanooga Convention Center at 6 p.m. This year’s theme is “Fashionetta 2019 – A Dream Comes True.” Fashionetta is a traditional expansion program of Alpha Kappa Alpha Sorority, Inc. that was conceived in ... (click for more)

Christmas At The Courthouse School Performances Continue Next Week

The annual Christmas at the Courthouse concert series showcase will continue next week with student ensembles from 11 more Hamilton County Schools set to perform. “This decades-old tradition for Hamilton County Government recognizes public servants and elected officials with sounds of the season provided by students from elementary, middle, and high schools in Hamilton County ... (click for more)

Breaking News

Chattanooga Man Charged With Killing Huntsville Police Officer

A Chattanooga man has been charged with killing a Huntsville Police officer on Friday night. LaJeromeny Brown, 41, is facing a capital murder charge.was arrested Friday night. Police had set up a drug buy at a house on Levert Street. Police said Brown immediately shot Billy Clardy III. He was struck outside his bulletproof vest. Brown tried to flee, but was soon captured. ... (click for more)

Woman Dies From Injuries Sustained In Wreck Last Tuesday At Frazier Avenue And River Street

A woman has died from injuries sustained last Tuesday in a wreck at Frazier Avenue and River Street. The victim was Glenda Harris, 61. At approximately 5:55 a.m., the Chattanooga Police Department's Traffic Unit responded to 400 Frazier Ave. on the single-vehicle traffic crash. The Dodge Ram 1500 driven by Ms. Harris was traveling east on Frazier Avenue. It merged onto ... (click for more)

Opinion

A Better Plan Is Needed For Quarry Golf Course At Mountain Creek

With regard to the ongoing saga of the old Quarry golf course and its proposed development, I reject the proposed plan endorsed by the North Chickamauga Creek Conservancy (Chattanoogan - Breaking News 11/30/2019) and believe a better outcome can be achieved. There is a middle ground that involves all R-1 construction including preserving the tree, greenspace, streams and ponds. ... (click for more)

Roy Exum: The Saturday Funnies

Hot dog for every December and here we go! We at The Saturday Funnies relish in each December because it is during this time many of the best stories are borne. From Thanksgiving to Christmas each year is a “busy street” and over these holidays, which we dutifully celebrate because of a very real and ever-revealing Christ-child, and not just from the teacher’s advancement, we will ... (click for more)